Metal Trades, Inc. v. United States

810 F. Supp. 689, 38 Cont. Cas. Fed. 76,503, 23 Envtl. L. Rep. (Envtl. Law Inst.) 21235, 1992 U.S. Dist. LEXIS 19989, 1992 WL 386230
CourtDistrict Court, D. South Carolina
DecidedAugust 3, 1992
DocketCiv. A. 2:90-0497-1
StatusPublished
Cited by3 cases

This text of 810 F. Supp. 689 (Metal Trades, Inc. v. United States) is published on Counsel Stack Legal Research, covering District Court, D. South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Metal Trades, Inc. v. United States, 810 F. Supp. 689, 38 Cont. Cas. Fed. 76,503, 23 Envtl. L. Rep. (Envtl. Law Inst.) 21235, 1992 U.S. Dist. LEXIS 19989, 1992 WL 386230 (D.S.C. 1992).

Opinion

ORDER

HAWKINS, Chief Judge.

This action is on appeal from a decision of the Armed Services Board of Contract *691 Appeals (ASBCA) pursuant to the Contract Disputes Act, 41 U.S.C. § 601 et seq.

Initially, a timely appeal was lodged with the Federal Circuit Court of Appeals under 41 U.S.C. § 607(g). The Federal ■ Circuit transferred the case to this court pursuant to 41 U.S.C. § 603, which provides in pertinent part that “appeals under paragraphs (g) of § 607 of this Title ..., arising out of maritime contracts, shall be governed by Chapter 20 or 22 of Title 46 as applicable, to the extent that those Chapters are not inconsistent with this Chapter.” 1

The SAA and PVA are not set up as Appellate remedies, but rather as remedies of first resort. Thus, the applicable standard of review is unclear. However, the factual disputes are limited, and regardless of what the standard of review is (i.e., whether substantial evidence exists to support the ASBCA findings, or whether the ASBCA finding was in accordance with the preponderance of the evidence, or, for that matter, whether this court is free to make de novo findings) the result is the same.

I

BACKGROUND FACTS AND SUMMARY OF PROCEEDINGS AND RESOLUTION OF THE CLAIM BELOW

On April 14, 1987, Appellant and Appellee entered into a repair and maintenance contract for a U.S. naval vessel, the USS SANTA BARBARA. The contract was issued as Job Order No. 115. Portions of the contract required Appellant to replace the vessel’s fire pump and soot blower piping. In the course of these replacements, insulation and lagging material were encountered. As it turned out, the insulation and lagging material contained asbestos. The presence of asbestos necessitated special removal, treatment, handling, transportation, storage, and disposal techniques. The special techniques were mandated by law. Because of these special requirements, Appellant was forced to modify upwardly the subcontract under which the fire pumps and blower piping was replaced because of the added costs incurred by its subcontractor in complying with the law relating to asbestos removal, treatment, handling, transportation, storage and disposal. The cost to Appellant was significantly greater than its bid estimate as to those items.

Appellant sought an adjustment to the contract price based on the increased cost of treatment, removal, storage, transportation, and disposal of the asbestos-containing material. Its claim is bottomed on 10 U.S.C. § 7311, enacted November 14, 1986. Section 7311, which applies only to repair and maintenance contracts for naval vessels, requires in such contracts that the Navy identify and quantify the type and amount of hazardous wastes expected to be generated during performance of the contract. In cases where the contractor, during performance of the contract, discovers hazardous wastes different in type or amount from those identified in the contract, § 7311 requires that the Navy shall renegotiate the contract. Asbestos was not positively identified and was not in any manner quantified by the Navy in Job Order No. 115. Even so, Appellee refused to renegotiate the contract after discovery of the asbestos-containing material, insisting that asbestos is not a hazardous waste that the Navy is required to identify and quantify under § 7311, and further insisting that Appellant was not surprised by the fact that asbestos was contained in the insulation and lagging and thus was not harmed by Appellee’s failure to identify and quantify it.

As a result of the Appellee’s refusal to renegotiate, Appellant, pursuant to the Contract Disputes Act, commenced an action with the Armed Services Board of Contract Appeals (“ASBCA”). A full hearing was conducted December 1, 1988, at which the parties produced both testimony and exhibits. The record of the proceedings is included in a Joint Appendix compiled for this appeal.

*692 On February 9, 1989, the ASBCA issued its Order finding that asbestos is a hazardous waste that must be identified and quantified under § 7311, and finding that Appellee by failing to quantify the asbestos, breached its statutory duty imposed by § 7311. Despite these findings, the Order concluded that Appellant is not entitled to renegotiation of the contract because of a standard item to the contract, Standard Item No. 009-10. This standard item provides that all insulation and lagging on board the ship is to be considered asbestos. Although Standard Item No. 009-10 did not positively identify the insulation and lagging as containing asbestos, and although it completely failed to quantify it, the ASBCA concluded that “[ajppellant here cannot reasonably argue that it was surprised by the amount of asbestos actually found,” in light of Standard Item No. 009-10.

II

FACTS CONCLUSIVELY ESTABLISHED IN THE OPINION OR BY STIPULATION OF FACTS BETWEEN THE PARTIES

The following pertinent facts were either established by the ASBCA’s findings, or were not challenged on appeal by Appellee or were agreed to by Appellee in a stipulation of facts (“S.F.”) submitted at the hearing. Thus, these facts are conclusively established as against Appellee without further inquiry.

1. Asbestos was not identified or quantified in Job Order No. 115. (App. p. 5, Opinion of ASBCA).

2. The presence of asbestos in lagging cannot be determined by visual inspection. (App. pp. 5 & 18; Order of ASBCA; S.F. No. 13).

3. Asbestos in insulation generally cannot be determined by visual inspection since most insulation is hidden from view. (App. p. 8; Order of ASBCA).

4. Asbestos is recognized as a serious health hazard when its fibers are ingested or inhaled. Usually exposure occurs when asbestos fibers are produced as a fine dust and become airborne. Asbestosis is pulmonary fibrosis caused by accumulation of asbestos fibers in the lungs. (App. pp. 5 and 18; Order of ASBCA; S.F. No. 9).

5. The cost of treatment, removal, handling, transporting, and disposing of asbestos is ten times as costly as that of ordinary insulation. (App. pp. 7-8; Order of ASBCA).

6. Asbestos must be treated properly, removed properly, handled properly, transported properly and disposed of properly to insure that the asbestos fiber which is hazardous to human health does not get airborne. (App. p. 7; Order of ASBCA).

7. The Navy generally stopped using asbestos on its vessels in 1978. (App. p. 5; Order of ASBCA).

Ill

FACTS ESTABLISHED THROUGH UNCONTRADICTED EVIDENCE

The following facts are among the important facts established by evidence offered by Appellant, uncontradicted and unchallenged by Appellee:

1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

South Bay Boiler Repair, Inc.
Armed Services Board of Contract Appeals, 2017
Harris v. AC & S, Inc.
915 F. Supp. 1420 (S.D. Indiana, 1995)
Castor v. United States
883 F. Supp. 344 (S.D. Indiana, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
810 F. Supp. 689, 38 Cont. Cas. Fed. 76,503, 23 Envtl. L. Rep. (Envtl. Law Inst.) 21235, 1992 U.S. Dist. LEXIS 19989, 1992 WL 386230, Counsel Stack Legal Research, https://law.counselstack.com/opinion/metal-trades-inc-v-united-states-scd-1992.