Snow v. Harnischfeger Corp

Court of Appeals for the First Circuit·Decided December 29, 1993·No. 93-1489·Published

Opinion

UNITED STATES COURT OF APPEALS FOR THE FIRST CIRCUIT

No. 93-1489

DAVID SNOW, ET AL.,

Plaintiffs, Appellants,

v.

HARNISCHFEGER CORPORATION,

Defendant, Appellee.

APPEAL FROM THE UNITED STATES DISTRICT COURT

FOR THE DISTRICT OF MASSACHUSETTS

[Hon. Douglas P. Woodlock, U.S. District Judge]

Before

Torruella and Stahl, Circuit Judges,

and DiClerico,* District Judge.

Walter A. Costello, Jr. with whom Julie M. Conway and Costello,

Barrett and Gonthier, P.C. were on brief for appellants.

David M. Rogers with whom Richard P. Campbell and Campbell &

Associates, P.C. were on brief for appellee.

December 29, 1993

*Of the District of New Hampshire, sitting by designation.

DiClerico, District Judge. Plaintiffs David Snow, DiClerico, District Judge.

Linda Snow, Jason Snow and Kevin Snow brought an action

against defendant Harnischfeger Corporation

("Harnischfeger") alleging defective design and negligence

after the trolley wheel of an Harnischfeger crane injured

David Snow. Harnischfeger moved for summary judgment,

claiming the Massachusetts real estate statute of repose

barred the action. The district court agreed and granted

summary judgment. We affirm.

I

BACKGROUND

In March 1973, Rust Engineering Company ("Rust"),

an engineering and construction firm acting as agent for

Refuse Energy Systems Company ("RESCO"), engaged

Harnischfeger to assist in the design and manufacture of two

thirteen-ton overhead cranes for use at RESCO's Saugus,

Massachusetts trash-to-energy plant.1 The cranes are used

1Harnischfeger has designed and manufactured overhead cranes since 1906 and has built more than 24,000 overhead trolley cranes. Harnischfeger customizes each overhead trolley crane it manufactures. Overhead cranes such as those built by Harnischfeger are generally considered heavy-duty machinery for specific production purposes and used by many industries to lift and move heavy objects.

-2- 2

to move trash into trash feed hoppers where the trash is

burned and steam is generated and converted into

electricity. Rust incorporated the cranes into the plant's

buildings as part of the original construction.

Harnischfeger was not involved in the design or construction

of the RESCO facility, nor did Harnischfeger install the

cranes.

On December 29, 1987, the trolley wheel of one of

the overhead cranes severed David Snow's third, fourth and

fifth finger and a portion of his right hand. At the time,

Snow was working at the Saugus facility. The Snow family

brought an action in Essex Superior Court, Commonwealth of

Massachusetts, alleging the crane was unsafe due to

Harnischfeger's failure to equip the trolley with wheel

guards and rail sweeps, automatic audio or visual movement

alarms, a proper lock-out system or kill switch, and

Harnischfeger's failure to warn of inherent risks.2

Harnischfeger removed the action to the district court

pursuant to 28 U.S.C. 1446, and moved for summary judgment

2In their amended complaint, the Snows charge Harnischfeger with defective design, negligence, breach of express warranty and breach of the implied warranty of merchantability.

-3- 3

under the Massachusetts real estate statute of repose

("statute").

The statute, Mass. Gen. Laws Ann. ch. 260, 2B

(West 1992) ("M.G.L. c. 260, 2B"), provides:

Action [sic] of tort for damages arising out of any deficiency or neglect in the design, planning, construction or general administration of an improvement to real property . . . shall be commenced only within three years next after the cause of action accrues; provided, however, that in no event shall such actions be commenced more than six years after the earlier of the dates of: (1) the opening of the improvement to use; or (2) substantial completion of the improvement and the taking of possession for occupancy by the owner.3

Id.4 The district court found Harnischfeger was included

in the class of actors protected under the statute and

granted the summary judgment motion.5

3Massachusetts courts have construed the statute to apply to implied breach of warranty claims where the underlying cause of action is the same as the tort claim. Klein v. Catalano,

437 N.E.2d 514, 526 & n.19 (Mass. 1982); see also Anthony's

Pier Four, Inc. v. Crandall Dry Dock Eng'rs, Inc., 489

N.E.2d 172, 175 (Mass. 1986).

4M.G.L. c. 260, 2B was last revised in 1984. Id.

5The district court barred the Snows' action noting the RESCO plant became operational in 1975 and the Snows did not institute their action until 1990. In 1986, Harnischfeger designed two replacement trolleys. The Snows do not argue that we should measure the application of the statute from the date Harnischfeger designed the replacement trolleys.

-4- 4

On appeal the Snows argue (1) the district court

improperly granted summary judgment where genuine issues of

material fact remained; (2) the district court impermissibly

extended repose to the manufacturer of a machine thereby

changing Massachusetts' product liability law; (3) the

district court improperly found Harnischfeger was a

protected actor within the meaning of M.G.L. c. 260, 2B;

and (4) questions of local law are central to the

disposition of the appeal and should be certified to the

Massachusetts Supreme Judicial Court ("SJC").

II

DISCUSSION

Standard of Review

"We review a grant of summary judgment de novo,

using the same criteria incumbent upon the district court."

Gaskell v. Harvard Coop. Soc'y, 3 F.3d 495, 497 (1st Cir.

1993) (citing Vanhaaren v. State Farm Mut. Auto. Ins. Co.,

989 F.2d 1, 3 (1st Cir. 1993); High Voltage Eng'g Corp. v.

Federal Ins. Co., 981 F.2d 596, 598 (1st Cir. 1992); Pedraza

v. Shell Oil Co., 942 F.2d 48, 50 (1st Cir. 1991), cert.

denied, U.S. , 112 S. Ct. 993 (1992). The role of

summary judgment is "to pierce the boilerplate of the

-5- 5

pleadings and assay the parties' proof in order to determine

whether trial is actually required." Wynne v. Tufts Univ.

Sch. of Medicine, 976 F.2d 791, 794 (1st Cir. 1992). It is

appropriate only if "the pleadings, depositions, answers to

interrogatories, and admissions on file, together with the

affidavits, if any, show that there is no genuine issue as

to any material fact and that the moving party is entitled

to judgment as a matter of law." Fed. R. Civ. P. 56(c).

The burden is on the moving party to establish the lack of a

genuine, material factual issue, Finn v. Consolidated Rail

Free access — add to your briefcase to read the full text and ask questions with AI

Snow v. Harnischfeger Corp, (1st Cir. 1993).

Snow v. Harnischfeger Corp (Snow v. Harnischfeger Corp) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Michael A. Caputo v. Boston Edison Company
924 F.2d 11 (First Circuit, 1991)
Samuel Mesnick v. General Electric Company
950 F.2d 816 (First Circuit, 1991)
Steven Wynne v. Tufts University School of Medicine
976 F.2d 791 (First Circuit, 1992)
Milligan v. Tibbetts Engineering Corp.
461 N.E.2d 808 (Massachusetts Supreme Judicial Court, 1984)
McDonough v. Marr Scaffolding Co.
591 N.E.2d 1079 (Massachusetts Supreme Judicial Court, 1992)
Parent v. Stone & Webster Engineering Corp.
556 N.E.2d 1009 (Massachusetts Supreme Judicial Court, 1990)
Anthony's Pier Four, Inc. v. Crandall Dry Dock Engineers, Inc.
489 N.E.2d 172 (Massachusetts Supreme Judicial Court, 1986)
Klein v. Catalano
437 N.E.2d 514 (Massachusetts Supreme Judicial Court, 1982)
Raffel v. Perley
437 N.E.2d 1082 (Massachusetts Appeals Court, 1982)
Dighton v. FED. PAC. ELEC. CO. SERT, JACKSON & ASSOC.
506 N.E.2d 509 (Massachusetts Supreme Judicial Court, 1987)
Snow v. Harnischfeger Corp.
823 F. Supp. 22 (D. Massachusetts, 1993)
Finn v. Consolidated Rail Corp.
782 F.2d 13 (First Circuit, 1986)
Pedraza v. Shell Oil Co.
942 F.2d 48 (First Circuit, 1991)