Panhandle Eastern Pipe Line Company v. Federal Energy Regulatory Commission, Indiana Gas Company, Inc., Central Illinois Light Company, Associated Natural Gas Company, Intervenors. Panhandle Eastern Pipe Line Company v. Federal Energy Regulatory Commission, Associated Natural Gas Company, Michigan Consolidated Gas Company, Michigan Gas Storage Company, Indiana Gas Company, Inc., Intervenors

777 F.2d 739, 250 U.S. App. D.C. 80, 1985 U.S. App. LEXIS 23762
CourtCourt of Appeals for the D.C. Circuit
DecidedNovember 22, 1985
Docket84-1297
StatusPublished

This text of 777 F.2d 739 (Panhandle Eastern Pipe Line Company v. Federal Energy Regulatory Commission, Indiana Gas Company, Inc., Central Illinois Light Company, Associated Natural Gas Company, Intervenors. Panhandle Eastern Pipe Line Company v. Federal Energy Regulatory Commission, Associated Natural Gas Company, Michigan Consolidated Gas Company, Michigan Gas Storage Company, Indiana Gas Company, Inc., Intervenors) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Panhandle Eastern Pipe Line Company v. Federal Energy Regulatory Commission, Indiana Gas Company, Inc., Central Illinois Light Company, Associated Natural Gas Company, Intervenors. Panhandle Eastern Pipe Line Company v. Federal Energy Regulatory Commission, Associated Natural Gas Company, Michigan Consolidated Gas Company, Michigan Gas Storage Company, Indiana Gas Company, Inc., Intervenors, 777 F.2d 739, 250 U.S. App. D.C. 80, 1985 U.S. App. LEXIS 23762 (D.C. Cir. 1985).

Opinion

777 F.2d 739

250 U.S.App.D.C. 80

PANHANDLE EASTERN PIPE LINE COMPANY, Petitioner,
v.
FEDERAL ENERGY REGULATORY COMMISSION, Respondent,
Indiana Gas Company, Inc., Central Illinois Light Company,
Associated Natural Gas Company, et al., Intervenors.
PANHANDLE EASTERN PIPE LINE COMPANY, Petitioner,
v.
FEDERAL ENERGY REGULATORY COMMISSION, Respondent,
Associated Natural Gas Company, et al., Michigan
Consolidated Gas Company, Michigan Gas Storage
Company, Indiana Gas Company, Inc., Intervenors.

Nos. 84-1297, 84-1468.

United States Court of Appeals,
District of Columbia Circuit.

Argued Sept. 26, 1985.
Decided Nov. 22, 1985.

Petition for Review of an Order of the Federal Energy Regulatory commission.

Raymond N. Shibley, with whom Patrick J. Whittle was on brief for petitioner in Nos. 84-1297 and 84-1468.

Joseph S. Davies, Attorney, Federal Energy Regulatory Commission, with whom William H. Satterfield, General Counsel, Jerome M. Feit, Solicitor, and Leslie J. Lowner, Attorney, Federal Energy Regulatory Commission were on the brief for respondent in Nos. 84-1297 and 84-1468. Barbara Weller, Attorney, Federal Energy Regulatory Commission, Washington, D.C., also entered an appearance for respondent in No. 84-1297.

John R. Schaefgen, Jr., with whom Stephen L. Huntoon was on the brief for intervenor Associated Natural Gas Company, et al. in Nos. 84-1297 and 84-1468. Richard M. Merriman, Washington, D.C., also entered an appearance for intervenor Associated Nat. Gas Co., et al. in No. 84-1468.

George A. Avery and Daniel L. Koffsky, Washington, D.C., were on brief for intervenor Michigan Gas Storage Co. in No. 84-1468.

Jeffrey M. Petrash, Detroit, Mich., and James H. Holt, Washington, D.C., were on brief for intervenor Michigan Consolidated Gas Co. in No. 84-1468.

J. Richard Tiano, Washington, D.C., Kenneth T. Rynne and Daniel W. McGill, Indianapolis, Ind., were on brief for intervenor Indiana Gas Co., Inc. in Nos. 84-1297 and 84-1468.

Before J. SKELLY WRIGHT, MIKVA and GINSBURG, Circuit Judges.

GINSBURG, Circuit Judge:

Two Federal Energy Regulatory Commission (Commission or FERC) orders are before us for review; both orders deny petitioner, Panhandle Eastern Pipe Line Company (Panhandle), recovery of carrying charges for unrecovered gas costs in its Account No. 191.1 The two orders represent the Commission's attempt to halt the rapid growth of already enormous sums in petitioner's deferred account--sums that Panhandle expects some day to recover from future consumers. We hold that the first order was a reasonable response to a situation created primarily by Panhandle's own imprudence. We do not pass on the reasonableness of the second order, but instead remand that matter to the Commission for the statutorily required hearing.

The first order granted Panhandle's request to amortize its enormous deferred balance over thirty-nine months rather than the usual six allowed by regulation, but permitted Panhandle to recover only those carrying charges that would be recovered if the balance were amortized over twelve months. See Panhandle Eastern Pipe Line Co., 23 F.E.R.C. p 61,319, at 61,699-709 (May 31, 1983) (First Order ). FERC found that the build-up of the deferred account balance was ascribable primarily to Panhandle's imprudence; consequently, the Commission determined that a large portion of the requested carrying costs could not stand as "just and reasonable" charges under the Natural Gas Act (Act). See 15 U.S.C. Sec. 717c(a) (1982). We conclude that substantial evidence supports FERC's position. We further hold that the Commission's decision to disallow specifically twenty-seven months of interest was within the "zone of reasonableness."

The second order denied Panhandle recovery of all carrying charges on unrecovered gas costs for the months June-August 1983, on the ground that Panhandle had not lived up to its "representations" recorded in the First Order, that it would "reach or closely approximate" its targeted purchased gas price for those months. Panhandle Eastern Pipe Line Co., 26 F.E.R.C. p 61,252, at 61,564 (Feb. 28, 1984) (Second Order ). We vacate this order and remand the matter so that FERC may undertake the hearing required by statute before the Commission disallows rates on the basis of disputed factual issues. See 15 U.S.C. Sec. 717c(e) (1982).

I. BACKGROUND

Under the Natural Gas Act, pipeline companies must file proposed "just and reasonable" rates with the Commission. They commonly do so in two ways. First, at least once every three years, pipelines must initiate a general rate proceeding under section 4 of the Act, 15 U.S.C. Sec. 717c (1982), to adjust their rates on the basis of a complete cost-of-service study. Second, because the price of gas may fluctuate widely over short periods, FERC also allows pipelines to adjust their rates at six month intervals to reflect recent changes in the price of gas without going through a full cost-of-service rate filing. These biannual filings are called purchased gas adjustments (PGAs). See 18 C.F.R. Sec. 154.38 (1985).2

The amount that a pipeline in fact pays for natural gas during each six month period may vary from the purchase price targeted in its PGA. When actual costs exceed estimated costs, the pipeline may place the costs that were not recovered from its customers in a deferred account, called Account No. 191, to be amortized as a surcharge to the pipeline's rates over the next six month period. Similarly, the pipeline may collect interest on the unamortized balance remaining in Account No. 191 by adding a surcharge to the rates filed in its next PGA. This interest to be recovered is called "carrying charges." See 18 C.F.R. Sec. 154.38(d)(4)(iv)(a)-(d) (1985).

This case involves two denials by FERC of requests for extraordinary carrying charges in extraordinary circumstances. As of November 1981, Panhandle had a negative balance in its Account No. 191. Beginning that fall, Panhandle decided to buy greater quantities of expensive Algerian gas from its wholly-owned subsidiary Trunkline Gas Company (Trunkline) and reduced its purchases of low cost gas; this purchasing pattern continued throughout the period in question.3 Shortly thereafter, Panhandle's sales volume began steadily to drop. During the same period, Panhandle consistently under-recovered a substantial portion of its gas costs and deferred them for later recovery. The amount in its Account No. 191 climbed with startling rapidity: from a negative balance of 4.7 million dollars in November 1981 to a positive balance of 32.5 million in December of that year, to 189.1 million in June 1982, and to 269.8 million in November 1982.

Finally, this enormous balance gave rise to such an enormous surcharge that Panhandle's gas became unmarketable. In April 1983, Panhandle filed for an out-of-cycle PGA to reduce its prices.4 It offered two bases for this proposed reduction.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

West Ohio Gas Co. v. Public Util. Comm'n of Ohio
294 U.S. 63 (Supreme Court, 1935)
Federal Power Commission v. Texaco Inc.
377 U.S. 33 (Supreme Court, 1964)
Badger v. United States
449 U.S. 889 (Supreme Court, 1980)
Joseph v. Helms
457 U.S. 1117 (Supreme Court, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
777 F.2d 739, 250 U.S. App. D.C. 80, 1985 U.S. App. LEXIS 23762, Counsel Stack Legal Research, https://law.counselstack.com/opinion/panhandle-eastern-pipe-line-company-v-federal-energy-regulatory-cadc-1985.