Snider v. Dickinson Elks Building, LLC

2017 ND 31, 889 N.W.2d 867, 2017 WL 632883, 2017 N.D. LEXIS 12
CourtNorth Dakota Supreme Court
DecidedFebruary 16, 2017
Docket20160145
StatusPublished
Cited by3 cases

This text of 2017 ND 31 (Snider v. Dickinson Elks Building, LLC) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Snider v. Dickinson Elks Building, LLC, 2017 ND 31, 889 N.W.2d 867, 2017 WL 632883, 2017 N.D. LEXIS 12 (N.D. 2017).

Opinion

Sandstrom, Surrogate Judge.

[¶ 1] Rick Snider and Janan Snider, doing business as RJ Snider Construction (“Snider”), appeal from a summary judgment forfeiting a construction lien against the property that formerly housed the Dickinson Elks Lodge but is now owned by private investors, the Dickinson Elks Building, LLC (“DEB”), and prohibiting Snider from recording additional liens against the property without performing additional work. We affirm.

I

[¶ 2] In December 2011, Snider contracted with Beaver Brinkman to perform work on real property owned by DEB. Snider recorded a construction lien in January 2013 for $198,255.08 against the property after it did not get paid for all of its work performed between December 2011 and October 2012. In May 2014, DEB served Snider with a demand under N.D.C.C. § 35-27-25 to begin a lawsuit to enforce the lien and record a lis pendens within thirty days of the demand. Snider sued DEB in June 2014, seeking foreclosure of the construction lien. Snider recorded a notice of lis pendens on July 28, 2014.

[¶ 3] DEB moved for summary judgment, arguing Snider did not have a valid construction lien because Snider did not record a lis pendens within thirty days of receiving the demand to enforce the lien. The district court granted the motion and entered a judgment forfeiting Snider’s construction lien because Snider did not record a lis pendens within thirty days of receiving DEB’s demand to enforce the lien as required under N.D.C.C. § 35-27-25.

*869 [¶ 4] In February 2015, two days after the district court entered judgment forfeiting Snider’s construction lien, Snider recorded another construction lien for $174,642.09 against DEB’s property for work performed between March 2012 and November 2012. After Snider sued to enforce the lien, DEB moved for summary judgment, arguing the district court’s previous forfeiture of Snider’s lien prevented Snider from recording another lien pertaining to the same work performed on the property. The court granted the motion, concluding that although the lien amounts differed, both of Snider’s recorded liens were related to the same work performed on DEB’s property. The court also concluded its earlier forfeiture of Snider’s lien under N.D.C.C. § 35-27-25 prohibited Snider from recording another lien for the same work.

[¶ 5] The district court had jurisdiction under N.D. Const, art. VI, § 8, and N.D.C.C. § 27-05-06. Snider’s appeal is timely under N.D.R.App.P. 4(a). This Court has jurisdiction under N.D. Const, art. VI, §§ 2 and 6, and N.D.C.C. § 28-27-01.

II

[¶ 6] Snider argues the district court erred in granting summary judgment to DEB. Snider argues a lien claimant whose construction lien is forfeited under N.D.C.C. § 35-27-25 can record another construction lien for the same work performed.

[¶ 7] The standard of review for summary judgment is well-established:

Summary judgment under N.D.R.Civ.P. 56(c) is a procedural device for the prompt and expeditious disposition of a lawsuit without a trial if either litigant is entitled to judgment as a matter of law and if no dispute exists as to either the material facts or the infer-enees to be drawn from undisputed facts, or if resolving factual disputes will not alter the result. Whether a district court properly granted summary judgment is a question of law that we review de novo on the record.

Nichols v. Goughnour, 2012 ND 178, ¶ 9, 820 N.W.2d 740 (citations and quotations omitted). Here neither party argues disputed issues of material fact exist. Snider’s arguments involve the interpretation of N.D.C.C. § 35-27-25, relating to enforcement of a construction lien.

III

[¶ 8] Snider argues the district court erred in its interpretation of N.D.C.C. § 35-27-25.

[¶9] Statutory interpretation is a question of law fully reviewable on appeal. Kittleson v. Grynberg Petroleum Co., 2016 ND 44, ¶ 22, 876 N.W.2d 443. Words in a statute are given their plain, ordinary, and commonly understood meaning, unless defined by statute or unless a contrary intention plainly appears. N.D.C.C. § 1-02-02. The language of a statute must be interpreted in context and according to the rules of grammar. N.D.C.C. § 1-02-03. Technical words having acquired a “peculiar and appropriate meaning in law ... must be construed according to such peculiar and appropriate meaning or definition.” Id. It is presumed that the entire statute is intended to be effective, so that no part of the statute is rendered inoperative or superfluous. N.D.C.C. § 1-02-38(2) and (4). We presume the legislature did not intend an unreasonable result or unjust consequences. N.D.C.C. § 1-02-38(3).

[¶ 10] Under N.D.C.C. § 35-27-02, “[a]ny person that improves real estate ... has a lien upon the improvement and upon the land on which the improvement is situated ... for the price or value of such *870 contribution.” A construction lien attaches and takes effect “from the time the first item of material or labor is furnished upon the premises for the beginning of the improvement.” N.D.C.C. § 35-27-03. Recording a lien statement “describing the property and stating the amount due, the dates of the first and last contribution, and the person with which the claimant contracted” with the county recorder perfects the lien as against third parties. N.D.C.C. § 35-27-13. A lien may not be recorded “more than three years after the date of the first item of material is furnished.” N.D.C.C. § 35-27-14. Under N.D.C.C. ch. 35-27, a construction lien is not created upon perfection, it arises and attaches as a matter of law when work begins on the property. See N.D.C.C. §§ 35-27-02 and 35-27-03.

[¶ 11] Section 35-27-25, N.D.C.C., provides:

Upon written demand by or on behalf of the owner which has been delivered to the lienor and filed with the county recorder, suit must be commenced and filed and a lis pendens as provided in chapter 28-05 must be recorded within thirty days after the date of delivery of the demand or the lien is forfeited. This thirty-day requirement applies regardless of the method of delivery and additional time may not be allowed based on the method of delivery. The demand must inform the lienor that if suit is not commenced and a lis pendens recorded within the thirty days required under this section, the lien is forfeited. A lien is not valid, effective, nor enforceable, unless the lienor commences an action and records with the county recorder a lis pendens within three years after the date of recording of the lien. If a lis pendens is not recorded within the limitations provided by this section, the lien is deemed satisfied.

[¶ 12] Snider argues the lien referred to in the phrase “the lien is forfeited” is the recorded lien under N.D.C.C. § 35-27-13, and not the lien created and attached as a matter of law under N.D.C.C. §§ 35-27-02 and 35-27-03. Snider argues the district court forfeited its recorded lien under N.D.C.C. § 35-27-25 for failing to comply with DEB’s written demand to enforce the lien. Snider argues N.D.C.C. § 35-27-25 did not prohibit it from recording another construction lien against the property.

[¶ 13] The district court addressed Snider’s arguments:

The Court interprets the language of N.D.C.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kutcka v. Gateway Building Systems
2023 ND 91 (North Dakota Supreme Court, 2023)
Snider v. Dickinson Elks Building, LLC
2017 ND 31 (North Dakota Supreme Court, 2017)
State v. Lee
645 N.W.2d 459 (Supreme Court of Minnesota, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
2017 ND 31, 889 N.W.2d 867, 2017 WL 632883, 2017 N.D. LEXIS 12, Counsel Stack Legal Research, https://law.counselstack.com/opinion/snider-v-dickinson-elks-building-llc-nd-2017.