Slavin v. Borinstein

25 Cal. App. 4th 713, 30 Cal. Rptr. 745, 30 Cal. Rptr. 2d 745, 94 Daily Journal DAR 7763, 94 Cal. Daily Op. Serv. 4226, 1994 Cal. App. LEXIS 564
CourtCalifornia Court of Appeal
DecidedJune 6, 1994
DocketB063777
StatusPublished
Cited by33 cases

This text of 25 Cal. App. 4th 713 (Slavin v. Borinstein) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Slavin v. Borinstein, 25 Cal. App. 4th 713, 30 Cal. Rptr. 745, 30 Cal. Rptr. 2d 745, 94 Daily Journal DAR 7763, 94 Cal. Daily Op. Serv. 4226, 1994 Cal. App. LEXIS 564 (Cal. Ct. App. 1994).

Opinion

Opinion

HASTINGS, J.

This is an appeal from an award in favor of contractor Leon Slavin (respondent) and against property owner Joan W. Borinstein (appellant) for contracting costs, fees and profits relating to a residence in Bel Air. Appellant asserts one issue on appeal: that the trial court erred in not finding that an amendment to the original agreement between appellant and respondent dated August 10, 1983, was a covenant which limited respondent’s recovery for contractor’s fees to the total sum of $300,000. We find appellant’s argument without merit and we affirm.

Statement of Facts

In December of 1981, Albert Fink (Fink), appellant’s agent, asked respondent if he would like to build a custom house in Los Angeles for appellant. Respondent answered in the affirmative and asked to see a set of plans; however, no set was available. Fink asked respondent to send him a resume of his prior contracting experience, and respondent complied on December 31, 1981.

Shortly thereafter, respondent spoke with Fink about the conditions under which he would work as a contractor. Fink indicated that appellant was prepared to pay a fee of 10 percent of cost, and that she preferred to set the fee in that manner because the drawings had not been completed. Fink also *716 advised respondent that appellant wanted him to start the job immediately. Respondent agreed orally to build the structure for his cost plus 10 percent.

On January 11, 1982, respondent sent Fink a standard American Institute of Architects form contract and asked whether it met with Fink’s approval. Fink never executed it, advising respondent that he did not like the form and would draw up an appropriate contract. Respondent never received a contract from Fink.

Meanwhile, respondent received sufficient plans to enable him to obtain a building permit and to begin construction. To confirm the agreement he had reached with Fink, respondent sent Fink a memorandum dated April 5, 1982, which stated: “This will confirm our mutual agreement as follows pertaining to the subject building project: [<][] 1. Leon Slavin will perform general contractor duties for the construction of the subject project in accordance with plans & spec, prepared by Fred Briggs, architect. [j[] 2. The scope of work will include the complete building with the exception of certain items of work to be done by owner. These items will be determined by owner. H] 3. Contractor fee shall be 10% of total cost of work completed each month. [It] 4. Payments shall be made each month for cost of construction plus said contractor fee. [1] 5. Formal contract by owner will follow.” No formal contract followed.

From April 1982, through November 1983, respondent furnished labor and materials in construction of the house. As provided by their agreement, requests for payment of construction costs and contractor’s fees were made on a monthly basis except for the periods between April through June 1982, and July through August 1982, in which there was only one billing for the amount owing in each of those periods. In total, respondent sent to appellant 17 payment requests. Requests 1-8 were paid in their entirety, while request number 9 was paid in two installments, and request number 10 was paid in three installments. Beginning with request number 11, no construction fees were paid, and appellant fell behind on payment of construction costs. As of the end of July, appellant owed respondent $369,983 for unpaid construction costs and contractor’s fees.

Respondent approached Fink and advised him that the arrearage was causing problems. Fink advised respondent that appellant was “having some cash flow problems” and that “we have decided that we are not going to pay you anymore than a maximum of $300,000, regardless of what the cost of the project would be. . . .” Respondent became upset and Fink advised him, “You can go take it or leave it. If you don’t like it, then you can sue me.” Because respondent was hard-pressed for money, he advised Fink “that if he *717 would agree to bring [respondent] current, on the unpaid balances, that [respondent] would accept that $300,000 maximum fee.” Fink said that he would take it up with appellant and let him know. A few days later respondent called Fink and asked whether Fink had discussed the matter with appellant. Fink advised him that they were not going to pay more than the $300,000. Respondent asked whether they were going to bring him current and Fink advised “they would do the best they could on that.”

After the latter conversation, respondent sent a letter dated August 10, 1982, to appellant to confirm the proposed modification. It is this letter which is the subject of the appeal. The letter stated as follows: “This will confirm our mutual agreement that our original owner/contractor agreement (April 5, 1983 [sic]) of cost plus contractor fee of 10% of costs for the construction work at the subject project be amended to limit the aforementioned 10% of cost contractor fee to a maximum sum of $300,000, payable in 18 equal payments, [f] In accordance with the original agreement between us, to date there have been 13 billings for said contractor fee for a total of $233,522.97. [][] Please advise me if the above meets with your approval.” Fink was to speak with appellant about the proposed modification and then confirm it with respondent.

At this point, the evidence conflicts. Respondent testified at trial that he received no response from either appellant or Fink agreeing to the modification proposal set out in the letter. Fink testified that prior to receiving the letter it was his understanding that respondent would continue with the project and take $300,000 “based upon a percentage completion of the house.” When he received the letter he contacted respondent and advised him that they were not going to pay in 18 equal installments but were only going to pay on a “pro rata percentage as to the completion of the house.” Respondent testified that at no time was there any agreement that he would accept his contractor’s fees based upon a percentage of the work completed. He never received any additional payments for contractor’s fees, although, from time to time, he did receive payments for construction costs. Ultimately he stopped work on the project.

During September and October 1991, a court trial was held relating to claims by respondent against appellant for recovery of construction costs, fees and loss of profits, and counterclaims by appellant against respondent relating to construction defects. 1 On October 10, 1991, the trial court filed a notice of tentative decision. The document stated, in part: “44. The foregoing shall be deemed the court’s Statement of Decision, unless a formal request *718 for a Statement of Decision is filed and served pursuant to the provisions of Code of Civil Procedure [section] 632 and California Rules of Court, Rule 232.” The record on appeal does not reflect that any statement of decision was requested, and respondent’s brief advises us that none was made. On November 22, 1991, a judgment was rendered in favor of respondent awarding him sums for unpaid construction costs plus interest, unpaid contractor’s fees plus interest and loss of net profits plus interest, for a total sum of $875,644.17.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mendoza v. Fresh Venture Foods CA2/6
California Court of Appeal, 2025
Din v. Sutter Valley Hospital CA3
California Court of Appeal, 2025
Rodgers-Vieira v. First American Title Co. CA3
California Court of Appeal, 2025
Executive Dynamics Search v. Lawrence CA4/1
California Court of Appeal, 2024
Salto v. Empire Transportation Services CA4/1
California Court of Appeal, 2023
Maddox v. Maddox CA4/1
California Court of Appeal, 2023
Lopez v. La Casa de Las Madres
California Court of Appeal, 2023
Barney v. Com. on Prof. Competence CA4/1
California Court of Appeal, 2021
Semeil v. Nelson CA3
California Court of Appeal, 2021
Richardson v. Ruan Transport Corp. CA5
California Court of Appeal, 2020
Sweetwater Union High Sch. Dist. v. Julian Union Elementary Sch. Dist.
249 Cal. Rptr. 3d 309 (California Court of Appeals, 5th District, 2019)
Grandmaison v. Rosa CA2/7
California Court of Appeal, 2016
A.G. v. C.S.
California Court of Appeal, 2016
Coats v. Callaway CA4/1
California Court of Appeal, 2015
Ehrlichman v. Heart Tronics CA2/8
California Court of Appeal, 2014
Wallis v. PHL Associates Inc.
220 Cal. App. 4th 814 (California Court of Appeal, 2013)
139 S. Occidental Blvd. v. Ha CA2/7
California Court of Appeal, 2013

Cite This Page — Counsel Stack

Bluebook (online)
25 Cal. App. 4th 713, 30 Cal. Rptr. 745, 30 Cal. Rptr. 2d 745, 94 Daily Journal DAR 7763, 94 Cal. Daily Op. Serv. 4226, 1994 Cal. App. LEXIS 564, Counsel Stack Legal Research, https://law.counselstack.com/opinion/slavin-v-borinstein-calctapp-1994.