Soda Mountain Wilderness Council v. United States Bureau of Land Management

607 F. App'x 670
Court of Appeals for the Ninth Circuit·Decided April 20, 2015·No. 13-35438·Unpublished

Opinions

MEMORANDUM **

Soda Mountain Wilderness Council and several other environmental organizations (collectively “Soda Mountain”) appeal the district court’s grant of summary judgment in favor of the Bureau of Land Management (“BLM”). Soda Mountain challenges the validity of the BLM’s Environmental Assessment (“EA”), and Finding of No Significant Impact (“FONSI”), for the proposed Sampson Cove Forest Management Project (the “Project”). Soda Mountain alleges that the BLM committed several violations of the National Environmental Policy Act (“NEPA”), 42 U.S.C. §§ 4321-4370(d), and the Federal Land Policy Management Act (“FLPMA”), 43 U.S.C. § 1701 et seq. We have jurisdiction under 28 U.S.C. § 1291, and we affirm in part and reverse in part.

1. We review de novo a district court’s ruling on cross motions for summary judgment. Guatay Christian Fellowship v. Cnty. of San Diego, 670 F.3d 957, 970 (9th Cir.2011). Judicial review of an agency’s compliance with NEPA and FLPMA is governed by the Administrative Procedures Act, 5 U.S.C. §§ 701-06; Klamath Siskiyou Wildlands Ctr. v. Boody, 468 F.3d 549, 554 (9th Cir.2006). Agency decisions may be set aside only if they are “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.” Id. (quoting 5 U.S.C. § 706(2)(A)). “Agency action is valid if the agency considered the relevant factors and articulated a rational connection between the facts found and the choices made.” Lands Council v. McNair, 629 F.3d 1070, 1074 (9th Cir.2010) (internal quotation marks omitted).

2. We agree with the district court that the BLM adequately assessed the Project area’s wilderness characteristics. The EA relies on a 2006 wilderness survey prepared by the BLM, which addressed the definitional elements of wilderness in the Wilderness Act, 16 U.S.C. § 1131(c). The BLM’s decision to rely on a report that was four years old when it issued the EA was reasonable. Moreover, the BLM’s assessment of wilderness characteristics as described in the 2006 survey warrants our deference. See Native Ecosystems Council v. Weldon, 697 F.3d 1043, 1053 (9th Cir.2012). In determining that the Project would not impact the area’s wilderness characteristics, the BLM’s decision was neither arbitrary nor capricious.

[672]*6723. The BLM’s decision not to analyze the effects of the Project on the potential expansion of the Cascade Siskiyou National Monument did not violate NEPA. An EA is required to consider the “direct, indirect, and cumulative impacts” of an action on the environment. Ctr. for Envtl. Law & Policy v. U.S. Bureau of Reclamation (“Envtl. Law”), 655 F.3d 1000, 1006 (9th Cir.2011). Here, monument expansion was a “remote and highly speculative consequence[ ]” that did not warrant analysis in the EA. See Ground Zero Ctr., for Non-Violent Action v. U.S. Dep’t of the Navy, 383 F.3d 1082, 1090 (9th Cir.2004). The district court properly granted summary judgment on this issue.

4. When determining whether an action requires an Environmental Impact Statement (“EIS”), an agency must consider “[wjhether the action is related to other actions with individually insignificant but cumulatively significant impacts.” Envtl. Protection Info. Ctr. v. U.S. Forest Serv. (“EPIC”), 451 F.3d 1005, 1014 (9th Cir.2006) (quoting 40 C.F.R. § 1508.27(b)(7)). “Projects that are ‘reasonably foreseeable’ should be included in the cumulative effects analysis.” Id. (quoting 40 C.F.R. § 1508.7). However, “projects need not be finalized before they are reasonably foreseeable.” N. Plains Res. Council, Inc. v. Surface Transp. Bd., 668 F.3d 1067, 1078 (9th Cir.2011).

5. Soda Mountain argues that the BLM violated NEPA because the EA’s cumulative impact analysis did not include any discussion of the Cottonwood Forest Management project. As the record reflects, this project was reasonably foreseeable at the time the BLM issued the EA for the Project. See id. Six months before the BLM issued the Project’s EA, an interdisciplinary team (“IDT”) decided to “spread the due dates out more for the 2011 timber sales,” including changing a “specialist due date” for the Cottonwood EA. This note indicates that the Cottonwood project was certain to occur. Moreover, less than one month before the BLM issued the Project’s EA, many elements of the Cottonwood project were already firmly established. For example, a team meeting document includes the note that “[syl-viculture prescriptions will be similar to” another project’s “with a disease management component.” The document also states that determinations regarding Northern Spotted Owl habitats would be complete within the next month. Given the focus on details, implementation of the Cottonwood project was not in question. Indeed, just two months after the BLM issued the Project’s EA, it notified the public of the Cottonwood project. This timing is consistent with the January and June 2010 IDT notes, and leaves little doubt that the Cottonwood project was reasonably foreseeable in July 2010. Thus, we conclude that the record demonstrates that the Cottonwood project was reasonably foreseeable. Accordingly, we vacate the district court’s ruling on this issue and direct the court to remand to the BLM for further consideration of its cumulative impact analysis regarding the Cottonwood project, and whether that analysis affects its decision not to issue an EIS.

6. Soda Mountain also argues that the EA’s cumulative impact analysis of the Shale City project was inadequate. We disagree. The cumulative impact analysis of the Shale City project was sufficient under NEPA because the EA contained “some quántifíed or detailed information.” Kern v. U.S. Bureau of Land Mgmt., 284 F.3d 1062, 1075 (9th Cir.2002). In particular, the EA noted that the Shale City project was of limited size, no new roads would be built in the project area, the project was not expected to affect special status wildlife species, and no direct or [673] indirect effects to aquatic habitat were anticipated as a result of the project.

Free access — add to your briefcase to read the full text and ask questions with AI

Soda Mountain Wilderness Council v. United States Bureau of Land Management, 607 F. App'x 670 (9th Cir. 2015).

607 F. App'x 670 (Soda Mountain Wilderness Council v. United States Bureau of Land Management) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Kleppe v. Sierra Club
427 U.S. 390 (Supreme Court, 1976)
Lands Council v. McNair
629 F.3d 1070 (Ninth Circuit, 2010)
Guatay Christian Fellowship v. County of San Diego
670 F.3d 957 (Ninth Circuit, 2011)
Tri-Valley Cares v. U.S. Department of Energy
671 F.3d 1113 (Ninth Circuit, 2012)
Destinni Mardesich v. Matthew Cate
668 F.3d 1164 (Ninth Circuit, 2012)
Klamath Siskiyou Wildlands Center v. Boody
468 F.3d 549 (Ninth Circuit, 2006)
Native Ecosystems Council v. Leslie Weldon
697 F.3d 1043 (Ninth Circuit, 2012)
Oregon Natural Resources Council Fund v. Brong
492 F.3d 1120 (Ninth Circuit, 2007)
John Jones, III v. National Marine Fisheries Serv
741 F.3d 989 (Ninth Circuit, 2013)
Northern Alaska Environmental Center v. Kempthorne
457 F.3d 969 (Ninth Circuit, 2006)