Hercules Iron Works v. Dodsworth

57 F. 556, 8 Ohio F. Dec. 17, 1893 U.S. App. LEXIS 2799
CourtU.S. Circuit Court for the District of Southern Ohio
DecidedOctober 2, 1893
DocketNo. 4,481
StatusPublished
Cited by2 cases

This text of 57 F. 556 (Hercules Iron Works v. Dodsworth) is published on Counsel Stack Legal Research, covering U.S. Circuit Court for the District of Southern Ohio primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Hercules Iron Works v. Dodsworth, 57 F. 556, 8 Ohio F. Dec. 17, 1893 U.S. App. LEXIS 2799 (circtsdoh 1893).

Opinion

TAFT, Circuit Judge.

A verdict was rendered by a jury duly ■impaneled in favor of the plaintiff, the Hercules Iron Works, for the purchase price of an ice machine furnished by plaintiff to defendants under 'a written contract and guaranty, less certain credits'which, plaintiff conceded, should be allowed on the claim. The •contract described the machine to be furnished by specifications of ’’its various parts, and contained the warranty “that the machine •shall be capable of producing 25 tons of good, crystal, merchantable [557]*557ice each twenty-four hours of continuous operation, provided it is kept in good order and properly handled, and the temperature of the condensing water is not above 60 degrees Fahrenheit.” The answer set up that the machine furnished had not been a compliance with the contract; that the machine furnished was not the article purchased; and that plaintiff had been notified that the machine was not accepted, and must be removed. It appeared beyond controversy that the machine was ready for operation about June 1, 1890; that it was operated during the summer and fall of that year; that the ice made was sold by and for the benefit of the defendants; that in September defendants sent word to plaintiff that the machine furnished did not fulfill the contract in any respect, and was not accepted, and requested its removal; that plaintiff declined to remove the same, claiming that there had been a full compliance with the contract on its part, and that the machine had been accepted by defendants in the July previous; that, after this correspondence, defendants continued to make ice with the machine during the remainder of September and October, 1890, and during the entire ice seasons of 1891 and 1892, and to sell the ice thus made for their own benefit. It was contended on the part of defendants that, if the machine failed in any material respect to fulfill the description of it in the contract, then this action, which was on the contract, must be defeated. In view of the evidence, the court declined to submit this issue to the jury. It appeared that the machine, described by parts in the contract, had been supplied in substantial compliance with the contract. Some of these parts were claimed to be defective, but none of the defects, if they existed, were of a character which could not be remedied by repairs at a cost very small in comparison with the cost of the machine.

It also was strongly contended that the machine would not make 25 tons of ice a day, and that failure in this was a failure in identity of the article furnished with that agreed to be furnished, so that recovery could only be had on a quantum valebat after defendants had declined to accept the machine under the contract, even if they subsequently kept and used the machine as their own. The court refused to take this view of the case, but charged the jury that the course of the defendants was an acceptance of the machine under the contract, which made the defendants liable for the contract price, but that they might recoup from that price damages of two kinds: First, the equivalent of the sum required to cure defects in the machine, as described by parts in the contract; and, second, the differences between the value of the machine producing the amount of ice per day it could produce and its value if it had been a 25-ton machine. It will not be necessary to review the correctness of this view of the law, for it was fully argued at the trial, and the conclusion reached only after full consideration. Counsel for defendants suggest that they were misled by some observations of the court early in the trial as to tin. rule of law on the general subject into thinking that the court [558]*558would submit to the jury the issue as to the identity of the machine furnished with that described in the contract, and that, relying on the merits of this issue, they did not adduce evidence of the difference' in value between the machine furnished and that contracted to be furnished. The remarks referred to, in mv opinion, cannot be reasonably construed to indicate any. such intention on the part of the court. The issues to be submitted could only be determined after the evidence had all been put in. The admitted facts at the close of the evidence showed that the defendants had actually accepted and used the ice machine which the plaintiff had furnished in attempted compliance with the contract. The machine furnished corresponded substantially in respect to size, form, measurements, material, and otherwise with that described in the contract. It would have been entirely proper for defendants to have introduced evidence of the value of the machine furnished, and of that to be furnished, whatever their contention as to a complete defense to the contract. They could not foresee with certainty what view the jury might take of the issue upon which their main contention was rested, even if the court had submitted it to the jury. If they were content to risk the decision of the jury on this issue, they risked also the action of the court in respect to the sufficiency of the evidence to raise the issue.

The main argument in support of the motion for a new trial is ■based' on the claim that the verdict is against the weight of the evidence. - The verdict was for the full amount claimed. The jury could not have returned the verdict without finding that the ice machine furnished would make 25 -tons of ice in a day, in continuous operation, when properly handled. This finding, counsel for defendants claim, is so clearly against the weight of the evidence as to require the court to set it aside. The machine in question was a "compression” machine; that is, the ammonia gas was reduced to a liquid by pressure effected in a “compressor,” and the cold was produced in this process of reduction. The liquid ammonia was forced through coils of one-inch iron pipe, placed in rows -in a large tank of brine, and reduced the brine to a temperature varying from 10° to- 17° Fahrenheit. In the tank of brine, or freezing tank, and between the coils of pipe, (which were 23 in number, 6 pipes high, and ran the width of the tank, 41-),- feet,) were 440 galvanized iron cans, 11 inches wide, 22 inches long, and 36 inches deep, in which was placed the water to be made into ice. The heat of' the water was extracted by the low temperature of the ■ brine, and after • a certain number of hours the water was frozen into a solid and clear cake, weighing on the average 250 pounds. It is said by counsel for defendants to be established by the -great weight of the evidence that the amount of pipe provided in the contract, and furnished under it, was not enough to make 25 tons- of ice la day. The only evidence to support this contention is that of one Rinman, the superintendent of the Blymyer Ice Machine Company, which makes a machine operating on a different' principle. from that of the plaintiff. Instead of re[559]*559ducing the ammonia gas to a liquid by pressure, this change is brought about by absoiption, and water is an agent in the process. The witness had had some little experience 1.0 or 12 years ago with compression machines. He said that, to produce a ton. of ice a day, from 815 to 830 lineal feet of 1-inch iron pipes were required for circulating the ammonia througli the brine. This would require from 7,875 to 8,250 feet of pipe. In the machine furnished there were but 5,727'feet of pipe in the freezing tank. If Rinman’a statement be true, then the machine as furnished could not furnish more that 5727-7875.of 25 tons a day; that is, not more than 18.18 tons.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Skinner Manufacturing Co. v. Carrier Engineering Corp.
203 N.W. 585 (Nebraska Supreme Court, 1925)
Detroit Heating & Lighting Co. v. Stevens
52 P. 379 (Utah Supreme Court, 1898)

Cite This Page — Counsel Stack

Bluebook (online)
57 F. 556, 8 Ohio F. Dec. 17, 1893 U.S. App. LEXIS 2799, Counsel Stack Legal Research, https://law.counselstack.com/opinion/hercules-iron-works-v-dodsworth-circtsdoh-1893.