Southern Minnesota Municipal Power Agency v. City of St. Peter

433 N.W.2d 463, 1988 Minn. App. LEXIS 1275, 1988 WL 136723
CourtCourt of Appeals of Minnesota
DecidedDecember 27, 1988
DocketC5-88-1422
StatusPublished
Cited by9 cases

This text of 433 N.W.2d 463 (Southern Minnesota Municipal Power Agency v. City of St. Peter) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southern Minnesota Municipal Power Agency v. City of St. Peter, 433 N.W.2d 463, 1988 Minn. App. LEXIS 1275, 1988 WL 136723 (Mich. Ct. App. 1988).

Opinion

OPINION

RANDALL, Judge.

Southern Minnesota Municipal Power Agency (SMMPA) brought a declaratory judgment action against the City of St. Peter (St. Peter) to determine whether its April 11,1984, electric power sales contract (contract) was enforceable. St. Peter counterclaimed, seeking to have the contract rescinded on equitable grounds. Concerned Citizens for Reasonable Electric *465 Rates, Inc. (CCRER) intervened (on the side of St. Peter) as a defendant, representing consumers of St. Peter’s municipal electricity. The trial court declared the contract to be valid and dismissed all counterclaims. Post-trial motions were denied and judgment was entered for SMMPA, with an amended judgment against St. Peter taxing costs. St. Peter and CCRER appeal from the judgments. We affirm.

FACTS

St. Peter is a municipality located in southern Minnesota. Unlike some municipalities that own their own generating plants, St. Peter contracts with outside suppliers for electric power. For over 50 years, St. Peter contracted with Northern States Power Company (NSP), a private utility, for its supply of electricity. St. Peter eventually became dissatisfied with NSP. Each year, St. Peter actively contested NSP’s proposed rate increases. St. Peter had been dissatisfied with NSP’s unwillingness to contract for over 15 years. River Electric Association, an organization formed by southern Minnesota municipalities to which NSP supplied electricity, joined in these challenges.

SMMPA is a municipal power agency incorporated under Minn.Stat. § 453.53 (1976). 1 As such, SMMPA had the capacity to finance and acquire its own electric energy facility. SMMPA initially planned to construct and operate a 300m megawatt base load facility. Under this plan, SMMPA would supply electricity to its members from the new generating plant, existing member-owned generating plants, and outside sources. SMMPA’s plan included providing reasonably priced electricity (by economies of scale), economical dispatching, tax-exempt-bond financing, and no dividend payments to stockholders. SMMPA’s rates would be only high enough to cover its revenue requirements, and its members would have a voice in determining those rates. If excess revenues were realized in any year, they would be returned to the members.

Desiring to be less dependent on NSP for its supply of electricity, St. Peter joined SMMPA in March 1977 to explore an alternative supplier of electricity. St. Peter’s representative to SMMPA, Jim Sandeen, was elected to SMMPA’s seven-member board of directors in late 1977 and served until 1983. SMMPA’s board of directors was comprised of member municipalities’ appointed representatives, who had a variety of backgrounds. Sandeen’s background included serving for a number of years as St. Peter’s Director of Public Works and Superintendent of St. Peter’s electrical department.

While SMMPA’s construction plans were being formulated, SMMPA’s consulting engineers, the R.W. Beck firm, learned that NSP was interested in having other utilities own part of NSP’s proposed 800 megawatt SHERCO 3 facility. SMMPA thereafter initiated negotiations with NSP, resulting in a September 17, 1980, letter of intent between the parties. Under the terms of the letter, SMMPA would purchase at least 300 megawatts of SHERCO 3 if its construction was approved by the State of Minnesota. If NSP could not obtain construction approval, SMMPA would proceed with its initial plan of constructing its own facility.

After entering into the letter of intent with NSP, SMMPA asked its twenty-two member cities to decide by April 1981 whether they would enter into “Power Sales Contracts” with SMMPA. Executed contracts would allow SMMPA to determine how much of SHERCO 3 it would purchase and how many revenue bonds it had to sell to finance the purchase.

To assist its members in reaching a decision on whether to contract, SMMPA provided information through a newsletter, SMMPA Facts, and a slide show, “Our Power for Our Future.” In these communications, SMMPA commented on the uncertainties of the future energy supply in *466 general, and from NSP specifically. These communications also commented on feasibility studies done by SMMPA that showed SMMPA as being the most economical way for municipalities to obtain reliable electric power during the next two decades. SMMPA’s intent in these communications was to downplay NSP’s capacity and pricing structure in favor of its own. However, SMMPA’s intent was not hidden, and was clear to those receiving the communications.

While St. Peter deliberated over whether to contract, it asked SMMPA to provide it with a cost comparison between electricity supplied by SMMPA and electricity supplied by NSP. SMMPA asked the R.W. Beck firm to prepare such a cost comparison. In compiling the requested comparison, R.W. Beck used NSP’s historical rate increase performance as the basis for projecting NSP’s future costs. As SMMPA did not have any performance history, the R.W. Beck firm developed projected performance data to estimate SMMPA’s future costs. Ultimately, Beck compiled three projected cost comparisons for SMMPA — a “low,” a “probable,” and a “high” comparison. The “low” comparison projected that SMMPA’s power costs would be higher than NSP’s from 1985 through 1992. The “probable” comparison projected that initially SMMPA’s power costs would be higher than NSP’s, but by 1990, SMMPA’s costs would cross over NSP’s and remain lower than NSP’s through 1992. Finally, the “high” comparison projected that in 1985 SMMPA’s power costs would be lower than NSP’s, but in 1986, SMMPA’s costs would cross over and become higher than NSP’s costs through 1987, and, then, in 1988, SMMPA’s costs would again cross over and then remain lower than NSP’s costs through 1992. The R.W. Beck firm clearly indicated on each of the comparisons that the figures were projections. Although the R.W. Beck firm provided all three comparisons to SMMPA, SMMPA elected to provide only the “probable” comparison to St. Peter.

The St. Peter City Council discussed and considered from September 1980 to April 1981 the issue of contracting with SMMPA. Finally, on April 13, 1981, the council met to decide on whether to contract with SMMPA for its supply of municipal electricity. Before voting, the council heard from staff and from proponents and opponents of contracting with SMMPA. The opponents challenged the council’s concerns over future availability of energy and challenged the accuracy of SMMPA’s cost comparisons. Following public comment, the council voted 6-1 to contract with SMMPA for its municipal supply of electricity. Thereafter, a power supply contract dated as of April 1, 1981, was entered into by St. Peter and SMMPA. The effective date of the contract, however, was delayed until May 1, 1985, to coincide with the then projected commercial operation date of SHERCO 3. The contract by its terms was to be effective for a period of 45 years, terminating in the year 2030.

Before SMMPA began supplying St. Peter’s electricity, NSP continued under contract to be St. Peter’s supplier. During this interim period of 1982 through 1984, NSP’s costs of power increased and were passed on to St. Peter through their contract’s fuel adjustment clause. For reasons not contained in the record, St.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sandra Weise v. Alan M. Powell
Court of Appeals of Minnesota, 2024
Ransom v. VFS, Inc.
918 F. Supp. 2d 888 (D. Minnesota, 2013)
UNION COUNTY, IA v. Piper Jaffray & Co., Inc.
741 F. Supp. 2d 1064 (S.D. Iowa, 2010)
Best Buy Stores, L.P. v. Developers Diversified Realty Corp.
636 F. Supp. 2d 869 (D. Minnesota, 2009)
Swenson v. Bender
764 N.W.2d 596 (Court of Appeals of Minnesota, 2009)
Bloom v. Hennepin County
783 F. Supp. 418 (D. Minnesota, 1992)
Production Credit Ass'n v. Farm Credit Bank
781 F. Supp. 595 (D. Minnesota, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
433 N.W.2d 463, 1988 Minn. App. LEXIS 1275, 1988 WL 136723, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southern-minnesota-municipal-power-agency-v-city-of-st-peter-minnctapp-1988.