Sloan v. Perryman

CourtCourt of Appeals of Tennessee
DecidedAugust 31, 2000
DocketM1999-00828-COA-R3-CV
StatusPublished

This text of Sloan v. Perryman (Sloan v. Perryman) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sloan v. Perryman, (Tenn. Ct. App. 2000).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE APRIL 2000 Session

JASON SLOAN d/b/a SLOAN CONSTRUCTION v. SHELBY RAY PERRYMAN, JR., ET AL.

Direct Appeal from the Chancery Court for Maury County No. 97-159; The Honorable Stella L. Hargrove, Chancellor

No. M1999-00828-COA-R3-CV - Filed August 31, 2000

This appeal arises from a breach of contract suit and action to assert priority of a mechanics lien filed by Jason Sloan (“Contractor”) against Shelby Ray Perryman (“Owners”) and First Farmers & Merchants National Bank (“Bank”). Contractor sought recovery for labor and materials under the contract including expenses that exceeded Contractor’s original bid price. In the alternative, Contractor sought recovery under quantum meruit. The court granted Bank’s motion for summary judgment on the issue of priority of liens. Following trial, the court awarded Contractor damages under an implied contract theory, limiting Contractor’s recovery to the bid price. In addition, the court denied Contractor’s claim for alternative recovery in quantum meruit. Contractor appeals.

Tenn. R. App. P. 8; Appeal as of Right; Judgment of the Chancery Court Affirmed in Part, Reversed in Part and Remanded

ALAN E. HIGHERS, J., delivered the opinion of the court, in which FARMER , J., and LILLARD, J., joined.

L. Robert Grefseng, Columbia, for Appellant

Thomas F. Bloom, Nashville, for Appellees Shelby and Jamie Perryman

Scott C. Williams, Columbia, for Appellee First Farmers & Merchants National Bank of Columbia

OPINION

Facts and Procedural History

On May 7, 1996, Owners entered into a contract for Contractor to build a residence on Owners’ property. Owners provided house plans and Contractor submitted a bid to build the residence for a total cost of around seventy-two thousand dollars.1 The contract did not include the actual dollar amount stated in the bid, but did contain a provision allowing for reduction in costs for any on-site work performed by Owners as well as a provision requiring owners to bear all construction expenses.

Owners obtained a construction loan from First Farmers & Merchants National Bank (“Bank”). The loan agreement included the bid price of seventy-one thousand, seven hundred fifty- seven dollars and twenty-one cents ($71,757.21). Bank’s loan was secured by a construction mortgage on Owner’s future residence. Both Owners and Contractor signed a pre-loan affidavit stating “no labor or materials, pre-fabricated or otherwise, have been used or prepared for use on said premises to this date (6/7/96).” Bank’s deed of trust on the property was executed and filed on June 7, 1996.

Contractor began construction on June 10, 1996.2 Throughout the construction project, Contractor periodically provided Owners with bills for materials and labor which Owners paid as they came due. When construction was completed in September 1996, Contractor presented owner with three final invoices totaling over fifteen thousand dollars. At this point, Owners had already spent almost seventy-one thousand dollars on the project and did not realize costs had exceeded the original bid price. Owners refused to pay additional costs.

On November 12, 1996, Contractor filed a mechanics lien against Owners’ property to secure payment for labor and materials.3 Thereafter, on March 11, 1997, Contractor filed suit against Owners and Bank to recover additional costs under breach of contract theory. Contractor asserted that Owners owed almost twenty-three thousand dollars, including a seventy-five hundred dollar contractor fee. In the alternative, Contractor sought recovery under quantum meruit. In addition, Contractor asserted that his mechanics lien had priority over Bank’s construction mortgage.

Owners filed a counter-claim alleging outrageous conduct and gross negligence by Contractor. Owners based this claim on Contractor’s alleged negligence in preparing an

1 During negotiations, Owners stated that maximum amount of money available for the project was a home loan for seventy-five tho usand dollars. 2 Although Contractor used the June date in his original complaint, he later claimed that the actual date of construction was April 17, 1996. Contractor amended the date after the priority of liens became an issue below. According to Contractor, the preliminary dozer work and some foundation work took place in April 1996. In addition, “batter boards” were created and installed and a temporary utility pole was erected.

3 The creation and enforcement of mechanics lien is governed by statute. Contractor seeks recovery under § 66-11-104 of the Tennessee Code. This statute provides that the lien takes affect upon “the visible commencement of operation s.” While this term is not defined, the statute specifically excludes “demolition, surveying, excavating, clearing, filling or grading, placem ent of sew er or drain age lines o r other un dergrou nd utility lines or work preparatory therefor, erection of temporary security fencing and the delivery of materials therefor.” Contractor asserts that the construction and placement of “batter boards” and the placement of a temporary utility pole qualify as visible comm encemen t of operations.

-2- unreasonable bid and his subsequent failure to stay within the bid price. Bank filed an answer asserting that its deed of trust had priority over Contractor’s mechanics lien because the deed of trust was executed and filed prior to the commencement of construction.

Contractor filed a motion for partial summary judgment. Court granted Contractor summary judgment on Owner’s counter-claim but allowed Owners to amend to add a breach of contract claim. The court denied summary judgment on issue of priority of the mechanics lien and construction mortgage. Bank later filed a motion for summary judgment on this issue. After a hearing on priority, the court held Bank’s construction mortgage had priority over the mechanics lien based in part on the pre-construction loan affidavit signed by Contractor.

The case proceeded to trial on the remaining claims between Contractor and Owner. At trial, Contractor claimed Owners made several deviations from the original plans that resulted in additional costs for materials and labor. Among these deviations from the original plans were the following: Owners’ use of more expensive fixtures and material; additional windows; foundation costs; the installation of additional electrical, phone and cable outlets; and the use of concrete rather than vinyl siding. Contractor also claimed site-preparation work done by Owners had to be redone and created additional expenses. Owners claimed these deviations from the original plans were offset by their performance of the on-site work. In addition, Owners claimed Contractor did not tell them the project was over budget and failed to warn them of all additional costs.

The trial court found the parties’ written contract was unenforceable because of the failure to include a specific price term. However, the court held that an implied contract existed between the parties for an agreed on maximum cost of seventy-one thousand, seven hundred fifty-seven dollars and twenty-one cents ($71,757.21) and that the contract was not a “cost-plus contract.” The amount awarded was one thousand ten dollars and twenty-one cents ($1,010.21), which represented the difference between what Owners already paid to Contractor and the bid price. In addition, the court held that Contractor did not meet the burden of proof to recover under quantum meruit.

Contractor appeals, alleging the court erred in holding the written contract unenforceable. as well as in its interpretation of the implied contract. In the alternative, Contractor asserts the trial court erred in denying the claim of unjust enrichment or quantum meruit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Edwards v. Travelers Indemnity Co.
300 S.W.2d 615 (Tennessee Supreme Court, 1957)
Castelli v. Lien
910 S.W.2d 420 (Court of Appeals of Tennessee, 1995)
Heyer-Jordan & Associates, Inc. v. Jordan
801 S.W.2d 814 (Court of Appeals of Tennessee, 1990)
Rainey v. Stansell
836 S.W.2d 117 (Court of Appeals of Tennessee, 1992)
Cowden v. Sovran Bank/Central South
816 S.W.2d 741 (Tennessee Supreme Court, 1991)
Downen v. Allstate Insurance Co.
811 S.W.2d 523 (Tennessee Supreme Court, 1991)
Anderson v. Standard Register Co.
857 S.W.2d 555 (Tennessee Supreme Court, 1993)
Associated Press v. WGNS, INCORPORATED
348 S.W.2d 507 (Court of Appeals of Tennessee, 1961)
Ridings v. Ralph M. Parsons Co.
914 S.W.2d 79 (Tennessee Supreme Court, 1996)
Winfree v. Educators Credit Union
900 S.W.2d 285 (Court of Appeals of Tennessee, 1995)
Hillis v. Powers
875 S.W.2d 273 (Court of Appeals of Tennessee, 1993)
Byrd v. Hall
847 S.W.2d 208 (Tennessee Supreme Court, 1993)
Wright v. City of Knoxville
898 S.W.2d 177 (Tennessee Supreme Court, 1995)
Bain v. Wells
936 S.W.2d 618 (Tennessee Supreme Court, 1997)
Union Planters National Bank v. American Home Assurance Co.
865 S.W.2d 907 (Court of Appeals of Tennessee, 1993)
Taylor v. White Stores, Inc.
707 S.W.2d 514 (Court of Appeals of Tennessee, 1985)
John J. Heirigs Const. Co., Inc. v. Exide
709 S.W.2d 604 (Court of Appeals of Tennessee, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
Sloan v. Perryman, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sloan-v-perryman-tennctapp-2000.