Space Center, Inc. v. 451 CORP.

298 N.W.2d 443, 13 A.L.R. 4th 912, 1980 Minn. LEXIS 1604
CourtSupreme Court of Minnesota
DecidedOctober 17, 1980
Docket50281
StatusPublished
Cited by31 cases

This text of 298 N.W.2d 443 (Space Center, Inc. v. 451 CORP.) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Space Center, Inc. v. 451 CORP., 298 N.W.2d 443, 13 A.L.R. 4th 912, 1980 Minn. LEXIS 1604 (Mich. 1980).

Opinion

OTIS, Justice.

Space Center, Inc. brought an action for damages against 451 Corporation, Arthur G. Mueller, and Oliver N. Dyste for breach and anticipatory breach of an option contract and a purchase agreement under which Space Center was to acquire title to certain warehouse and office properties in Minneapolis. The jury returned a verdict in favor of Space Center. The trial court vacated the jury verdict and entered judgment against Space Center on defendants’ counter-claim for unpaid rent. Space Center appeals claiming the trial court incorrectly interpreted the contract. We reverse.

The essential facts are not in dispute. Arthur G. Mueller, a defendant, and his original business associate, Douglas H. Peterson, were developers of an office-warehouse project on a seventeen-acre tract in the Mid-City Industrial Park in Minneapolis. In mid-1972 defendant Oliver N. Dyste left his employment with Heitman Mortgage Company and bought out Peterson so that he (Dyste) and Mueller could complete the development of property in question.

Mueller and Dyste formed 451 Corporation in which they were equal shareholders. 451 Corporation took title to the project and assumed the obligations of the Commanche Corporation (successor to the Douglas H. Peterson Company) under the construction loan. Mueller and Dyste personally guaranteed the loan. Commanche Corporation was dissolved.

Mueller and Dyste formed 451 Corporation, rather than a partnership, in order to avoid usury law limits on interest rates that could be charged to partnerships. However, Dyste and Mueller wanted to take the tax benefits of depreciation and interest deductions against their individual incomes. To that end they formed a partnership called 451 Company which held an unrecorded contract for deed to the 451 property under which 451 Company could demand conveyance of legal title from 451 Corporation. 451 Corporation contracted with 451 Company for 451 Company to manage the property. Under the agreement, 451 Company, the partnership, paid al 1 expenses and received all of the income from the property. None of the partnership arrangements was disclosed to Space Center until discovery proceedings attendant to this lawsuit.

The project was financed by a temporary construction loan from Heitman Mortgage Company. The loan was secured by a mortgage on the property. Because Mueller and Dyste were unable to obtain permanent financing by the time the construction loan came due, Heitman formally extended the maturity date on the mortgage three times. First, it was extended to January 31, 1973, then to May 31, 1973, and finally to March 31, 1974. ■ The first two extensions were recorded, but the third was not. After March 31, 1974, Heitman agreed not to foreclose for some unspecified period provided the interest was paid monthly.

The property had been certified for occupancy in April 1972, but no major tenant was found until Space Center expressed an interest in purchasing the property in late 1972. On April 5, 1973, 451 Corporation and Space Center signed a letter of intent which outlined the basic terms of their agreement under which Space Center agreed to lease some of the property for five years with an option to purchase the property at the end of the lease period for *447 $3,400,000. The lease was executed on April 16, 1973, and was amended to cover most of the building on August 26, 1974. (The provisions relevant to this suit were not changed.) The lease was to expire on April 15,1978, with monthly installments of rent of $27,491.83 ($329,902.00 annual rent). Space Center also agreed to pay, as additional rent, all real estate taxes and assessments apportionable to the percentage of the premises it leased.

The option contract was not signed by 451 Corporation until April 1974. The purchase agreement at issue in this case was attached to and was part of the option agreement. Under the option and purchase agreement 451 Corporation agreed to convey marketable title to Space Center for $3,400,000 if Space Center exercised its option on or before July 1, 1977. The agreement also provided that, within a reasonable time after Space Center executed and delivered the purchase agreement, 451 Corporation would furnish Space Center with an abstract of title or registered property abstract. Space Center was then allowed ten days to examine title and note any objections to it. 451 Corporation was, in turn, “allowed 120 days from the date of written objections thereto * * * to make such title marketable.” The agreement provided that if the title “is not marketable and is not made so within [the] 120 days * * *, this agreement shall be null and void.”

Defendants paid some of the interest, on the Heitman loan, monthly through August 1974. By September 1974, approximately $100,000 unpaid interest had accrued. Heit-man informed defendants that it would no longer extend the loan and that the full amount of principal and interest was due on October 31, 1974. Defendants were unable to pay Heitman because their efforts to obtain long-term financing during 1973 and 1974 were unsuccessful and because they did not have $3,100,000 cash. Heitman foreclosed in November 1974.

451 Corporation defended the foreclosure action so that trial was delayed until October 1975. Judgment was entered against 451 Corporation, Mueller, and Dyste for $3,570,260.60.

The foreclosure sale was held on January 28, 1976. Although Space Center was present, the only bidder was Heitman which initially bid $3,400,000. Upon protest by respondents’ attorneys, that the bid was inadequate, Heitman raised its bid to $3,615,089.69 representing the full amount of the debt to that date. Thus, respondents were relieved of the burden of a deficiency judgment which would have otherwise remained. The higher bid also meant a higher redemption price for Space Center had it chosen to redeem. Defendants did not redeem; after the redemption period expired on January 31, 1977, they lost all rights in the property.

Defendants also did not pay the real estate taxes for the second-half of 1974 and for all of 1976. The 1974 tax was not paid, even though each tenant had paid its proportionate share of the taxes to 451 Corporation.

For each 1976 tax assessment Space Center tendered a check, payable to 451 Corporation and Hennepin County, jointly, for its portion of the tax. The check was refused by 451 Corporation, and Space Center paid the whole amount of the taxes directly to Hennepin County.

Space Center offered to buy the property repeatedly from 1974 through 1976. At least one proposal was rejected even before a specific price was mentioned. At another meeting, after the foreclosure proceedings were initiated, Space Center offered to satisfy the Heitman loan in full, which by that time was more than the option price, and to pay defendants an additional sum to be negotiated. This offer was also refused.

Space Center filed this action on February 6, 1976, a week after the foreclosure sale and within the redemption period, alleging that 451 Corporation had anticipa-torily breached the option contract. In defendants’ answer to the complaint, defendants alleged non-exercise of the option. Space Center then exercised the option on April 2, 1976, by signing the purchase agreement and delivering it and the $5,000 *448 earnest money to 451 Corporation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chase Rovere v. Clifford Ling
Court of Appeals of Minnesota, 2024
Mono Adver., LLC v. Vera Bradley Designs, Inc.
285 F. Supp. 3d 1087 (D. Maine, 2018)
Casimir Robert Krithers v. State of Minnesota
Court of Appeals of Minnesota, 2016
Victor Legatt v. Dennis Legatt
Court of Appeals of Minnesota, 2015
State Ex Rel. Friends of the Riverfront v. City of Minneapolis
751 N.W.2d 586 (Court of Appeals of Minnesota, 2008)
Slidell, Inc. v. Millennium Inorganic Chemicals, Inc.
460 F.3d 1047 (Eighth Circuit, 2006)
Schwickert, Inc. v. Winnebago Seniors, Ltd.
680 N.W.2d 79 (Supreme Court of Minnesota, 2004)
Home Insurance Co. v. National Union Fire Insurance of Pittsburgh
658 N.W.2d 522 (Supreme Court of Minnesota, 2003)
Carlson Real Estate Co. v. Soltan
549 N.W.2d 376 (Court of Appeals of Minnesota, 1996)
In Re Hennepin County 1986 Recycling Bond Litigation
540 N.W.2d 494 (Supreme Court of Minnesota, 1995)
Petroskey v. Lommen, Nelson, Cole & Stageberg, P.A.
847 F. Supp. 1437 (D. Minnesota, 1994)
Murphy Oil USA, Inc. v. Brooks Hauser
820 F. Supp. 437 (D. Minnesota, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
298 N.W.2d 443, 13 A.L.R. 4th 912, 1980 Minn. LEXIS 1604, Counsel Stack Legal Research, https://law.counselstack.com/opinion/space-center-inc-v-451-corp-minn-1980.