SNET Cellular, Inc. v. Angell

99 F. Supp. 2d 190, 2000 U.S. Dist. LEXIS 7497, 2000 WL 730399
CourtDistrict Court, D. Rhode Island
DecidedJune 2, 2000
DocketC.A.97-0597T
StatusPublished
Cited by12 cases

This text of 99 F. Supp. 2d 190 (SNET Cellular, Inc. v. Angell) is published on Counsel Stack Legal Research, covering District Court, D. Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
SNET Cellular, Inc. v. Angell, 99 F. Supp. 2d 190, 2000 U.S. Dist. LEXIS 7497, 2000 WL 730399 (D.R.I. 2000).

Opinion

Memorandum and Order

TORRES, Chief Judge.

MEMORANDUM AND ORDER. .191

Background.192

Contentions of the Parties.193

The Statutes.193

The Telecommunications Act.193

R.I. Gen. Laws § 45-24-69 .194

Standard of Review.194

The Summary Judgment Standard .195

Discussion.195

I.The No “Substantial Evidence” Claim .195

A. Compatibility with Neighboring Uses.196

B. Consistency with Purposes of Comprehensive Plan.196

C. Compatibility with Orderly Development of Town.196

D. Environmental Compatibility.197

II.The Prohibition of Services Claim.197

III.The Untimeliness Claim .198

Conclusion.199

SNET Cellular, Inc. (“SNET”) and the owners of land that SNET proposes to lease for the purpose of constructing and operating a cellular communications tower brought this action pursuant to the Federal Telecommunications Act, 47 U.S.C. § 332 (the “TCA”), and R.I. Gen. Laws § 45-24-69(a). The plaintiffs seek reversal of a decision by the Richmond Zoning Board of Review (the “ZBR” or the “Board”) denying SNET’s application for a special use permit that would allow a tower to be constructed. The plaintiffs also seek either reversal of that portion of the ZBR’s decision denying their application for a dimensional variance or a determination that, contrary to a ruling by Rich *192 mond’s zoning official, such a variance is not required.

The defendants have moved- for summary judgment, and the questions presented are:

(1) whether there is substantial evidence in the record supporting the ZBR’s decision;
(2) whether the ZBR acted on SNET’s application within a reasonable time; and
(3) whether the defendants’ actions effectively prohibit the provision of wireless communications services in the Richmond area.

Because I find, based upon the undisputed evidence, that the first two questions should be answered affirmatively; and, because I further find that the record is not sufficiently developed to permit an answer to the third question, the motion for summary judgment is granted in part and denied in part.

Background

SNET is in the business of providing interstate cellular communications service. Federal Communications Commission (“FCC”) regulations require SNET, as a licensee, to provide service to a specified geographic area. In 1996, SNET engineers determined that, in order to satisfy that requirement, SNET needed to install an antenna array in the Shannock Hill area of the Town of Richmond, Rhode Island. Accordingly, SNET entered into an agreement to lease a parcel of land in Richmond owned by Barbara Burdick and Howard Bentley (the “Bentley Property” or the “Site”) for the purpose of erecting a 190-foot antenna tower.

The Bentley Property is a 25-acre lot most of which is wooded and on which a single-family residence is located. The Bentley Property is zoned R-2, at the time of SNET’s application, “[cjommunication ... towers and antenna” were permitted in R-2 zones only as special uses. See Richmond Code, § 18.16.010. Moreover, under the Richmond Zoning Code (the “Code”), structures for permitted uses could not exceed a height of 35 feet, see id. § 18.20.020, except that “[sjpires, towers, belfries, steeples, flagpoles, chimneys, water standpipes, radio or television antennae, silos or similar structures,” were exempt from the height requirement. Id. § 18.36.050.

Because Richmond’s Zoning Official determined that the proposed telecommunications tower was not a “radio or television antenna[ SNET applied to the ZBR for a dimensional variance as well as a special use permit. That application was filed on July 2,1996.

The ZBR consists of five members and two alternates, all of whom serve as part-time, unpaid volunteers. The Board, ordinarily, meets once a month, and it scheduled a hearing on the plaintiffs’ application for its next scheduled meeting, on July 22, 1996. However, the Board did not begin considering SNET’s application until December because both the July and October meetings were consumed by hearings on another telecommunications tower application; the August session was canceled due to lack of a quorum; SNET’s attorney requested a postponement of the hearing scheduled for September; and the attorney representing objectors requested a postponement of the hearing scheduled for November.

At the initial hearing, SNET maintained that, although it was applying for a dimensional variance, no such variance was required because the proposed communications tower was a radio antenna structure that was exempt from the Code’s height restrictions.

When it became apparent that the hearings would require a considerable amount of time, the Board decided to hold “special” hearings devoted entirely to SNET’s application between January 9 and July 24 of 1997.

At those hearings, SNET and residents opposed to the application presented testimony and documentary evidence focusing *193 on the impact that the proposed tower would have on nearby property and the tower’s compatibility with Richmond’s comprehensive land use plan. Some evidence also was presented as to the question of whether there were alternative sites that could provide the required service coverage.

During the period that those hearings were being conducted, the Richmond Town Council decided to develop a plan that would establish where cellular communications towers could be placed in the town. On June 24, 1997, pending completion of that plan, the Council imposed a moratorium on the issuance of special use permits for wireless communication towers. However, the moratorium exempted applications, such as SNET’s, that were filed before its adoption. The moratorium lasted until October 7, 1997, when the Council amended the Zoning Ordinance to make telecommunications towers a permitted use in industrial zones and to allow them as special uses in commercial zones or as attachments to existing structures in any zone.

On October 2, 1997, the ZBR denied SNET’s application for both a special use permit and a dimensional variance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
99 F. Supp. 2d 190, 2000 U.S. Dist. LEXIS 7497, 2000 WL 730399, Counsel Stack Legal Research, https://law.counselstack.com/opinion/snet-cellular-inc-v-angell-rid-2000.