Smith v. Showalter

734 P.2d 928, 47 Wash. App. 245
CourtCourt of Appeals of Washington
DecidedMarch 17, 1987
Docket7644-0-III
StatusPublished
Cited by24 cases

This text of 734 P.2d 928 (Smith v. Showalter) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Smith v. Showalter, 734 P.2d 928, 47 Wash. App. 245 (Wash. Ct. App. 1987).

Opinion

Thompson, A.C.J.

Gerald and Rose Marie Showalter's motion for summary judgment was granted on the basis that any cause of action the Smiths might have had was barred by the builders' statute of repose, RCW 4.16.310. The Smiths appeal, contending under the facts of this case, the action is not barred. We agree and reverse.

In 1975, the Showalters began construction on their home in Kennewick, Washington. When first occupied by them in 1975, it was approximately 50 percent completed. They performed all construction work themselves, including installation of the electrical wiring. In July 1975, a permit was issued for an electrical "service only" panel, allowing limited use for a shop, or construction of the home. It is disputed whether any further electrical permits were given or inspections conducted by appropriate authorities.

In 1977, the Showalters added a utility room and a living room and, though they were not finished, began using them. The Showalters continued work on the home. On April 5, 1981, the home was sold to the Smiths and was approximately 90 percent complete. The utility room was still unfinished at the time of sale, but its electrical wiring was complete. When the Smiths purchased the home, they were not told that the Showalters were the builders. Nor were the Smiths informed the Showalters had not received final building or electrical inspections, or that the wiring was substandard.

On May 18, 1984, the home was destroyed by fire. Kenneth A. Sugden, the Smiths' expert witness, inspected the fire scene and was of the opinion the fire began in an outlet on the west wall of the utility room. His report, challenged for the first time on appeal, further states: the outlet and its circuit breaker were substandard given the size of the wiring; nonstandard workmanship was apparent; only an electrical service permit was issued; no further electrical permits for the utility room were' issued; and there were *247 no electrical inspections of the home. A report by the Department of Labor and Industries, Electrical Inspection Section, confirms that only a "service" was approved in 1975, and that interior wiring had not been inspected or approved.

The Smiths brought suit against the Showalters, alleging negligent installation of electrical wiring, failure to meet electrical building code requirements, and lack of proper inspection for residential use caused the fire and resulting damage. The Showalters moved for summary judgment, contending suit was barred by RCW 4.16.300-.310, the builder/contractor 6-year statute of repose. Their motion was granted and this appeal ensued.

The Smiths' cause of action falls within the ambit of RCW 4.16.300-.310; it involves a claim or cause of action arising from the construction of an improvement upon real property. To determine whether the statute of repose in RCW 4.16.310 bars the Smiths' claim, a 2-step analysis is necessary. First, we must determine whether the cause of action accrued within 6 years of "substantial completion of construction, or within six years after such termination of services, whichever is later". Second, we must determine whether the Smiths filed suit thereafter within the time allowed by the applicable statute of limitation. If the cause of action does not accrue within 6 years of substantial completion of construction or termination of services, whichever is later, the statute bars commencement of the suit. Del Guzzi Constr. Co. v. Global Northwest Ltd., 105 Wn.2d 878, 883, 719 P.2d 120 (1986). The question presented here is when the 6-year period began to run on the underlying claim or cause of action.

The trial court determined as a matter of law RCW 4.16-.300-310 barred the Smiths' action. It did so based on the view that the 6 years began when the utility room was wired and occupied in 1977. The Smiths contend substantial completion or termination of construction services did not occur until 1981, and thus the time period did not begin until that latter date. We agree.

*248 Summary judgment is proper only if there is no genuine issue as to any material fact and the moving party is entitled to judgment as a matter of law. Wilson v. Steinbach, 98 Wn.2d 434, 656 P.2d 1030 (1982). Interpretation of a statute is a matter of law. Condit v. Lewis Refrigeration Co., 101 Wn.2d 106, 676 P.2d 466 (1984). In its ruling, the trial court considered affidavits of the Showalters, the Smiths, and Mr. Sugden, as well as a certified copy of a recorded statement made by the Showalters to an insurance carrier. This court considers the same evidence, and all reasonable inferences therefrom, in favor of the nonmoving party. Wilson v. Steinbach, supra.

As a preliminary matter, the Showalters argue this court should not consider the hearsay statements contained in Kenneth Sugden's affidavit and attachments thereto regarding failure to comply with electrical permit and inspection requirements. They argue CR 56(e) prevents consideration of such statements on summary judgment if the statements are not based on personal knowledge and are not admissible at trial. That is true. State v. The (1972) Dan J. Evans Campaign Comm., 86 Wn.2d 503, 506, 546 P.2d 75 (1976). However, where no objection or motion to strike is made prior to entry of summary judgment, a party is deemed to waive any deficiency in the affidavit. Lamon v. McDonnell Douglas Corp., 91 Wn.2d 345, 352, 588 P.2d 1346 (1979); Greer v. Northwestern Nat'l Ins. Co., 36 Wn. App. 330, 338, 674 P.2d 1257 (1984). The record does not reveal an objection or motion to strike any portion of the Sugden affidavit or attachments prior to the trial court's entry of judgment. Therefore, the Showalters have waived any alleged deficiency.

The Smiths first argue that the Showalters continued to work on the home until 1981 and the statute allows that later date as the beginning of the 6-year period. In interpreting a statute, we must ascertain and give effect to the intent and purpose of the Legislature as expressed in the act as a whole. In doing so, we first look to the language of the statute. Condit, at 110. The relevant portion of RCW *249 4.16.310 states a claim or cause of action must accrue:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Puget Sound Energy, Inc. v. Pilchuck Contractors, Inc.
Court of Appeals of Washington, 2020
Brandon Welch v. City Of Burlington
Court of Appeals of Washington, 2018
American Express Bank, Resp. v. Jerry Hoang, App.
Court of Appeals of Washington, 2015
Dori Ellen Cardon v. Estate Of James Leroy Bredesen
Court of Appeals of Washington, 2015
Dania, Inc. v. Skanska USA Building Inc.
340 P.3d 984 (Court of Appeals of Washington, 2014)
Wells Fargo Bank v. Christopher L. Short
Court of Appeals of Washington, 2014
Mattingly v. Palmer Ridge Homes, LLC
157 Wash. App. 376 (Court of Appeals of Washington, 2010)
Bonneville v. Pierce County
202 P.3d 309 (Court of Appeals of Washington, 2009)
LAKEVIEW v. Apartment Sales Corp.
6 P.3d 74 (Court of Appeals of Washington, 2000)
1519-1525 Lakeview Boulevard Condominium Ass'n v. Apartment Sales Corp.
101 Wash. App. 923 (Court of Appeals of Washington, 2000)
Gordon v. Western Steel Co.
950 S.W.2d 743 (Court of Appeals of Texas, 1997)
State v. Hughes
907 P.2d 336 (Court of Appeals of Washington, 1995)
United Food & Commercial Workers Union Local 367 v. Canned Foods, Inc.
900 P.2d 569 (Court of Appeals of Washington, 1995)
First Maryland Leasecorp v. Rothstein
864 P.2d 17 (Court of Appeals of Washington, 1993)
Walker v. TRANSAMERICA TITLE INSURANCE
828 P.2d 621 (Court of Appeals of Washington, 1992)
Pfeifer v. City of Bellingham
772 P.2d 1018 (Washington Supreme Court, 1989)
Parkin v. Colocousis
769 P.2d 326 (Court of Appeals of Washington, 1989)
Hash v. Children's Orthopedic Hospital & Medical Center
741 P.2d 584 (Court of Appeals of Washington, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
734 P.2d 928, 47 Wash. App. 245, Counsel Stack Legal Research, https://law.counselstack.com/opinion/smith-v-showalter-washctapp-1987.