Specialty Tires of America, Inc. v. CIT Group/Equipment Financing, Inc.

82 F. Supp. 2d 434, 2000 WL 133435
CourtDistrict Court, W.D. Pennsylvania
DecidedMarch 1, 2000
DocketC.A. 98-982
StatusPublished
Cited by7 cases

This text of 82 F. Supp. 2d 434 (Specialty Tires of America, Inc. v. CIT Group/Equipment Financing, Inc.) is published on Counsel Stack Legal Research, covering District Court, W.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Specialty Tires of America, Inc. v. CIT Group/Equipment Financing, Inc., 82 F. Supp. 2d 434, 2000 WL 133435 (W.D. Pa. 2000).

Opinion

MEMORANDUM OPINION and ORDER

D. BROOKS SMITH, District Judge.

In this case, Specialty Tires, Inc. (“Specialty”) has sued The CIT Group/ Equipment Financing, Inc. (“CIT”) for breach of contract arising out CIT’s failure to deliver eleven tire presses that it had previously contracted to sell to Specialty. CIT, in turn, has filed a third-party complaint against Condere Corporation, Titan Tire Corporation and Titan International, Inc. (collectively “Condere”) arising out of the latter’s alleged wrongful refusal to permit those presses to be removed from its factory. Specialty has moved for partial summary judgment, dkt. no. 39, arguing that CIT’s defenses are without merit, while CIT has moved for full summary judgment on the ground that its performance was excused under the doctrine of impossibility or commercial impracticability, 1 dkt. no. 42. CIT has also moved, in the alternative, to dismiss the stay I previously entered in the third-party action, dkt. no. 45. For the following reasons, I will grant CIT’s motion based on impossibility and deny the other two motions as moot.

I.

The material facts of this case are simple and undisputed. In December 1993, CIT, a major equipment leasing company, entered into a sale/leaseback with Condere for eleven tire presses located at Con-dere’s tire plant in Natchez, Mississippi, under which CIT purchased the presses from Condere and leased them back to it for a term of years. CIT retained title to the presses, as well as the right to possession in the event of a default by Condere. In May 1997, Condere ceased making the required lease payments and filed for Chapter 11 bankruptcy in the Southern District of Mississippi. 2 In September 1997, Condere rejected the executory portion of the lease agreement, and the bankruptcy court lifted the automatic stay as to CIT’s claim involving the presses.

CIT thus found itself, unexpectedly, with eleven tire presses it needed to sell. Maurice “Maury” Taylor, a former minor candidate for President of the United States 3 and the CEO of Condere and Titan International, stated his desire that the presses be removed quickly and advised CIT on how they might be sold. Later, CIT brought two potential buyers to Condere’s Natchez plant, where representatives of Condere conducted them on a tour of the facility. Subsequently, Taylor and CIT negotiated concerning Condere’s purchase of the presses, but negotiations fell through, after which Taylor again offered his assistance in locating another buyer.

When no buyer was found, CIT decided to advertise the presses. Specialty, a manufacturer of tires which sought to expand its plant in Tennessee, responded, and in early December 1997, representatives of Specialty, CIT and Condere met to conduct an on-site inspection of the equipment. Condere’s representative discussed with CIT’s personnel and in the presence of Specialty’s agents the logistics concerning the removal of the presses. At that meeting, Condere’s representative told CIT and Specialty that CIT had an immediate right to possession of the tire presses, and the right to sell them. At no time did any representative of Condere, whether by words or conduct, express any intent to oppose the removal of this equipment. *436 CIT Group/Equipment Financing, Inc. v. Condere Corp., typescript at 8-9, No. 5:98cv5BrS (S.D.Miss. Jan. 27, 2000). 4 The negotiations proved fruitful, and, in late December 1997, CIT and Specialty entered into a contract for the sale of the presses for $250,000. CIT warranted its title to and right to sell the presses.

Events then took a turn which led to this lawsuit. When CIT attempted to gain access to the presses to have them rigged and shipped to Specialty, Condere refused to allow this equipment to be removed from the plant. This refusal was apparently because Condere had just tendered a check to CIT for $224,000, without the approval of the bankruptcy court, in an attempt to cure its default under the lease. See Condere Corp., typescript at 3, 9. This unexpected change in position was rejected by CIT, which promptly filed a complaint in replevin in the Southern District of Mississippi to obtain possession. 5 Condere then posted a bond and the replevin court removed the action from the expedited list, scheduling a case management conference for April 1998. It became clear at that juncture that Specialty was not going to obtain its tire presses expeditiously.

CIT then advised Specialty that the presses were subject to the jurisdiction of the bankruptcy court and suggested that Specialty either withdraw its claim to the equipment and negotiate with CIT for a sum of liquidated damages or make a bid for the presses at any auction that might be held by that court. Specialty, as was its right, rejected both suggestions and affirmed the existing contract, demanding performance. To date, Condere has refused to surrender to CIT, and CIT has failed to deliver to Specialty, the tire presses.

Subsequent to the briefing of these motions, the replevin court has issued findings of fact and conclusions of law to the effect that Condere wrongfully retained possession of the presses and that CIT is entitled to remove them immediately. Condere Corp., typescript at 17. Although Condere may appeal this ruling, CIT has informed Specialty that it is still willing to deliver the presses as soon as it gains possession, and Specialty has indicated its interest in accepting them, in “partial” settlement of its claims.

II.

Summary judgment is appropriate where admissible evidence fails to demonstrate a genuine issue of material fact and the moving party is entitled to judgment as a matter of law. Fed.R.Civ.P. 56(c). If the nonmoving party bears the burden of persuasion at trial, the moving party must show that the nonmoving party’s evidence is insufficient to carry that burden. Celotex Corp. v. Catrett, 477 U.S. 317, 322-23, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986). The nonmoving party can create a genuine issue of material fact by pointing to evidence in the record sufficient to support a jury verdict in its favor at trial. Brewer v. Quaker State Oil Refining Corp., 72 F.3d 326, 330 (3d Cir.1995). Alternatively, “the burden on the moving party may be discharged by showing ... that there is an absence of evidence to support the non-moving party’s case.” Celotex, 477 U.S. at 325, 106 S.Ct. 2548 (internal quotation marks omitted). “[Sjince a complete failure of proof concerning an essential element,” id. at 323-24, 106 S.Ct. 2548, on which a party bears the burden of proof at trial establishes that the moving party is “entitled to a judgment as a matter of law,” the nonmoving party must establish the existence of every element essential to its case. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
82 F. Supp. 2d 434, 2000 WL 133435, Counsel Stack Legal Research, https://law.counselstack.com/opinion/specialty-tires-of-america-inc-v-cit-groupequipment-financing-inc-pawd-2000.