Small Construction Group, LLC v. Berkshire Hathaway Specialty Insurance Company

District Court, E.D. Louisiana·Decided July 3, 2024·No. 2:23-cv-06866·Unknown

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF LOUISIANA

SMALL CONSTRUCTION GROUP, LLC CIVIL ACTION

VERSUS NO. 23-6866

BERKSHIRE HATHAWAY SPECIALTY SECTION: “G”(1) INSURANCE COMPANY

ORDER AND REASONS Before the Court is Defendant Berkshire Hathaway Specialty Insurance Company’s (“Defendant”) Motion to Dismiss for Failure to State a Claim.1 This case involves a public works contract with the State of Louisiana through the Department of Education to construct a high school in New Orleans.2 Lemoine Company, LLC (“Lemoine”) was general contractor for the project.3 Defendant issued a statutory payment and performance bond for the project with Lemoine as principal and Defendant as surety.4 Plaintiff brings this action pursuant to the Louisiana Public Works Act alleging that the construction project was compromised due to discrepancies in the construction drawings, and Plaintiff is entitled to costs for a change order.5 Defendant argues that Plaintiff has failed to allege facts that entitle it to relief because: (1) Plaintiff has not shown that it is entitled to costs for the change order pursuant to the terms of the subcontract; and (2) Lemoine

1 Rec. Doc. 7. 2 Rec. Doc. 1. 3 Id. 4 Id. 5 Id. is statutorily immune pursuant to Louisiana Revised Statute § 9:2771.6 For the reasons stated herein, the Court finds that Plaintiff’s allegations are insufficient to show that Plaintiff is entitled to relief pursuant to the Louisiana Public Works Act. Therefore, the Court grants Plaintiff leave to amend the Complaint to cure this deficiency, if possible. The issue

of whether Lemoine is statutorily immune involves questions of fact that cannot be resolved on a Rule 12(b)(6) motion. Accordingly, considering the motion, the opposition, the reply memorandum, the record, and the applicable law, the Court denies the motion and grants Plaintiff leave of Court to amend the complaint to cure the noted deficiencies. I. Background On August 21, 2019, Lemoine, as general contractor, entered into a public works contract with the State of Louisiana through the Department of Education to construct the New Cohen High School located at 3520 Dryades Street, New Orleans, Louisiana 70115 (“the Project”).7 On September 19, 2019, a copy of the contract was recorded with the Recorder of Mortgage for Orleans Parish, State of Louisiana.8 Defendant issued a statutory Payment and Performance Bond for the project with Lemoine as principal and Defendant as surety.9

On August 13, 2020, Plaintiff submitted a bid proposal to Lemoine to perform masonry work.10 The Complaint alleges that Plaintiff bid the project in accordance with Lemoine’s written bidding documents, which included a set of black and white construction drawings dated June 5,

6 Rec. Doc. 7. 7 Rec. Doc. 1 at 2. 8 Id. 9 Id. 10 Id. 2020.11 The Complaint states that Plaintiff relied on said construction drawings to calculate the number of red and tan bricks needed to complete the masonry work.12 On April 7, 2021, Lemoine entered into a Master Subcontract Agreement (“the Subcontract”) with Plaintiff to perform the masonry work for the project.13 The price for the subcontract was $1,079,997.00.14 The subcontract required Plaintiff to complete the work in

accordance with the construction drawings, which were identified by name and number in exhibit B of the subcontract.15 Upon Lemoine’s acceptance of the subcontract, Plaintiff was provided electronic access to updated construction drawings dated March 15, 2021.16 The Complaint states that the March 15, 2021 construction drawings were substantively identical to the June 5, 2020 drawings and did not change the brick quantity and color calculation.17 The Complaint states that neither of the construction drawings were color-coded.18 The Complaint states that after the execution of the subcontract, Plaintiff informed Lemoine that the time for delivery of the bricks to the construction site would be at least sixteen weeks.19 At Lemoine’s request, Plaintiff agreed to work expeditiously to ensure the bricks were

11 Id. 12 Id. 13 Id. at 3. 14 Id. 15 Id. 16 Id. 17 Id. 18 Id. 19 Id. ordered so that work could commence by Thanksgiving.20 On June 30, 2021, after conferring and obtaining approval from Lemoine, Plaintiff ordered the brick color and quantity for the project.21 The Complaint states that Plaintiff determined the quantity and color based on the construction drawings provided by Lemoine and by means and methods consistent with the general standards of the industry.22

The bricks were delivered to the construction site in late October 2021.23 The Complaint states that Lemoine was not prepared for Plaintiff to begin the project by Thanksgiving, and Plaintiff was forced to store the materials on the site for approximately one month.24 In January 2022, Plaintiff’s on-site supervisor asked Lemoine if color-coded construction drawings existed for the project.25 On January 14, 2022, Lemoine emailed Plaintiff a color-coded copy of the March 15, 2021 construction drawings from the project architect.26 The Complaint alleges that the color-coded construction drawings included red and tan coloring on the bricks but otherwise appeared to be the same as the black and white version.27 The Complaint states that as the project progressed, Plaintiff noticed a significant discrepancy between the color-coded drawings and the black and white drawings.28 The Complaint

20 Id. 21 Id. 22 Id. at 4. 23 Id. 24 Id. 25 Id. 26 Id. 27 Id. 28 Id. alleges that the shading on the color-coded drawings did not match the labels for the brick colors and locations on the black and white drawings.29 For example, the Complaint states that the A-201 West Elevation is labeled with “brick veneer (tan) only” on the black and white drawings, while the color-coded drawings show a pattern of tan and red bricks.30 Based on this discrepancy, there

was a brick surplus of one color and a shortage of another color, resulting in an overall miscalculation of 78,570 bricks.31 The Complaint states that Plaintiff promptly notified Lemoine of the discrepancy, and the parties worked together to devise a new plan for procuring the correct quantity and color of bricks.32 On or about June 3, 2022, Lemoine and the project architect approved and expressly directed Plaintiff to order new bricks and perform the extra work on the project.33 Plaintiff completed the entire scope of the work by December 2022.34 The Complaint states that despite multiple demands, Lemoine has failed to pay Plaintiff’s change order, which represents the current amount due pursuant to the subcontract.35 The Complaint states that the outstanding amount due is $248,741.28.36

On December 29, 2022, Plaintiff filed a Sworn Statement of Claim and Privilege with the Recorder of Mortgage for Orleans Parish for the unpaid balance pursuant to the Louisiana Public

29 Id. at 5. 30 Id. 31 Id. 32 Id. 33 Id. 34 Id. 35 Id. 36 Id. at 6. Works Act.37 On the same date, the Complaint states that Plaintiff notified Defendant, Lemoine, and the State of Louisiana through the Department of Education – Recovery School District of its Sworn Statement of Claim and Privilege via certified mail.38 To date, Plaintiff has not been paid in connection with its Sworn Statement of Claim and Privilege.39

Free access — add to your briefcase to read the full text and ask questions with AI

Small Construction Group, LLC v. Berkshire Hathaway Specialty Insurance Company, (E.D. La. 2024).

Small Construction Group, LLC v. Berkshire Hathaway Specialty Insurance Company (Small Construction Group, LLC v. Berkshire Hathaway Specialty Insurance Company) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Collins v. Morgan Stanley Dean Witter
224 F.3d 496 (Fifth Circuit, 2000)
Carbe v. Lappin
492 F.3d 325 (Fifth Circuit, 2007)
Lormand v. US Unwired, Inc.
565 F.3d 228 (Fifth Circuit, 2009)
Tellabs, Inc. v. Makor Issues & Rights, Ltd.
551 U.S. 308 (Supreme Court, 2007)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Jones v. Bock
549 U.S. 199 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
A & M Pest Control Serv., Inc. v. FEJTA CONST. CO. INC.
338 So. 2d 946 (Louisiana Court of Appeal, 1976)
Cormier v. Honiron Corp.
771 So. 2d 193 (Louisiana Court of Appeal, 2000)
Bernard v. STATE, THROUGH DOTD
640 So. 2d 694 (Louisiana Court of Appeal, 1994)
Richard v. State Through DOTD
610 So. 2d 839 (Louisiana Court of Appeal, 1992)
State v. McInnis Bros. Const.
701 So. 2d 937 (Supreme Court of Louisiana, 1997)
Wilkin v. Dev Con Builders, Inc.
561 So. 2d 66 (Supreme Court of Louisiana, 1990)
Walls v. American Optical Corp.
740 So. 2d 1262 (Supreme Court of Louisiana, 1999)
Martin v. Boh Bros. Const. Co., LLC
934 So. 2d 196 (Louisiana Court of Appeal, 2006)