Southern Union Gas Company v. Federal Energy Regulatory Commission

725 F.2d 99, 1984 U.S. App. LEXIS 26400
CourtCourt of Appeals for the Tenth Circuit
DecidedJanuary 16, 1984
Docket81-2032, 81-2164
StatusPublished
Cited by4 cases

This text of 725 F.2d 99 (Southern Union Gas Company v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern Union Gas Company v. Federal Energy Regulatory Commission, 725 F.2d 99, 1984 U.S. App. LEXIS 26400 (10th Cir. 1984).

Opinions

SETH, Chief Judge.

The principal supplier of natural gas to Southern Union, which was a distributor in the Oklahoma panhandle, was Western Gas Interstate (a wholly owned subsidiary of Southern Union). Additional gas was supplied by local producers, by Cities Service Gas Company, and by Northern Natural Gas Company. The purchases from Cities were under Rate Schedule IRG-1 of Cities’ FERC tariff and from Northern under its X-46. Southern Union was not a certificate holder.

In 1973 Southern Union encountered shortages in gas for its local users, and Western had trouble moving gas through sections of its lines for Southern Union’s distribution to Beaver, Oklahoma. It appeared that as a result it might be necessary for Southern Union to cut off deliveries to its high priority customers in Beaver, a community of about 1,800 people. These were residential, commercial and irrigation customers.

The matter became critical and the local managers of Southern Union in the Oklahoma panhandle took it upon themselves to provide more gas to Beaver. This involved changes in the facilities for delivery of gas from Cities at what was known as the Adams Tap. This tap was to serve the Adams Irrigation System and gas was supplied there to Southern Union under the Rate Schedule IRG-1 referred to above. It was gas for irrigation pumps. This change -was actually of interstate facilities at that point. A meter inspector of Cities was present when the change in the delivery facilities was made to increase delivery to Southern Union. Cities’ management was aware [101]*101shortly thereafter as was Southern Union. The two then began negotiations to amend the existing contract (IRG-1) covering delivery at this point. The amendments were not accomplished and Cities continued to deliver under the old irrigation agreement. Southern Union distributed this added gas to its Beaver customers.

The local supervisors of Southern Union, as mentioned, did not advise their superiors before the change had been accomplished at the Adams Tap. The change was a violation of the Natural Gas Act as no prior authorization was obtained. Thereafter Southern Union filed with the Commission an application under 7(a) to have Cities deliver quantities of gas to Southern Union at the Adams Tap to regularize what was taking place. The Commission during the hearings and extended consideration of the case, issued a temporary authorization necessary for transportation of the gas to the Beaver distribution system.

The record demonstrates that the increased amount of gas delivered by Cities under the change at the Adams Tap was very small in comparison to the large volumes transported by Cities. It was an amount which was too small to be taken into consideration by Cities in the dispatchers’ estimates. The testimony was that on a peak day during the shortages the total volume delivered for Southern Union at the Adams Tap was .12421 of one percent of Cities’ volumes on such a day.

The Commission found that Southern Union’s taking of gas at the Adams Tap for Beaver without prior Commission approval was a violation of the Natural Gas Act. The Commission referred the matter to the Department of Justice (without a recommendation). The Department advised the Commission that it would not institute any criminal proceedings. Such a reference is contemplated by the Act and appears to be the only remedy therein expressly provided.

In another attempt to meet the gas shortage for the priority users of the Beaver distribution system, Southern Union built a three and one-half mile connection between that system and its small irrigation distribution facilities known as the Balko Irrigation System. Balko was supplied by Northern Natural Gas Company. This connection was considered by Southern Union as part of its intrastate distribution, thus not within the Natural Gas Act (15 U.S.C. § 717(b)). No authority was sought from the Commission to build it. It also considered that it was taking this extra gas from Northern under the X-A6 Rate Schedule which was in effect between them. Northern delivered under this schedule for the entire period. If deliveries exceeded the máximums under that contract there would be an exchange of gas or billing for the excess at the contract rate (X-46). The gas provided for Balko was done so originally and during the proceeding under irrigation schedules. These volumes received by Southern Union in 1976 were about .042 of one percent of Northern’s sales. In 1976 the volumes so used to deliver to Beaver were 84,602 Mef or about .01 percent of Northern’s total volume. Southern Union’s take for Beaver on a peak day (565 Mcf) was about .092 of one percent of Northern’s peak day firm requirements.

The record contains no evidence of damages to customers of Northern or Cities by reason of the gas going to Beaver. The volumes were so small that they were not considered by the suppliers in their allocations. The Commission appears to have assumed that damages would have occurred. The extra gas however was purchased by Southern Union at irrigation rates and sold at the regular retail rates at Beaver.

In response to these connections or takes by Southern Union, which the Commission considered to be a violation of the Act, it sought to apply a remedy. The Attorney General had advised that his office was not going to act on the matter referred to it. It is the nature of this remedy which is at issue here as a question of the authority of the Commission under the Act.

As the remedy sought to be applied, the Commission in Opinions 120 and 120A directed that Cities Service and Northern Natural should collect from Southern Union for the past deliveries of the extra gas at [102]*102rates under what the Commission considered to be emergency rate schedules rather than under the rates applied by the parties to the transaction (IRG-1 and X-46). In compliance with the order Northern has billed Southern Union $419,284 for the past service for Beaver and Cities will apparently bill for about the same amount.

Thus the basic issue on appeal is whether this order of the Commission constitutes an assessment of a “penalty”, is some form of “reparations” or to punish Southern Union in some way for misconduct. Also the issue arises as to whether the application of “emergency rates” is retroactive rate making in view of the question as to whether there were any such “emergency” rates in existence at the time in question.

The petitioner asserts that there were no emergency rate schedules then in effect between it and Cities or Northern. Thus the Commission has engaged in retroactive rate making. The petitioner also asserts that the order of the Commission by its terms and language itself demonstrates that a penalty is sought to be imposed or reparations ordered under the guise of rate making.

The Commission, on the other hand, urges that its order is proper as an administrative action taken pursuant to Section 16 of the Natural Gas Act. The Commission acknowledges that it has no authority to impose penalties nor to engage in retroactive rate making. The Commission cites United Gas Company v. Gallery Properties, Inc., 382 U.S. 223, 86 S.Ct. 360, 15 L.Ed.2d 284 (1965); Gulf Oil Corp. v. F.P.C., 563 F.2d 588 (3d Cir.1977), Mesa Petroleum Co. v. F.P.C., 441 F.2d 182

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
725 F.2d 99, 1984 U.S. App. LEXIS 26400, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-union-gas-company-v-federal-energy-regulatory-commission-ca10-1984.