North Dakota Statutes
§ 35-27-13 — How lien perfected - Construction lien recorded
North Dakota § 35-27-13
This text of North Dakota § 35-27-13 (How lien perfected - Construction lien recorded) is published on Counsel Stack Legal Research, covering North Dakota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Bluebook
N.D. Cent. Code § 35-27-13 (2026).
Text
Every person desiring to perfect the person's lien shall record with the recorder of the
county in which the property to be charged with the lien is situated, within ninety days after all
the person's contribution is done, and having complied with the provisions of this chapter, a lien
describing the property and stating the amount due, the dates of the first and last contribution,
and the person with which the claimant contracted. Unless the owner of the freehold estate also
is the owner of the leasehold for wind turbines or an electric energy conversion facility for which
the labor, materials, or services were supplied, if a recorded lien is for a wind turbine or
associated facility under section 17-04-07, the recorded lien must contain the following
statement in at least sixteen-point t
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Snider v. Dickinson Elks Building, LLC
2017 ND 31 (North Dakota Supreme Court, 2017)
Nearby Sections
15
§ 35-01-01
Scope of statutes relating to liens§ 35-01-02
Definition of lien§ 35-01-05.1
When security interest in vehicle valid§ 35-01-05.2
Priority of liens securing future advances§ 35-01-06
Obligations not in existence§ 35-01-08
Lien transfers no title§ 35-01-09
Recorder to file and index lienCite This Page — Counsel Stack
Bluebook (online)
North Dakota § 35-27-13, Counsel Stack Legal Research, https://law.counselstack.com/statute/nd/35-27-13.