Crescent Milling Co. v. H. N. Strait Mfg. Co.

227 F. 804, 142 C.C.A. 328, 1915 U.S. App. LEXIS 2347
CourtCourt of Appeals for the Eighth Circuit
DecidedOctober 12, 1915
DocketNo. 4331
StatusPublished
Cited by4 cases

This text of 227 F. 804 (Crescent Milling Co. v. H. N. Strait Mfg. Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crescent Milling Co. v. H. N. Strait Mfg. Co., 227 F. 804, 142 C.C.A. 328, 1915 U.S. App. LEXIS 2347 (8th Cir. 1915).

Opinion

AMIDON, District Judge.

The Strait Manufacturing Company was plaintiff below. It brought this action against the Crescent Milling Company to recover the purchase price of an engine. The contract • was in writing, and took the form of a proposal from the Manufacturing Company, and an acceptance by the Milling Company. It binds the plaintiff to supply and install in the defendant’s mill at Fairfax, Minn., a 300 indicated horse power horizontal tandem double acting gas engine, which engine is to operate the flouring mill of the purchaser, and the lighting plant of the village, and, at 150 revolutions per •minute, carry a load of 200 brake horse power, and a peak load 'of 264 horse power. The contract also contains numerous guaranties as to the amount of power which the engine will develop by the use Orf specified British thermal units of heat. While these qualities are sometimes spoken of as guaranties in the contract, they are by its express provision made conditions precedent to any liability on the part of tire purchaser to accept or pay for the engine. We quote from the contract the following language;

“In case said engine does not fulfill said test or satisfy said guaranties, said purchaser shall not be required to pay therefor, and said engine shall be forthwith removed by said corporation upon demand.”

[807]*807The contract provides for a 60-day endurance test by means of which the engine should be shown to possess the qualities specified in the contract. The engine was installed, and its use in defendant’s mill commenced on the 8th day of March, 1912. For various causes, partly due to the engine, and partly due to the fact that defendant found it necessary to put in new transmission machinery in its milling plant, the 60-day test was not commenced until July 25th. The engine, however, was run a large part of the time between its installation and that date. The endurance test extended from July 25th to September 23d. The result left the question whether the engine fulfilled the guaranties of the contract in controversy. Considerable trouble was experienced during the period. Plaintiff insisted that this was due to the quality of the gas furnished by defendant. Defendant insisted that it was due to defects in the engine. Plaintiff requested defendant to accept the engine and make the first payment at the conclusion of this test, in accordance with the terms of the contract. This defendant refused to do. The parties separated with the understanding that defendant should go on using the engine, and that plaintiff should supply some minor parts, which it was hoped would remedy the defects complained of by defendant. The correspondence continued for some three months — plaintiff urging an acceptance of the engine and a settlement; defendant continuing to use the engine, but refusing to accept or pay for it.

[1] The complaint is based upon the contract, which is set forth ir> full as an exhibit. It alleges that the engine was supplied by the plaintiff, installed, and tested, and that it fulfilled all the conditions of the contract. It contained no allegation on the subject of acceptance of the engine by defendant, or of a waiver of any of the conditions specified in the contract. The answer denies performance of the contract, by plaintiff, and alleges specifically the particulars wherein the engine failed to comply with the conditions and guaranties specified in the contract. No issue is raised on these guaranties by the answer, save only a failure of the plaintiff to perform its contract. The breach of the guaranties is not made the basis of any claim of damages upon the ground that the engine furnished is less valuable than the one contracted for. The answer, however, does set up by way of counterclaim two grounds of recovery: First, expenses incurred by the defendant in testing the engine; second, loss of profits in defendant’s milling and electric lighting operations by reason of the failure of the engine to furnish necessary power. On the 31st of March, 1913, counsel for plaintiff served upon defendant notice that at the trial of the action it would apply to the court for an order permitting an amendment of the complaint, adding the following allegation:

“That at all times since the completion of said endurance test, the defendant has continuously retained and used said engine.”

So far as we can discover from the record this motion was never brought to the notice of the court, or any order made permitting the amendment. Evidence, however, was received at the trial, without objection, showing that defendant had continuously used the engine in its mill, without any notice other than the answer, of its dissatis fac[808]*808tion, or any demand upon plaintiff to remove the same from defendant’s premises. The trial commenced April- 21, 1913. On the 7th day of May, while the trial was still progressing, defendant notified the plaintiff in writing to remove the engine from its plant. The trial court dealt with the case as if the complaint had been actually amended in accordance with the notice, and we think we must treat it in the same way. The trial resulted in a judgment in favor of plaintiff for the full purchase price. Defendant brings error.

[2-4] The trial court submitted to the jury the question as to whether defendant had, by its continued use of the engine, accepted it, and instructed the jury that if they found such acceptance they should then return a verdict in favor of plaintiff, less any reduction in the value of the engine due to its failure to fulfill the guaranties, and also less any damages allowed in respect of the counterclaims. Defendant insisted throughout the trial that the contract was still ex-ecutory, that no title to the engine had passed, and that defendant could not be held liable for any part of the purchase price if the engine failed to fulfill any of the guaranties. It made numerous requests that the case be submitted to the jury upon this theory, and took numerous exceptions challenging the charge of the court submitting the case to the jury in the manner above explained. All the important assignments of error rest upon this theory of the defense. If the theory is wrong, the assignments of error fail. We think the theory is wrong. At the time the original pleadings were drawn, it is possible that defendant might have stood upon such a theory. But when the summons was served it' was a call 'to defendant, not only to answer the complaint, but to decide what it would do with respect to the engine — whether it would reject it and demand its removal from its premises, or accept it, continue to use it, and rely upon a recovery of damages for any breach of the contract. It could not take both positions. It decided to keep the engine and use it. That election caused the title to pass to defendant. From that time forward the provisions o'f the contract ceased to be conditions precedent, and became collateral agreements. When the action was brought, defendant had already had a long experience with the engine. It had been in operation in its plant for nearly nine months. It had been subjected to an endurance test. As the result of that experience, defendant knew its qualities. There was .no evidence at the trial tending to show that anything of importance in regard to the engine was discovered after the action was brought. So when defendant continued to use it during the months that the action was pending, its conduct affords conclusive evidence that the engine was a “substantial performance” of the contract within the meaning of that term as used by this court in City of St. Charles v. Stookey. 154 Fed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
227 F. 804, 142 C.C.A. 328, 1915 U.S. App. LEXIS 2347, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crescent-milling-co-v-h-n-strait-mfg-co-ca8-1915.