South Carolina Wildlife Federation v. Limehouse

549 F.3d 324, 39 Envtl. L. Rep. (Envtl. Law Inst.) 20294, 2008 U.S. App. LEXIS 24722, 2008 WL 5103093
CourtCourt of Appeals for the Fourth Circuit
DecidedDecember 5, 2008
Docket07-1431
StatusPublished
Cited by84 cases

This text of 549 F.3d 324 (South Carolina Wildlife Federation v. Limehouse) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
South Carolina Wildlife Federation v. Limehouse, 549 F.3d 324, 39 Envtl. L. Rep. (Envtl. Law Inst.) 20294, 2008 U.S. App. LEXIS 24722, 2008 WL 5103093 (4th Cir. 2008).

Opinion

Affirmed by published opinion. Judge DUNCAN wrote the opinion, in which Judge MOTZ and Judge KING joined.

OPINION

DUNCAN, Circuit Judge:

The South Carolina Wildlife Federation and co-plaintiffs (collectively “SCWF”) brought suit against federal and state agencies and agency directors, alleging violations of the National Environmental Policy Act (“NEPA”), 42 U.S.C. § 4321 et seq., arising from the proposed construction of the Briggs-DeLaine-Pearson Connector (“the Connector”) in South Carolina. Relevant to this appeal, the Director of the South Carolina Department of Transportation (“the Director”), who was sued in his official capacity, moved to dismiss on the ground that the claims against him were barred by sovereign immunity under the Eleventh Amendment. The district court denied the Director’s motion, and he filed this interlocutory appeal. 1 For the reasons that follow, we affirm.

I.

NEPA requires an agency undertaking a “major Federal action[]” to produce a “detailed statement” concerning “the environmental impact of the proposed action.” 42 U.S.C. § 4332(C). The environmental impact statement (“EIS”) must address, inter alia, any adverse impact a proposed project would have on the environment and possible “alternatives to the proposed action.” Id. For actions funded by federal grants to states, NEPA provides that the EIS may be prepared by state actors, with federal guidance, so long as the state actors have “statewide jurisdiction” and re *328 sponsibility for the proposed action. 42 U.S.C. § 4332(D).

The EIS process has several steps. The responsible agency must first prepare a draft EIS and solicit comments on it. 40 C.F.R. § 1503.1. Those comments must then be “assess[ed] and considered]” in drafting the final environmental impact statement (“FEIS”), which is published in the Federal Register. 40 C.F.R. § 1503.4, 1506.10(b). The FEIS is followed by issuance of a record of decision, which must: state the agency’s decision; “[ijdentify all alternatives considered by the agency,” specifically noting those that were environmentally preferable and the factors considered in rejecting them; and state whether the agency has adopted all proposed practicable means to minimize environmental impact. 40 C.F.R. § 1505.2. During the NEPA process, an agency cannot take any action which would “(1) Have an adverse environmental impact; or (2) Limit the choice of reasonable alternatives.” 40 C.F.R. § 1506.1(a).

The major federal action in the instant case is the construction of the Connector, a bridge which, when complete, will span fewer than ten miles and link the South Carolina towns of Rimini (pop.286) and Lone Star (pop.601). J.A. at 61; Appel-lee’s Br. at 7. The Connector is slated to cost between $100 and $150 million and will be fully funded through federal appropriations; no state money is scheduled to be used. J.A. at 94. Thus far, at least $16 million in federal funds has been appropriated for the project. J.A. at 95. In the ongoing case below, SCWF contends that the Defendants have failed to comply with the procedural requirements of NEPA and that therefore the Federal Highway Administration’s (the “FHWA”) approval of the project is invalid under NEPA.

The FHWA and the South Carolina Department of Transportation (“SCDOT”) undertook the NEPA process following Congressional approval of the Connector, with the federal and state agencies sharing responsibility for the preparation of the EIS. J.A. at 47-49, 64-65; see also Environmental Impact Statement: Calhoun, Clarendon and Sumter Counties, SC, 65 Fed.Reg. 71,349, 71,349-50 (Nov. 30, 2000). The agencies promulgated a draft EIS, which was prepared by state and federal officials in conjunction with outside consultants, in October 2001. J.A. at 8-9, 95-96. Following the receipt of comments, the FEIS was issued in December 2002; and in June 2003, the FHWA issued a record of decision approving the FEIS. J.A. at 96. The FHWA published notice of its decision in the Federal Register on March 17, 2006, establishing a 180-day period to challenge the agency action. SCWF timely filed suit seeking a declaratory judgment on the ground that the FEIS and record of decision were improperly issued and seeking an injunction against further action pending compliance with NEPA. J.A. at 37.

The named defendants below were the SCDOT, the Executive Director of the SCDOT, 2 the FHWA, and the Division Administrator of the FHWA. The SCDOT and the Director moved to dismiss, claiming that SCWF lacked standing to proceed, that SCWF’s claims were not ripe, and that both the SCDOT and the Director were entitled to sovereign immunity from suit pursuant to the Eleventh Amendment. The district court found that SCWF had standing and that the claims were ripe. On the question of Eleventh Amendment *329 immunity, the district court found that there had been no congressional abrogation of the state’s immunity and so the SCDOT as a state agency was immune from suit. J.A. at 106-07; accord City of Boerne v. Flores, 521 U.S. 507, 117 S.Ct. 2157, 138 L.Ed.2d 624 (1997).

The Director also claimed Eleventh Amendment immunity. However, the district court found that the Director was not entitled to immunity pursuant to Ex parte Young, 209 U.S. 123, 28 S.Ct. 441, 52 L.Ed. 714 (1908). The Director now appeals this decision, challenging the district court’s conclusions on the standing and immunity questions.

II.

As a court must satisfy itself of its jurisdiction, we turn first to the issue of standing. Bender v. Williamsport Area Sch. Dist., 475 U.S. 534, 541, 106 S.Ct. 1326, 89 L.Ed.2d 501 (1986). 3 Standing has three essential elements: injury, causation, and redressability. Marshall v. Meadows, 105 F.3d 904, 906 (4th Cir.1997).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
549 F.3d 324, 39 Envtl. L. Rep. (Envtl. Law Inst.) 20294, 2008 U.S. App. LEXIS 24722, 2008 WL 5103093, Counsel Stack Legal Research, https://law.counselstack.com/opinion/south-carolina-wildlife-federation-v-limehouse-ca4-2008.