Skinner Manufacturing Co. v. Carrier Engineering Corp.

203 N.W. 585, 113 Neb. 365, 1925 Neb. LEXIS 112
Nebraska Supreme Court·Decided April 16, 1925·No. No. 23046·Published

Opinion

Good, J.

Skinner Manufacturing Company, plaintiff, brought this action against Carrier Engineering Corporation, defendant, to recover the amount paid by plaintiff to defendant on a written contract for the installation, in plaintiff’s macaroni factory, of a system for drying macaroni and kindred products; also to recover the cost of removal of the machinery and equipment from its factory, expense of storage, and for damages for macaroni spoiled in the process of testing the machinery.

A copy of the contract is made a part of the petition, •and among other things provides: That defendant shall install, on the fourth floor of plaintiff’s factory in Omaha, ;a system for drying macaroni and kindred products; warrants that the machinery, when installed, will handle and thoroughly and uniformly dry 40,000 pounds of macaroni and kindred products within 24 hours, the finished product to be free from checks, cracks, splits and molds. It further provides that, in the event the system installed fails to meet the contract requirements, the defendant shall remove the machinery and appliances at its own expense and restore plaintiff’s building as nearly as possible to its original condition, and that defendant shall return to plaintiff any sums that have been paid on the purchase price of the machinery.

Plaintiff alleges that the machinery installed failed to meet the requirements of the contract; that, although requested so to do, defendant failed to remove the machinery from the manufacturing plant, and that it was removed by plaintiff at its own cost. Plaintiff also alleges that it has paid to defendant $13,936.23 on the purchase price of the machinery; that it has sustained damages in the cost of its removal and storage, also for macaroni spoiled in the process of testing the drying system, and prays for judgment in the aggregate sum of $49,544.45.

Defendant in its answer admits the making of the contract; the installation of the machinery; that it failed to meet the contract requirements to dry 40,000 pounds of [367]*367macaroni in 24 hours, and that $13,936.23 has been paid on the purchase price, but alleges that the machinery would properly dry the required amount of macaroni within a period of 48 hours; that the contract was then modified so as to provide that plaintiff would waive the time limit of 40,000 pounds within 24 hours, and accept the plant, provided defendant would install cams on the machinery, said cams, so requested, not being called for by the plans and specifications, and provided further that plaintiff be given an opportunity of testing the same for a period of 60 days; that, in reliance upon the contract as modified, defendant added to the plant the cams at a cost of approximately $2,000, and delivered the completed plant to plaintiff on October 1, 1919, for the purpose of permitting plaintiff to test the same and to determine whether or not the conditions of the contract, as modified, were complied with;. that such test was made during the period of time from. October 1, 1919, to December 1, 1919, when the completed plant was turned over and accepted by the plaintiff. Defendant further alleges that during all of said time the' plant and equipment complied with each and every condition called for by the contract, as modified; that after plaintiff accepted such plant, on December 1, 1919, it continued to use and operate the machinery for its business, without any demand, request or complaint of any kind or character, until March 1, 1921; that plaintiff knew the kind and character of the product produced by the machinery, and that it had continued to use the same from the 1st of October, 1919, down to the time of bringing the action, and that it is thereby estopped from claiming that the machinery does not comply with all the terms and conditions of the contract.

Defendant filed a counterclaim for the reasonable value of the machinery, which it alleges to be in excess of $41,000, and asks for judgment therefor, less the amount that has been paid on the purchase price.

Plaintiff in its reply denies that the written contract was modified as alleged by defendant, and further alleges [368]*368that in the early part of 1919 the defendant admitted that it was unable to fulfil its written contract, and requested permission to endeavor to so arrange the machinery and appliances, to see if it could accomplish the drying of 40,-000 pounds of macaroni within a 48-hour period, with the purpose of then seeing if the system, so arranged, would be desired by plaintiff, and, if'so, on what basis, and alleges that defendant failed in its efforts to make the system properly dry 40,000 pounds of macaroni within the 48-hour period, and that after defendant had ceased work upon its system plaintiff made every reasonable effort to test out the system, to see if it would uniformly dry 40,000 pounds of macaroni within the 48-hour period, and that the result of such test proved that the machinery could not and did not properly dry that amount of macaroni within the 48-hour period-. A trial of the issues to a jury resulted adversely to plaintiff and in a verdict and judgment thereon for defendant on its counterclaim in the sum of $20,000. Plaintiff appeals.

' There are numerous assignments of error, but the only ones argued and relied upon are that the verdict is not supported by the evidence and is contrary to law; error in giving certain instructions, and error in excluding certain exhibits offered in evidence by plaintiff.

As to many of the facts in issue, the evidence is-in sharp conflict. Plaintiff’s evidence tends to show that it thoroughly tried and tested the machinery, and that at no time would it properly dry 40,000 pounds of macaroni in 24 hours, or even in 48 hours, and that a large percentage of the product checked and cracked to such an extent that it was unfit for market; that, after thorough trial and testing, plaintiff requested defendant to remove the machinery from the factory; that defendant failed so to do, and thereupon plaintiff removed the machinery at its own expense. The evidence tends to show that a very large amount of the product that was attempted to be dried by the machinery and equipment, installed by defendant, checked and [369]*369cracked so that it was unmarketable and, as a consequence, plaintiff sustained great damage.

It is conceded by defendant that it was unable to make the machinery properly dry the macaroni within the 24-hour period, but its evidence tends very) strongly to show that it was able to and did properly dry the required amount of macaroni in 48 hours; that this product was used and marketed by the plaintiff, and that only a small amount of dried product was unfit for use, but that some macaroni was spoiled while defendant was endeavoring to make the plant operate on a 24-hour basis, and that plaintiff was allowed credit for the spoiled product, in accordance with statements of the amount thereof rendered by plaintiff.

Free access — add to your briefcase to read the full text and ask questions with AI

Skinner Manufacturing Co. v. Carrier Engineering Corp., 203 N.W. 585, 113 Neb. 365, 1925 Neb. LEXIS 112 (Neb. 1925).

203 N.W. 585 (Skinner Manufacturing Co. v. Carrier Engineering Corp.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Chambers v. . Lancaster
54 N.E. 707 (New York Court of Appeals, 1899)
Brown v. . Foster
15 N.E. 608 (New York Court of Appeals, 1888)
McCormick Harvesting Machine Co. v. Martin
49 N.W. 700 (Nebraska Supreme Court, 1891)
Phelps v. Williams
200 N.W. 831 (Nebraska Supreme Court, 1924)
Thomas China Co. v. C. W. Raymond Co.
135 F. 25 (Sixth Circuit, 1905)
Crescent Milling Co. v. H. N. Strait Mfg. Co.
227 F. 804 (Eighth Circuit, 1915)
Dodsworth v. Hercules Iron Works
66 F. 483 (Sixth Circuit, 1895)
Hercules Iron Works v. Dodsworth
57 F. 556 (U.S. Circuit Court for the District of Southern Ohio, 1893)