Southwestern Bell Telephone Co. v. Beachner Construction Co.

221 P.3d 588, 289 Kan. 1262, 2009 Kan. LEXIS 1190
CourtSupreme Court of Kansas
DecidedDecember 11, 2009
Docket101,153
StatusPublished
Cited by24 cases

This text of 221 P.3d 588 (Southwestern Bell Telephone Co. v. Beachner Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southwestern Bell Telephone Co. v. Beachner Construction Co., 221 P.3d 588, 289 Kan. 1262, 2009 Kan. LEXIS 1190 (kan 2009).

Opinion

The opinion of the court was delivered by

Nuss, ].:

This is a property damage case arising out of a public improvements project in Frontenac, Kansas. Southwestern Bell Telephone Company d/b/a AT&T Kansas (SBT) obtained judgment against Beachner Construction Company, Inc. (Beachner) for damages negligently caused to an SBT underground telephone cable which SBT had relocated at the city’s request to accommodate Beachner’s project construction. We transferred Beachner’s appeal to this court pursuant to K.S.A. 20-3018(c).

The issue on appeal, and this court’s holding, is as follows:

Did the district court err in holding that SBT’s only duty was to relocate the cable “to avoid any conflicts” with Beachner’s completed construction? Yes.

Accordingly, we reverse the district court and remand.

Facts

The Kansas Department of Transportation (KDOT) submitted to interested contractors the specifications for a project involving McKay Street in Frontenac, Kansas. Defendant Beachner Construction Company, Inc., (Beachner) submitted a bid price in reliance upon the plans and specifications and was awarded the contract. The project required Beachner to tear out and widen McKay Street, to install a storm sewer, new curb, gutter, and inlets, and then to repave the street. KDOT and Beachner ultimately signed a contract for the project.

The KDOT construction plans required the storm sewer to be installed at specified underground locations at a depth of 4 feet 11 inches sloping downward to 5 feet 1 inch for drainage. According to Beachner, the construction plans required the actual depth of the sewer to deviate no more than 2 inches from the depth provided in the plans.

SBT had an underground telephone cable located in the same public right-of-way where the sewer was to be trenched and laid. Prior to construction, KDOT notified SBT of the upcoming project *1264 and instructed SBT to move the cable in accordance with the project plans and specifications. SBT was provided a copy of the plans.

David Ghram was in charge of the cable relocation for SBT. He testified on cross-examination about his understanding of the relocation standards:

[ATTORNEY]: Okay. And basically what they [KDOT] indicate to you is Southwestern Bell, here are die plans and specifications, you move your line to comply widi ensuring that you don’t violate those plans and specifications, isn’t Üiat die requirements?
“[GHRAM]: That sounds correct.
“[ATTORNEY]: Okay. And if tiiey say we are putting a storm sewer in and these are — and this is die location, tiiis is the depdi, we want you to move your fines so it doesn’t interfere with that, isn’t tiiat, in fact, what they indicate to you or to your engineers?
“[GHRAM]: That would be correct.
“[ATTORNEY]: Okay. And your engineers, based on KDOT’s plans and specifications for die project on your behalf, diey being your agent, draw up plans and specifications for Southwestern Bell on what they drink should be done?
"[GHRAM]: That would be correct.
“[ATTORNEY]: Okay. So it is not — these plans are not KDOT’s plans, it is the plans diat your agent has done for you on what they think they should do?
“[GHRAM]: That is correct.”

Ghram testified that he was able to point out the location of the proposed sewer line on the plans drawn up by SBT’s engineers for the cable relocation. He further testified that based upon KDOT specifications and SBT’s resultant engineering plan, the SBT cable was to be relocated at a minimum depth of 36 inches, unless otherwise noted. SBT’s engineers and its contractor, Radell Construction Company, relocated the cable outside of the public right-of-way and the area where the sewer line was to be built, except for two locations.

First, the cable remained within the public right-of-way at the eastern location but was lowered to a depth of 10 feet in accordance with SBT’s engineering plans. This depth was approximately 5 to 6 feet below Beachner’s subsequent trench and was not damaged by Beachner during construction. When Ghram was effectively asked whether SBT engineers could only avoid the storm sewer at *1265 this eastern location by drafting plans to bury the cable at 10 feet, he replied, “That sounds correct.”

Second, at the western location, SBT abandoned an older portion of cable and instead installed new cable. While SBT was able to place the majority of the new cable outside the right-of-way, a 30-foot “jog” of cable was simply relocated within the right-of-way, at a depth of 3 feet, to avoid conflict with an adjacent private landowner s circle drive. A portion of this jog was the part damaged during construction by Beachner.

KDOT held a preconstruction conference between state and city officials involved in the project, and utility companies were invited to attend. The purpose of the conference was to discuss issues involved with the project, including traffic concerns and utility conflicts. When Radell Construction Company attended the preconstruction conference on SBT’s behalf, its cable relocation for SBT was already complete.

Before Beachner began construction, it called the Kansas One Call notification center pursuant to K.S.A. 66-1801 et seq. SBT was notified of the call. Both parties agree that SBT then accurately marked with orange paint the “tolerance zone” of its cable at the east and west locations where Beachner would be operating. The tolerance zone is a lateral marking of a 24-inch area in all directions from where the cable is located underground. K.S.A. 66-1802(p). The marking does not provide information regarding the depth of the cable.

Ron Vyhlidal (Vyhlidal), Beachner’s construction foreman on the project, saw the SBT tolerance zone markings at the east and west locations. He testified he knew that Beachner would be digging within both zones during construction, i.e., according to the plans, the cable was in the area where the sewer trench was to be dug and the line was to be laid. Prior to any digging, Vyhlidal asked SBT’s Ghram about the depth of SBT’s cable at the east location. Ghram replied that the cable at the east location was 9 or 10 feet deep. Vyhlidal did not ask Ghram about the depth of SBT’s cable at the west end of the project. After receiving this information, Beachner began sewer line construction at tire east end of the *1266 project and progressed west. Beachner excavated 7 feet deep in SBT’s eastern tolerance zone and did not encounter the cable.

When Beachner reached the west end tolerance zone, Vyhlidal knew that the SBT cable was underneath the paint marking and that the construction project would cross the cable.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Odom
Court of Appeals of Kansas, 2026
State v. Evans
Supreme Court of Kansas, 2026
R.P. v. First Student, Inc.
515 P.3d 283 (Court of Appeals of Kansas, 2022)
Russell v. Kansas Dept. of Revenue
Court of Appeals of Kansas, 2022
Huffman v. Meier's Ready Mix
Court of Appeals of Kansas, 2021
– State v. Smith –
456 P.3d 1004 (Supreme Court of Kansas, 2020)
Biglow v. Eidenberg
424 P.3d 515 (Supreme Court of Kansas, 2018)
State v. Pollard
Supreme Court of Kansas, 2017
Lee v. State
Court of Appeals of Kansas, 2016
State v. Murdock
Court of Appeals of Kansas, 2016
In Re the Guardianship & Conservatorship of Burrell
367 P.3d 318 (Court of Appeals of Kansas, 2016)
In Re the Estate of Strader
339 P.3d 769 (Supreme Court of Kansas, 2014)
Fisher v. DeCarvalho
314 P.3d 214 (Supreme Court of Kansas, 2013)
Northern Natural Gas Co. v. ONEOK Field Services Co.
296 P.3d 1106 (Supreme Court of Kansas, 2013)
Friedman v. Kansas State Board of Healing Arts
294 P.3d 287 (Supreme Court of Kansas, 2013)
Kansas One-Call System, Inc. v. State
274 P.3d 625 (Supreme Court of Kansas, 2012)
Manhattan Ice & Cold Storage, Inc. v. City of Manhattan
274 P.3d 609 (Supreme Court of Kansas, 2012)
Holmes v. State
252 P.3d 573 (Supreme Court of Kansas, 2011)
LOUISBURG BLDG. & DEV'T CO. v. Albright
252 P.3d 597 (Court of Appeals of Kansas, 2011)
Osterhaus v. Schunk
249 P.3d 888 (Supreme Court of Kansas, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
221 P.3d 588, 289 Kan. 1262, 2009 Kan. LEXIS 1190, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southwestern-bell-telephone-co-v-beachner-construction-co-kan-2009.