Skip Kirchdorfer, Inc. v. United States

35 Fed. Cl. 742, 1996 U.S. Claims LEXIS 105, 1996 WL 332322
CourtUnited States Court of Federal Claims
DecidedJune 18, 1996
DocketNo. 337-89C
StatusPublished
Cited by1 cases

This text of 35 Fed. Cl. 742 (Skip Kirchdorfer, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Skip Kirchdorfer, Inc. v. United States, 35 Fed. Cl. 742, 1996 U.S. Claims LEXIS 105, 1996 WL 332322 (uscfc 1996).

Opinion

MEMORANDUM OF DECISION

HARKINS, Senior Judge.

This case is before the court on the request of Skip Kirehdorfer, Inc. (SKI) for attorney fees and other expenses, filed October 30, 1995,1 pursuant to the Equal Access to Justice Act (EAJA) (28 U.S.C. § 2412(d) (1994)).

The EAJA provides that a prevailing party other than the United States may recover an award for attorney fees and other expenses, in addition to costs incurred by that party in any civil action (other than eases sounding in tort), including proceedings for judicial review of agency action, brought by or against the United States, “unless the court finds that the position of the United States was substantially justified or that special circumstances make an award unjust.” 28 U.S.C. § 2412(d)(1)(A) (1994). Eligibility for attorney fees requires (1) that the claimant prevailed in the action, (2) that the Government’s position was not substantially justified, (3) that the award of attorney fees is not unjust, and (4) that the fee application is timely filed and supported by an itemized statement. Comm’r Immigration & Naturalization Serv. v. Jean, 496 U.S. 154, 158, 110 S.Ct. 2316, 2319, 110 L.Ed.2d 134 (1990).

In this case, criteria No. 2 and No. 3 preclude an award. The position of the United States was “substantially justified” and special circumstances make an award of attorney fees unjust.

Determination of plaintiffs taking claims has been protracted. Judicial proceedings on plaintiffs claims against the United States began on December 19, 1988, in the District Court for the Eastern District of Virginia, on a complaint that alleged a wrongful taking without due process of law, conversion, false imprisonment, and tortious interference with contract rights. By order dated March 31, 1989, the district court dismissed the tort claims, and ordered the taking claims to be transferred. The taking claims were transferred to this court on June 15,1989, and the complaint was filed on July 17,1989.

After trial, the complaint was ordered dismissed, on August 18, 1992, on the ground that SKI had not established a taking for which compensation was owed. Kirchdorfer v. United States, 26 Cl.Ct. 666 (1992). On appeal, the Federal Circuit on October 12, 1993, affirmed-in-part, reversed-in-part, and remanded for further proceedings to determine the value of SKI’s taken property interest. Kirehdorfer v. United States, 6 F.3d 1573 (1993).

On July 5,1994, by order, unpublished, the value of SKI’s taken property was determined and judgment was ordered in the amount of $24,062.50, plus simple interest on that amount calculated from December 13, 1988, to the date of payment at rates determined under the method provided in 41 U.S.C. § 611. Judgment was entered July 12, 1994. The Federal Circuit affirmed on May 12, 1995. Table; 56 F.3d 82. The Supreme Court denied certiorari on October 2, 1995. -U.S. -, 116 S.Ct. 191, 133 L.Ed.2d 127 (1995).

The status of SKI’s operations at the Guantanamo Bay Naval Station on December 13, 1988, provides perspective on its eligibility for attorney fees and expenses. SKI was a small business operation engaged in contracting at Guantanamo Bay, Cuba, either as a prime contractor or as a subcontractor on Navy construction contracts.

The taking claims originate from a subcontract (JV-SKI) entered on June 17,1986, for work on a “turn key” contract for design and construction of 125 units of family housing (the Project). A joint venture (JV or AE-GlS-Zublin) held the prime contract (JV-[745]*745NAVY). The prime contract was a firm fixed-price construction contract in the amount of $11,595,000 entered on November 25,1985. SKI’s subcontract covered the construction work at a fixed price of $4,250,000.

In its work as construction subcontractor, SKI obtained approval from the JV and the Navy to locate a temporary building on Sherman Avenue for office space and warehouse/shop operations. The total cost of materials used to construct the temporary warehouse facility was $68,105. Progress payments for mobilization costs included $150,000 paid to SKI for the office and warehouse/shop facility on Sherman Avenue.

The prime contract provided that work would start on November 30, 1985, and the project was to be completed by July 23,1987. During the period 1986-88, the Project was delayed and substantial changes occurred in the relationships of the parties. One member of the JV filed under Chapter 11 of the Bankruptcy Code, and the other member (Zublin) took over completion of the Project. Disputes between SKI and Zublin culminated on November 5, 1987, in the start of arbitration proceedings on SKI’s claims for delays, nonpayment, and extended overhead.

Beneficial occupancy was given as to all housing units by August 21, 1988. As of August 30, 1988, most of the Project construction work had been completed, and occupancy by Navy personnel of the residential units was in progress. As of that date, a substantial amount of work remained outstanding. Numerous punch list items needed completion, and workmanship deficiencies directly attributable to SKI’s performance, and for which SKI was responsible, were substantial. Workmanship deficiencies included: improper welding, improper plumbing connections, failure to connect bathtub overflow drains, defective duct work, use of defective materials, and use of rejected materials.

In September 1988, SKI repudiated work on the Project. SKI performed no work on the Project after September 15, 1988. Prior to December 1988, the subcontract had been terminated by mutual agreement.

As of September 30,1988, the JV had paid SKI $4,073,058 for subcontract work. The balance owed was $16,963. As of September 30,1988, SKI had submitted to the JV claims for delays, nonpayment, and extended overhead, that totaled $940,000.

After August 1988, the business of SKI was in the process of winding down. SKI’s only contracts were at Guantanamo Bay and there were only a few contracts at that facility that required completion. On November 30, 1986, SKI’s income statement listed nine completed contracts and six contracts in progress. As of May 31,1988, SKI’s income statement listed four completed contracts and three contracts in progress. As of November 30, 1986, SKI had retained earnings of $2,084,748; on November 30, 1987, retained earnings were $3,021,047; on May 31, 1988, retained earnings were $1,675,866. SKI’s president represents that SKI performed no further work and conducted no other business after December 1988 beyond liquidation of its assets and completion of its contracts at Guantanamo Bay.

SKI’s labor force at Guantanamo Bay during the contract years approached a maximum of 250 to 300 workers. By December 1988, the labor force had been reduced to 15-20 workers.

On December 13, 1988, numerous items in the Project needed completion, and workmanship deficiencies directly attributable to SKI’s performance, and for which SKI was responsible, were substantial. Final completion of all warranty and punch list work was in August 1989.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lion Raisins, Inc. v. United States
57 Fed. Cl. 505 (Federal Claims, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
35 Fed. Cl. 742, 1996 U.S. Claims LEXIS 105, 1996 WL 332322, Counsel Stack Legal Research, https://law.counselstack.com/opinion/skip-kirchdorfer-inc-v-united-states-uscfc-1996.