South Texas College of Law v. KBR, Inc.

433 S.W.3d 86, 2014 WL 982856, 2014 Tex. App. LEXIS 2809
CourtCourt of Appeals of Texas
DecidedMarch 13, 2014
Docket01-12-00864-CV
StatusPublished
Cited by3 cases

This text of 433 S.W.3d 86 (South Texas College of Law v. KBR, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
South Texas College of Law v. KBR, Inc., 433 S.W.3d 86, 2014 WL 982856, 2014 Tex. App. LEXIS 2809 (Tex. Ct. App. 2014).

Opinion

OPINION

SHERRY RADACK, Chief Justice.

In this construction case we consider whether the trial court erred by granting a construction manager’s motion for summary judgment, which was based on the statute of repose. We affirm.

BACKGROUND

The Construction

In 1981, South Texas College of Law [“South Texas”] hired KBR, Inc. [“KBR”] in connection with its plans to build an 11-story annex to its existing building. According to South Texas’s petition, “KBR contracted to provide management and supervision services to coordinate the project, as well as represent South Texas on all matters pertaining to the planning, design and construction of the project under a contract dated July 17, 1981.” The petition further alleges as follows:

13. KBR contracted with South Texas to provide management and supervision services for the project. Among the specific duties undertaken by KBR, KBR agreed to:
a. Establish, direct, and coordinate project schedule for the complete design and construction phase of the project;
b. Review and design development on a periodic basis and provide Value Analysis of Materials, Building Systems, Equipment, and Construction Methods; and
c. Represent South Texas and act in its behalf on all matters pertaining to the planning, design and construction of the Project.

Wilmac Contractors Inc. [“Wilmac”] was hired as the general contractor for the Project and Vernon Masonry, Inc., [“Vernon Masonry”] was its masonry subcontractor. Construction on the tower was completed in 1984.

Masonry Defects Appear Over 20 Years Later

In June 2006, brick and mortar began falling from the tower onto the sidewalks below. South Texas began an investigation by hiring two engineering firms to ascertain the cause of the problem. According to South Texas, both firms concluded that the masonry structure was constructed “in derogation of clear plans and specification which detailed the proper manner in which the masonry wall was to be installed.”

The Underlying Lawsuit

South Texas filed suit in May 2008 against KBR, Wilmac, Wilmac’s surety, Seaboard Surety Company, and Vernon Masonry. The claims against KBR included breach of contract, breach of warranty, negligence, breach of fiduciary duty, and violations of the Texas Deceptive Trade Practices Act. As to the breach of contract claim, South Texas’s petition alleged:

*89 With respect to the construction and installation of the masonry wall for the exterior of the 11-story tower, KBR wholly failed to comply with and breached its contract with South Texas. It has now been discovered [that] the masonry wall structure was not installed in accordance with the plans and specification, building codes and applicable industry standards. For example, the architectural drawings call for a one-half inch wide soft joint in front of each shelf angle. It has been discovered that the soft joints were eliminated altogether and the joints themselves were packed with mortar and covered with a polyurethane sealant over the mortar to give the outward appearance of a soft joint. KBR was contractually obligated to monitor, manage and supervise this work and the results of South Texas’ investigation reveal KBR whole failed to comply with the contract in this respect.

The warranty section of South Texas’s petition alleged that “KBR failed to comply with its express and implied warranty to act on behalf of South Texas and manage, monitor and supervise the construction of the masonry to ensure the masonry installation complied with the plans, specifications and contract documents, applicable industry standards, applicable building codes, and in a good and workmanlike manner.”

The negligence section of South Texas’s petition provided in part:

At all times material, KBR was in the business of providing construction management and supervision services .... By virtue of its business as a construction supervisor and manager, KBR had an existing legal duty to manage and supervision masonry work to ensure the work was performed in a good and workmanlike manner, that it adhered to standard industry practices, and complied with the applicable building codes.... KBR was negligent in its supervision and management of the activities and practices of Wilmac and Vernon.

KBR answered and asserted the affirmative defense of the statute of repose. KBR then filed a motion for summary judgment based on the ten-year statute of repose in section 16.009 of the Texas Civil Practice & Remedies Code. See Tex. Civ. PraC. & Rem.Code Ann. § 16.009 (Vernon 2002). South Texas responded, arguing that KBR could not rely on the statute of repose because it did not construct nor repair improvements to real property. The trial court granted KBR’s motion, but declined to grant a severance at that time. After South Texas settled its claims against the other defendants, KBR’s summary judgment became final. South Texas filed a Motion for New Trial as to KBR, which the trial court denied. This appeal followed.

SUMMARY JUDGMENT BASED ON STATUTE OF REPOSE

In three related issues on appeal, South Texas contends the trial court erred in granting KBR’s motion for summary judgment, which was based on the 10-year statute of repose. Specifically, South Texas contends that KBR cannot utilize the statute of repose because it is not a “per-sone ] who construct^] or repair[s] an improvement to real property.” Instead, South Texas argues that, as a construction manager, KBR’s position is more akin to that of an owner.

Standard of Review

We review a trial court’s summary judgment de novo. Valence Operating Co. v. Dorsett, 164 S.W.3d 656, 661 (Tex.2005); Provident Life & Accid. Ins. Co. v. Knott, 128 S.W.3d 211, 215 (Tex.2003). Under the traditional standard for summary judg *90 ment, the movant has the burden to show that no genuine issue of material fact exists and that the trial court should grant a judgment as a matter of law. Tex.R. Civ. P. 166a(c); KPMG Peat Marwick v. Harrison Cnty. Hous. Fin. Corp., 988 S.W.2d 746, 748 (Tex.1999). When reviewing a summary judgment, we take as true all evidence favorable to the nonmovant and indulge every reasonable inference and resolve any doubts in the nonmovant’s favor. Dorsett, 164 S.W.3d at 661; Knott, 128 S.W.3d at 215; Sci. Spectrum, Inc. v. Martinez, 941 S.W.2d 910, 911 (Tex.1997).

Traditional summary judgment is proper only if the movant establishes that there is no genuine issue of material fact and that the movant is entitled to judgment as a matter of law. Tex.R. Civ. P. 166a(c).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
433 S.W.3d 86, 2014 WL 982856, 2014 Tex. App. LEXIS 2809, Counsel Stack Legal Research, https://law.counselstack.com/opinion/south-texas-college-of-law-v-kbr-inc-texapp-2014.