Affirm and Opinion Filed January 11, 2023
In the Court of Appeals Fifth District of Texas at Dallas No. 05-21-00914-CV
NIKKO CONDOMINIUM ASSOCIATION, ON BEHALF OF ITSELF AND ITS OWNERS, Appellant V. KWA CONSTRUCTION, L.P., KW & ASSOCIATES, LLC, KENYON PLASTERING OF TEXAS, INC., SUBFLOOR SYSTEMS, LLP, AE COMMERCIAL CONTRACTING, INC., GREATER DALLAS, L.P., ABCO CONSTRUCTION SERVICES CORPORATION, AND STARK TRUSS COMPANY, INC., Appellees
On Appeal from the 14th Judicial District Court Dallas County, Texas Trial Court Cause No. DC-21-14653
MEMORANDUM OPINION Before Justices Carlyle, Garcia, and Rosenberg1 Opinion by Justice Carlyle
Appellant Nikko Condominium Association sued appellees to recover for
alleged construction defects in a residential condominium building. The parties filed
competing motions for summary judgment regarding the applicable ten-year statute
of repose. See TEX. CIV. PRAC. & REM. CODE § 16.009. The trial court denied
1 The Hon. Barbara Rosenberg, Justice, Assigned. Nikko’s motion and granted summary judgment in appellees’ favor. We affirm in
this memorandum opinion. See TEX. R. APP. P. 47.4.
Background
In 2007, a developer contracted with appellees KWA Construction, L.P. and
KW & Associates, LLC (collectively, KWA) to construct a Dallas condominium
building (the project). The remaining appellees were subcontractors on the project.
The City of Dallas issued a Certificate of Occupancy for the building on December
16, 2008.
The building was initially used as an apartment complex for about six years.
Then, the developer, who was also the owner, began marketing and selling the
building’s individual units as condominiums. In June 2015, Nikko was formed as
the unit owners’ governing association. See TEX. PROP. CODE § 82.101.
On December 28, 2018, Nikko sent appellees a letter “to present a written
claim for damages, contribution and/or indemnity pursuant to Texas law, including
but not limited to Sections 16.008 & 16.009 of the Texas Civil Practice and Remedies
Code.” The letter described the damages and an estimated cost to repair them.
On December 4, 2019, Nikko filed this lawsuit against appellees and the
developer,2 alleging causes of action including negligence, breach of warranty, and
2 The developer, not a party to this appeal, in turn asserted crossclaims against appellees. Nikko states in its appellate brief that pursuant to a settlement agreement between the developer and Nikko, the developer assigned its claims to Nikko and “[t]herefore, this appeal also seeks reversal of the Trial Court’s granting of summary judgment on the Statute of Repose MSJs filed by the Appellees, ABCO and KWA, against the Developer’s crossclaims.” –2– violation of the Texas Deceptive Trade Practices Act. Appellees filed separate
general denial answers and asserted various affirmative defenses, including that
Nikko’s claims “are barred by the applicable . . . statute of repose.” See TEX. CIV.
PRAC. & REM. CODE § 16.009(a).
In April 2021, Nikko moved for partial summary judgment as to KWA and the
developer regarding section 16.009’s statute of repose affirmative defense. Nikko’s
summary judgment evidence included (1) portions of the project’s contract; (2) an
October 2, 2008 “Change Order” signed by KWA and the owner that stated the
“Contract Time” “REMAINS UNCHANGED” and “[t]he date of Substantial
Completion as of the date of this Change Order therefore is . . . Dec. 29th, 2008”;
(3) various documents regarding 2009 payments by KWA to subcontractors; and
(4) an untitled one-page document the parties referred to as “the Certificate of
Substantial Completion” (CSC).
Over the next several months, appellees each moved for traditional summary
judgment on Nikko’s claims based on the statute of repose.3 Following a series of
hearings, the trial court signed (1) a June 21, 2021 order denying Nikko’s motion for
partial summary judgment as to KWA and the developer and (2) orders dated June
7, 2021, and August 3, 2021, granting appellees’ summary judgment motions
without specifying the bases for those rulings. On September 17, 2021, the trial court
3 Additionally, several appellees filed (1) traditional motions for summary judgment on the developer’s crossclaims based on the same statute of repose arguments and (2) no-evidence motions for summary judgment on Nikko’s claims. –3– signed a final judgment that incorporated the orders granting appellees’ summary
judgment motions against Nikko and the developer and severed Nikko’s claims
against appellees from its claims against the developer.4
Standard of review and applicable law
We review a summary judgment de novo. Trial v. Dragon, 593 S.W.3d 313,
316 (Tex. 2019). A traditional motion for summary judgment requires the moving
party to show that no genuine issue of material fact exists and it is entitled to
judgment as a matter of law. TEX. R. CIV. P. 166a(c); Lujan v. Navistar, Inc., 555
S.W.3d 79, 84 (Tex. 2018). We take evidence favorable to the nonmovant as true,
and we indulge every reasonable inference and resolve every doubt in the
nonmovant’s favor. Ortiz v. State Farm Lloyds, 589 S.W.3d 127, 131 (Tex. 2019). If
the movant satisfies its burden, the burden shifts to the nonmovant to raise a genuine
issue of material fact precluding summary judgment. Lujan, 555 S.W.3d at 84.
When a defendant moves for summary judgment based on a statute of repose,
“the defendant, as movant, bears the burden of proving each essential element of that
defense.” Fed. Deposit Ins. Corp. v. Lenk, 361 S.W.3d 602, 609 (Tex. 2012). When
both sides move for summary judgment and the trial court grants one motion and
denies the other, reviewing courts consider both sides’ summary judgment evidence,
4 The trial court’s June 21, 2021 order denying Nikko’s motion for partial summary judgment was not mentioned in the September 17, 2021 final judgment. After filing this appeal, Nikko, “out of an abundance of caution,” filed a separate appeal that included a complaint as to that denial. This Court consolidated the second appeal into this appeal.
–4– determine all questions presented, and render the judgment the trial court should
have rendered. E.g., Gilbert Tex. Constr., L.P. v. Underwriters at Lloyd’s London,
327 S.W.3d 118, 124 (Tex. 2010).
The statute of repose provides:
(a) . . . [A] claimant must bring suit for damages for a claim listed in Subsection (b) against a person who constructs or repairs an improvement to real property not later than 10 years after the substantial completion of the improvement in an action arising out of a defective or unsafe condition of the real property or a deficiency in the construction or repair of the improvement. .... (b) This section applies to suit for: (1) injury, damage, or loss to real or personal property; (2) personal injury; (3) wrongful death; (4) contribution; or (5) indemnity. (c) If the claimant presents a written claim for damages, contribution, or indemnity to the person performing or furnishing the construction or repair work during the applicable limitations period, the period is extended for . . . two years from the date the claim is presented[.]
TEX. CIV. PRAC. & REM. CODE § 16.009(a)–(c).
Statutory construction presents a question of law subject to de novo review.
Tawes v.
Free access — add to your briefcase to read the full text and ask questions with AI
Affirm and Opinion Filed January 11, 2023
In the Court of Appeals Fifth District of Texas at Dallas No. 05-21-00914-CV
NIKKO CONDOMINIUM ASSOCIATION, ON BEHALF OF ITSELF AND ITS OWNERS, Appellant V. KWA CONSTRUCTION, L.P., KW & ASSOCIATES, LLC, KENYON PLASTERING OF TEXAS, INC., SUBFLOOR SYSTEMS, LLP, AE COMMERCIAL CONTRACTING, INC., GREATER DALLAS, L.P., ABCO CONSTRUCTION SERVICES CORPORATION, AND STARK TRUSS COMPANY, INC., Appellees
On Appeal from the 14th Judicial District Court Dallas County, Texas Trial Court Cause No. DC-21-14653
MEMORANDUM OPINION Before Justices Carlyle, Garcia, and Rosenberg1 Opinion by Justice Carlyle
Appellant Nikko Condominium Association sued appellees to recover for
alleged construction defects in a residential condominium building. The parties filed
competing motions for summary judgment regarding the applicable ten-year statute
of repose. See TEX. CIV. PRAC. & REM. CODE § 16.009. The trial court denied
1 The Hon. Barbara Rosenberg, Justice, Assigned. Nikko’s motion and granted summary judgment in appellees’ favor. We affirm in
this memorandum opinion. See TEX. R. APP. P. 47.4.
Background
In 2007, a developer contracted with appellees KWA Construction, L.P. and
KW & Associates, LLC (collectively, KWA) to construct a Dallas condominium
building (the project). The remaining appellees were subcontractors on the project.
The City of Dallas issued a Certificate of Occupancy for the building on December
16, 2008.
The building was initially used as an apartment complex for about six years.
Then, the developer, who was also the owner, began marketing and selling the
building’s individual units as condominiums. In June 2015, Nikko was formed as
the unit owners’ governing association. See TEX. PROP. CODE § 82.101.
On December 28, 2018, Nikko sent appellees a letter “to present a written
claim for damages, contribution and/or indemnity pursuant to Texas law, including
but not limited to Sections 16.008 & 16.009 of the Texas Civil Practice and Remedies
Code.” The letter described the damages and an estimated cost to repair them.
On December 4, 2019, Nikko filed this lawsuit against appellees and the
developer,2 alleging causes of action including negligence, breach of warranty, and
2 The developer, not a party to this appeal, in turn asserted crossclaims against appellees. Nikko states in its appellate brief that pursuant to a settlement agreement between the developer and Nikko, the developer assigned its claims to Nikko and “[t]herefore, this appeal also seeks reversal of the Trial Court’s granting of summary judgment on the Statute of Repose MSJs filed by the Appellees, ABCO and KWA, against the Developer’s crossclaims.” –2– violation of the Texas Deceptive Trade Practices Act. Appellees filed separate
general denial answers and asserted various affirmative defenses, including that
Nikko’s claims “are barred by the applicable . . . statute of repose.” See TEX. CIV.
PRAC. & REM. CODE § 16.009(a).
In April 2021, Nikko moved for partial summary judgment as to KWA and the
developer regarding section 16.009’s statute of repose affirmative defense. Nikko’s
summary judgment evidence included (1) portions of the project’s contract; (2) an
October 2, 2008 “Change Order” signed by KWA and the owner that stated the
“Contract Time” “REMAINS UNCHANGED” and “[t]he date of Substantial
Completion as of the date of this Change Order therefore is . . . Dec. 29th, 2008”;
(3) various documents regarding 2009 payments by KWA to subcontractors; and
(4) an untitled one-page document the parties referred to as “the Certificate of
Substantial Completion” (CSC).
Over the next several months, appellees each moved for traditional summary
judgment on Nikko’s claims based on the statute of repose.3 Following a series of
hearings, the trial court signed (1) a June 21, 2021 order denying Nikko’s motion for
partial summary judgment as to KWA and the developer and (2) orders dated June
7, 2021, and August 3, 2021, granting appellees’ summary judgment motions
without specifying the bases for those rulings. On September 17, 2021, the trial court
3 Additionally, several appellees filed (1) traditional motions for summary judgment on the developer’s crossclaims based on the same statute of repose arguments and (2) no-evidence motions for summary judgment on Nikko’s claims. –3– signed a final judgment that incorporated the orders granting appellees’ summary
judgment motions against Nikko and the developer and severed Nikko’s claims
against appellees from its claims against the developer.4
Standard of review and applicable law
We review a summary judgment de novo. Trial v. Dragon, 593 S.W.3d 313,
316 (Tex. 2019). A traditional motion for summary judgment requires the moving
party to show that no genuine issue of material fact exists and it is entitled to
judgment as a matter of law. TEX. R. CIV. P. 166a(c); Lujan v. Navistar, Inc., 555
S.W.3d 79, 84 (Tex. 2018). We take evidence favorable to the nonmovant as true,
and we indulge every reasonable inference and resolve every doubt in the
nonmovant’s favor. Ortiz v. State Farm Lloyds, 589 S.W.3d 127, 131 (Tex. 2019). If
the movant satisfies its burden, the burden shifts to the nonmovant to raise a genuine
issue of material fact precluding summary judgment. Lujan, 555 S.W.3d at 84.
When a defendant moves for summary judgment based on a statute of repose,
“the defendant, as movant, bears the burden of proving each essential element of that
defense.” Fed. Deposit Ins. Corp. v. Lenk, 361 S.W.3d 602, 609 (Tex. 2012). When
both sides move for summary judgment and the trial court grants one motion and
denies the other, reviewing courts consider both sides’ summary judgment evidence,
4 The trial court’s June 21, 2021 order denying Nikko’s motion for partial summary judgment was not mentioned in the September 17, 2021 final judgment. After filing this appeal, Nikko, “out of an abundance of caution,” filed a separate appeal that included a complaint as to that denial. This Court consolidated the second appeal into this appeal.
–4– determine all questions presented, and render the judgment the trial court should
have rendered. E.g., Gilbert Tex. Constr., L.P. v. Underwriters at Lloyd’s London,
327 S.W.3d 118, 124 (Tex. 2010).
The statute of repose provides:
(a) . . . [A] claimant must bring suit for damages for a claim listed in Subsection (b) against a person who constructs or repairs an improvement to real property not later than 10 years after the substantial completion of the improvement in an action arising out of a defective or unsafe condition of the real property or a deficiency in the construction or repair of the improvement. .... (b) This section applies to suit for: (1) injury, damage, or loss to real or personal property; (2) personal injury; (3) wrongful death; (4) contribution; or (5) indemnity. (c) If the claimant presents a written claim for damages, contribution, or indemnity to the person performing or furnishing the construction or repair work during the applicable limitations period, the period is extended for . . . two years from the date the claim is presented[.]
TEX. CIV. PRAC. & REM. CODE § 16.009(a)–(c).
Statutory construction presents a question of law subject to de novo review.
Tawes v. Barnes, 340 S.W.3d 419, 425 (Tex. 2011). Similarly, if an agreement’s
language can be given a certain and definite meaning, the agreement is not
ambiguous and its construction is a question of law we review de novo. See Milner
v. Milner, 361 S.W.3d 615, 619 (Tex. 2012). Whether a contract is ambiguous is a
question of law for the court. Lopez v. Munoz, Hockema & Reed, L.L.P., 22 S.W.3d
–5– 857, 861 (Tex. 2000). For an ambiguity to exist, “both interpretations must be
reasonable.” Id.
Analysis
In its first and second issues, Nikko contends the trial court erred
(1) by “denying Nikko’s Repose MSJ because the construction documents for the
building establish that the repose defenses raised by [KWA] and the Developer fail
as a matter of law” and (2) alternatively, by “granting Appellees’ motions for
summary judgment on their repose defenses when the construction documents for
the building establish genuine issues of material fact concerning the date of
substantial completion of the building.” Nikko does not dispute that the statute of
repose bars its claims unless substantial completion occurred on or after December
28, 2008, within ten years of the date it provided the written claim to appellees. See
TEX. CIV. PRAC. & REM. CODE § 16.009(c). On this record, we cannot agree with
Nikko that it conclusively established its claims were timely or that the evidence
raised a fact issue as to whether substantial completion occurred on or after
December 28, 2008.
First, Nikko argues that because the relevant contract provision requires an
architect to complete a CSC and there is no evidence an architect did so, the CSC
completed by the property owner and KWA either did not sufficiently establish a
date of substantial completion or creates a fact issue as to the date. We turn first to
the contract: subsection 8.1.3 provided for a date of substantial completion “certified
–6– by the Architect in accordance with Section 9.8.” Subsection 9.8.4 stated, “When the
Work or designated portion thereof is substantially complete, the Architect will
prepare a Certificate of Substantial Completion which shall establish the date of
Substantial Completion, shall establish responsibilities of the Owner and Contractor
for security, maintenance, heat, utilities, damage to the Work and insurance, and shall
fix the time within which the Contractor shall finish all items on the list
accompanying the Certificate.” Subsection 9.8.5 stated, “The Certificate of
Substantial Completion shall be submitted to the Owner and Contractor for their
written acceptance of responsibilities assigned to them in such Certificate.” Nothing
in the project’s contract precluded the validity of the certificate of substantial
completion signed by the owner and contractor pursuant to subsection 9.8.5 in this
case.
Next, we address the CSC, which Nikko argues should support at least a fact
issue as to the date of substantial completion because the signatures are dated in early
2009. The CSC described the project and the contract, then stated:
–7– Nikko’s argument ignores portions of the CSC. See Seagull Energy E&P, Inc.
v. Eland Energy, Inc., 207 S.W.3d 342, 345 (Tex. 2006) (in construing an agreement,
“[n]o single provision taken alone will be given controlling effect; rather, all the
provisions must be considered”). The stated dates for commencement of warranties
and for the owner’s assumption of full possession with acceptance of the work as
substantially complete were both before December 28, 2008. The CSC
unambiguously shows the owner and KWA intended to establish a date of substantial
completion that was not later than December 12, 2008. To the extent the project’s
contract precluded substantial completion until the owner received a certificate of
occupancy, the city issued that that certificate on December 16, 2008. And to the
extent the owner and KWA had previously described a different date of substantial –8– completion in the October 2008 change order, the record does not show the date in
that change order controlled over the later CSC.
Nikko also contends the evidence showing KWA approved and received
payments regarding the project as late as February 2009 and described the project as
being “in its final stage of completion” at that time raised a fact question as to the
date of substantial completion. We cannot agree. Section 9.8.1 of the project’s
contract described substantial completion as “the stage in the progress of the Work
when the Work or designated portion thereof is sufficiently complete in accordance
with the Contract Documents so that the Owner can occupy or utilize the Work for
its intended use.” The record does not show how the 2009 payments or the reference
to “final completion” had any bearing on the project’s substantial completion or
precluded a substantial completion date prior to December 28, 2008. We conclude
the record shows the project’s substantial completion occurred no later than
December 16, 2008, as a matter of law.5
In its third issue, Nikko asserts the trial court erred by granting ABCO’s
motion for summary judgment “where ABCO neither constructed nor repaired
improvements to real property, rendering it unable to take advantage of the statute
5 Appellees’ appellate brief includes assertions that several individual appellees substantially completed their work on the project prior to December 2008 and that we should analyze substantial completion as to each of them individually. In light of our conclusion that substantial completion as to the entire project occurred by December 16, 2008, we need not address those arguments. –9– of repose.” ABCO cites South Texas College of Law v. KBR, Inc., 433 S.W.3d 86
(Tex. App.—Houston [1st Dist.] 2014, pet. denied).
That case involved an action against a construction manager, KBR, for
negligence, breach of warranty, DTPA violations, and other claims based on defects
in work performed by the general contractor KBR hired. The plaintiff’s petition
alleged KBR “contracted to provide management and supervision services to
coordinate the project” and failed to comply with its obligations “to ensure the work
was performed in a good and workmanlike manner.” Id. at 88–89. In response to
KBR’s motion for summary judgment on section 16.009’s statute of repose
affirmative defense, the plaintiff argued KBR could not rely on that section because
“it did not construct nor repair improvement to real property.” Id. at 89.
The trial court granted KBR’s summary judgment motion and the court of
appeals affirmed. Id. The court of appeals observed that section 16.009 “was
intended to apply to litigation against architects, engineers, and others involved in
designing, planning or inspecting improvements to real property, as distinguished
from materialmen and suppliers and from tenants and owners who possess or control
the property.” Id. at 91 (citing McCulloch v. Fox & Jacobs, Inc., 696 S.W.2d 918,
922 (Tex. App.—Dallas 1985, writ ref’d n.r.e) (interpreting predecessor statute)).
Though the parties did not dispute that “section 16.009’s protection extends to
parties who, though they did not personally perform the construction work at issue,
were nevertheless contractually responsible for the construction work and subject to
–10– liability in the lawsuit based on that responsibility,” they disagreed about whether
KBR’s involvement in the project was sufficient to invoke the statute’s protection.
Id.
The court of appeals reasoned that though the plaintiff contended KBR
“merely watched the contractor who built the building,” the pleadings belied that
assertion because the petition alleged KBR (1) was “contractually obligated to
monitor, manage and supervise” the work, “thereby causing damage to [plaintiff]”;
(2) “was in the business of providing construction management and supervision
services,” “had an existing legal duty to manage and supervise [the work] to ensure
the work was performed in a good and workmanlike manner,” and “was negligent in
its supervision and management of the activities and practices of [the general
conractor]”; and (3) breached an implied or express warranty “to act on behalf of
[plaintiff] and manage, monitor and supervise the construction of [the work] to
ensure [the work] complied” with plans, specifications, contractual documents,
industry standards, building codes, and was performed in a good and workmanlike
manner. Id. at 92. Additionally, the court of appeals noted that KBR, “who is being
sued for failing to properly supervise the contractor and subcontractor,” is “similarly
situated” to the general contractor and subtractors, to whom section 16.009 was
determined applicable. Id. The court stated that because “it is apparent that KBR is
an entity in the construction industry and that [plaintiff] is seeking to hold it
–11– contractually responsible for the faulty [work],” “we conclude that KBR is a ‘direct
actor’ in the construction process.” Id.
Nikko contends KBR is distinguishable because the plaintiff in KBR “alleged
that KBR was an agent with express contractual obligations to monitor construction
and ensure proper performance,” while Nikko’s pleadings “contain no such
allegations” and “ABCO’s service contract expressly disclaimed responsibility or
control over the parties involved in the underlying construction.” In support of its
position, Nikko cites its live petition and statements in ABCO’s 2007 service
contract that (1) ABCO’s services “are for limited observation of construction
elements and documents” and (2) “[t]he client retains ultimate control and
responsibility for all work at the project.”
The record shows Nikko’s live petition described ABCO as “Supervisor;
retained to conduct periodic site visits at various stages of construction of the
project.” The petition also alleged that the defendant “Contractors,” which the
petition stated included ABCO, “were in position, and had the duty to, among other
things”:
Ensure that the Condominium Project was constructed in a good and workmanlike manner; Ensure that the Condominium Project was constructed in accordance with all applicable City codes and ordinances; and Ensure that construction of the Condominium Project was properly supervised.
–12– Thus, Nikko sought to hold ABCO liable for improper performance of its
services, which purportedly contributed to the faulty construction work. On this
record, we conclude ABCO conclusively established it was entitled to section
16.009’s statute of repose affirmative defense. See id.
We conclude the trial court did not err by denying Nikko’s motion for partial
summary judgment or by granting appellees’ motions for summary judgment on
section 16.009’s statute of repose. See Gordon v. W. Steel Co., 950 S.W.2d 743, 749
(Tex. App.—Corpus Christi 1997, writ denied) (affirming summary judgment based
on section 16.009’s statute of repose where “appellees met their burden of proving
that they substantially completed their improvement to the project more than ten
years before they were sued”). We affirm the trial court’s judgment.6
/Cory L. Carlyle/ 210914f.p05 CORY L. CARLYLE JUSTICE
6 Appellee Stark Truss Company asserts on appeal that its motion for summary judgment should also be independently affirmed based on its no-evidence challenge because Nikko filed no response to its motion. Because our statute of repose conclusions above apply to all appellees, we need not reach Stark Truss Company’s no-evidence argument. See, e.g., Merriman v. XTO Energy, Inc., 407 S.W.3d 244, 248 (Tex. 2013) (where trial court does not specify ground for granting summary judgment motion, appellate court must affirm if any ground presented to trial court and preserved for appellate review is meritorious); see also TEX. R. APP. P. 47.1. –13– Court of Appeals Fifth District of Texas at Dallas JUDGMENT
NIKKO CONDOMINIUM On Appeal from the 14th Judicial ASSOCIATION, ON BEHALF OF District Court, Dallas County, Texas ITSELF AND ITS OWNERS, Trial Court Cause No. DC-21-14653. Appellant Opinion delivered by Justice Carlyle. Justices Garcia and Rosenberg No. 05-21-00914-CV V. participating.
KWA CONSTRUCTION, L.P., KW & ASSOCIATES, LLC, KENYON PLASTERING OF TEXAS, INC., SUBFLOOR SYSTEMS, LLP, AE COMMERCIAL CONTRACTING, INC., GREATER DALLAS, L.P., ABCO CONSTRUCTION SERVICES CORPORATION, AND STARK TRUSS COMPANY, INC., Appellees
In accordance with this Court’s opinion of this date, the judgment of the trial court is AFFIRMED.
It is ORDERED that appellees KWA CONSTRUCTION, L.P., KW & ASSOCIATES, LLC, KENYON PLASTERING OF TEXAS, INC., SUBFLOOR SYSTEMS, LLP, AE COMMERCIAL CONTRACTING, INC., GREATER DALLAS, L.P., ABCO CONSTRUCTION SERVICES CORPORATION, AND STARK TRUSS COMPANY, INC., recover their costs of this appeal from appellant NIKKO CONDOMINIUM ASSOCIATION, ON BEHALF OF ITSELF AND ITS OWNERS. –14– Judgment entered this 11th day of January, 2023.
–15–