South Bay Boiler Repair, Inc.

CourtArmed Services Board of Contract Appeals
DecidedJanuary 19, 2017
DocketASBCA No. 59281
StatusPublished

This text of South Bay Boiler Repair, Inc. (South Bay Boiler Repair, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
South Bay Boiler Repair, Inc., (asbca 2017).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) South Bay Boiler Repair, Inc. ) ASBCA No. 59281 ) Under Contract No. N55236-09-D-0017 )

APPEARANCES FOR THE APPELLANT: Robert L. Kenny, Esq. Law Office of Robert L. Kenny San Diego, CA

James A. Kelley, Esq. James A. Kelley & Associates Washington, DC

APPEARANCES FOR THE GOVERNMENT: Ronald J. Borro, Esq. Navy Chief Trial Attorney Ellen M. Evans, Esq. Senior Trial Attorney Rawn M. James, Esq. Matthew D. Bordelon, Esq. Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE WOODROW

INTRODUCTION

The case involves an appeal from a contracting officer's final decision (COFD) denying the claim of appellant, South Bay Boiler Repair, Inc. (SBBR), for alleged constructive changes and delays. The claim arises under a delivery order (DO) issued by the Navy under a firm-fixed-price, indefinite-delivery/indefinite-quantity contract for boatyard services. The DO was for ship repair and preservation services, including the removal and application of paint and other coatings, on a small vessel identified as Landing Craft Utility (LCU) No. 1631. Appellant maintains that the ship repair contract failed to comply with 10 U.S.C. § 731 l(a)(l) because it did not adequately identify "the types and amounts of hazardous wastes that are required to be removed by the contractor from the vessel."

The parties elected to proceed without an evidentiary hearing, via Board Rule 11, with each side relying upon the Rule 4 file and its supplements and submitting opening and reply briefs in accordance with an agreed-upon schedule. For the reasons set forth below, we conclude that the plain language of the ship repair contract - and specifically the requirements of DO 0007 - satisfied the requirements of 10 U.S.C. § 7311 and placed appellant on notice of the presence of toxic heavy metals in the paint and coatings onboard LCU 163 1. We deny the appeal.

FINDINGS OF FACT

I. The Parties and the Contract

1. Appellant SBBR is a small business ship repair contractor located in National City, California (app. supp. R4, tab 94, Bowen decl. ii 1).

2. SBBR uses subcontractors to perform most of the preservation work required by a Navy ship repair contract. Preservation work involves removing existing coatings from the surfaces of the vessel and applying new coatings to the surfaces. Most preservation subcontractors use a sandblasting process to remove the majority of the existing coatings from the ship (app. supp. R4, tab 94, Bowen decl. ii 4).

3. On 3 June 2009, the Navy's Southwest Regional Maintenance Center in San Diego, California (SWRM or government), awarded a firm-fixed-price, indefinite-delivery/indefinite-quantity (IDIQ) Contract No. N55236-09-D-OO 17 for boatyard services to SBBR (the contract) (R4, tab 1at1-2of121).

4. On 6 September 2012, the government issued Request for Proposal (RFP) No. 0168 for work described in contract line item numbers (CLINs) 0067, 0082, 0083, 0087, and 0088 for LCU 1631 (R4, tab 21 at 1 of 7).

5. At CLIN 0067, the RFP states: "Firm-Fixed Price. Prepare for and accomplish Specification Package SSSD-504-12 for LCU 1631 [the specifications], attached." (R4, tab 21 at 1, 4)

6. While the RFP was pending, the government issued four pre-proposal amendments to RFP 0168 (R4, tabs 23-26).

7. Also while the RFP was pending, SBBR asked a question concerning the government's estimate of hazardous waste set forth in paragraph 3.5 of Work Item 077-01-001. SBBR asked:

Since the requirements to accomplish removals differ greatly contractors utilize the government's quantities in generating their estimates of removal costs. If the amounts exceed the government's expectations and a mod is issued to cover the additional disposal costs it is the contractor's

2 . right to include additional expenses for labor, lab fees, analysis, etc. into the contract mod. Please advise.

(App. supp. R4, tab 78)

8. Amendment No. 1, dated 13 September 2012, contains, among other things, the government's response to the foregoing question posed by SBBR. Restated by the government, "QUESTION 1" reads as follows:

ITEM NO. 077-01-001 (Hazardous Waste Produced on Naval Vessels): Hazardous waste item Para 4.1 states: "Hazardous waste generated during the actual performance of this work may vary in type and amount from waste listed in 3.5 which may result in renegotiation for credit or increase pursuant to paragraph (b) of 2:4."

If the amount of hazardous waste exceeds the Government's expectations and a contract modification is issued to cover the additional disposal costs, is it the contractors right to include additional expenses for labor, lab fees, analysis, etc. into the contract modification?

(R4, tab 23 at 2 of 5) The Answer to Question 1 in the amendment states: "Yes, Government uses historical data to estimate and provide the amount of hazardous waste. Anything beyond the amount listed will be negotiated and addressed by a contract modification." (Id.) The historical data was based upon work on similar vessels, as verified by interviews with contractors and on a formula that uses surface area data to predict blast residue amounts (app. supp. R4, tab 98, King dep. at 46-47).

9. The government permitted contractors to take paint chip samples before submitting their proposals (app. supp. R4, tab 98, King dep. at 107-08).

10. SBBR's project manager, Donald Bowen, inspected LCU 1631 before SBBR submitted its proposal RFP. He did not take samples of the coatings on the vessel. (App. supp. R4, tab 143 at 1-2, 4)

11. Appellant admitted that it "based [its] hazardous paint removal costs on the small quantities of hazardous paint and paint chips [the government] included in Work Item 077-01-001" (app. br. at 108).

12. Appellant's estimator, Mr. Bowen, also acknowledges that mechanical cleaning processes (hammer, wire brush, needle guns) would produce paint chips as a

3 by-product, rather than spent abrasive material (app. supp. R4, tab 129, Bowen dep. at 70).

13. Mr. Bowen states that he was aware of the Navy's estimate of 275 tons of spent abrasive blast material contaminated with a known hazardous waste, but that he did not expect to generate that much because appellant's subcontractor, Pacific Yacht Refitters, Inc. (PYR), would be using a different process to remove the paint (app. supp. R4, tab 129, Bowen dep. at 63-64).

14. Mr. Bowen testified that, because PYR would be using steel grit, which could be recycled 300 - 500 times, the removal process would produce far less spent abrasive waste than the government's estimate of 275 tons (app. supp. R4, tab 129, Bowen dep. at 66-68).

15. Appellant understood PYR's estimate to include the cost of disposing of any spent abrasive material generated during the contract (app. supp. R4, tab 133, Wilkerson dep. at 21-29).

16. On 25 September 2012, SBBR submitted a proposal in response to RFP No. 0168 with a firm-fixed price of $2,492,859 for CLIN 0067 (plus $2,080 for CLINs 0082 and 0083) for the work outlined in Specification Packages SSD-504-12 for LCU 1631 (R4, tab 27 at 4-5).*

17. SBBR's proposal included a quote from its intended subcontractor, PYR, with $15,625.00 next to the description: "077-01-001 HAZARDOUS [WASTE] PRODUCED ON NAVAL VESSELS; CONTROL (SURF ACE PREPARATION RELATED ONLY, DOES NOT INCLUDE LIQUID PAINT WASTE)" (R4, tab 27 at 24).

18.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Winter v. Cath-dr/Balti Joint Venture
497 F.3d 1339 (Federal Circuit, 2007)
International Data Products Corp. v. United States
492 F.3d 1317 (Federal Circuit, 2007)
Lynteq, Inc. v. The United States
976 F.2d 693 (Federal Circuit, 1992)
Coast Federal Bank, Fsb v. United States
323 F.3d 1035 (Federal Circuit, 2003)
Nvt Technologies, Inc. v. United States
370 F.3d 1153 (Federal Circuit, 2004)
Metal Trades, Inc. v. United States
810 F. Supp. 689 (D. South Carolina, 1992)
Lakeshore Engineering Services, Inc. v. United States
748 F.3d 1341 (Federal Circuit, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
South Bay Boiler Repair, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/south-bay-boiler-repair-inc-asbca-2017.