Ski Acres Development Co. v. Douglas G. Gorman, Inc.

508 P.2d 1381, 8 Wash. App. 775, 1973 Wash. App. LEXIS 1505
CourtCourt of Appeals of Washington
DecidedApril 16, 1973
Docket1412-1
StatusPublished
Cited by10 cases

This text of 508 P.2d 1381 (Ski Acres Development Co. v. Douglas G. Gorman, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ski Acres Development Co. v. Douglas G. Gorman, Inc., 508 P.2d 1381, 8 Wash. App. 775, 1973 Wash. App. LEXIS 1505 (Wash. Ct. App. 1973).

Opinion

Williams, J.

Ski Acres Development Company, as owner, brought this action against Douglas G. Gorman, Inc., and United Masonry, Inc., contractors, and Eugene G. Mushkin and Harvey Dodd & Associates, a design team, to recover for damages to its building which occurred when an overburden of snow crushed a substantial portion of it. The cause was tried before the court and a jury. When all of the evidence was in, but before the jury was instructed, the design team was dismissed. Thereafter, the jury returned a verdict in favor of Ski Acres and against the contractors; Gorman in the amount of $100,686.72 and United Masonry in the amount of $35,685.01. The contractors moved for a reduction of the verdict by the 'amount paid to Ski Acres by the design team to secure its dismissal, and by the amount still owing by Ski Acres on the building contract. The motion was granted and judgment entered accordingly. Ski Acres appeals, assigning as error the two reductions and the refusal of the trial court to allow interest.

The facts which must be related for a review of the questions raised are these: Ski Acres employed Mushkin to design a large condominium to be built in an alpine recreation area of Kittitas County. Mushkin brought in Harvey Dodd & Associates, structural engineers, to assist in preparing the plans and to aid him in making inspections during construction. Gorman was awarded the construction contract by Ski Acres and subcontracted the chimney work to United Masonry. When the building was almost completed, and at a time when considerable snow had accumulated on the roof, some of the chimneys and gables fell off, resulting *777 in substantial damage to the structure. In its complaint, Ski Acres placed responsibility for the disaster as follows:

By reason of the negligence of each of said defendants and by reason of the further failure of the defendant, Douglas G. Gorman, Inc. to comply with the plans and specifications; and by reason of the further failure of the defendants, Mushkin and Harvey Dodd & Associates, to properly design and/or inspect during the course of construction, the said building was partially destroyed in March of 1969 when chimneys and gables tore away from the main structure, and other damage occurred to the structure. As a result, plaintiff has been damaged in the sum of $245,000.00.
The prayer was:
Wherefore, plaintiff prays for judgment against the defendants and each of them in the sum of $245,000.00 together with plaintiff’s costs and disbursements incurred herein.

The jury returned a verdict in favor of Ski Acres and against Gorman for $100,686.72 and United Masonry for $35,685.01. Acting upon a post-trial motion of the contractors, the court reduced the verdict by $76,500, which was the amount that the design team had paid Ski Acres to be dismissed from the case, and it set off $37,164.73 which was the unpaid balance on the contract. 1

The first question is whether the trial court erred in reducing the verdict by the amount paid to Ski Acres by the design team. Ski Acres argues that, in view of the proven cost of repair in the amount of $153,206.66 and its indirect cost of approximately $98,000, the jury, with a verdict totaling $136,371.73, must have deducted the losses attributable to the design team before arriving at the verdict. In this connection, Ski Acres contends that the losses should be segregated and that the contractors had the burden of making the separation.

The applicable rule, which was adopted by this *778 court in Christianson v. Plumb, 7 Wn. App. 309, 311, 499 P.2d72 (1972),is:

(3) Payments made by one tortfeasor on account of a harm for which he and another are each liable, diminish the amount of the claim against the other whether or not it was so agreed at the time of payment and whether the payment was made before or after judgment; the extent of the diminution is the amount of the payment made, or a greater amount if so agreed between the payor and the injured person.

Restatement of Torts § 885 (3) (1939).

In order for Ski Acres to prevail on this point, it must appear that the harm caused could be and was ascribed to the several tort-feasors, individually, so that the jury could apportion the responsibility of each. The loss consisted of the collapse of a substantial portion of a large building. The fault of both the design team and the contractors was inextricably woven into the evidence. No effort was made by any party to assess the particular responsibility for the damages between the design team and the contractors.

As might be expected, the trial strategy of Ski Acres was to place the causes of the loss upon both the contractor and the design team, and they, in turn, blamed each other. This resulted in a trial record of 1,667 pages containing substantial evidence that each party was responsible for almost all of the damages. As noted, there was a segregation between Goman and United Masonry, but this was a separate issue between the contractor and subcontractor and is not involved in this appeal.

The instructions given by the court which directly bear upon the question of segregation are as follows:

The fact that the defendants, Eugene G. Mushkin and Harvey R. Dodd & Associates, Inc. have been dismissed as defendants by the plaintiff, should have no bearing on your deliberations in this case. In your deliberations, you shall determine the issues between the plaintiff and the defendants disregarding entirely the fact that there may have been originally more defendants in the case.

Instruction No. 2

*779 There may be more than one proximate cause of a damage; that is to say, there may be lack of ordinary care on the part of more than one person. Where the concurring negligence of two or more persons results in damage to a third person, the third person may recover from either or all of them, but only one amount, without regard to a weighing of negligence or an attempted determination of who is the most negligent.
If you find from the evidence that more than one person was guilty of negligence in any of the particulars charged, and that the negligence of each was one of the proximate causes of the damages, then your verdict must be in favor of the plaintiff and against each defendant thus found to be negligent, whether or not other persons were also negligent.

Instruction No. 8

You are instructed that a defendant is not to be found negligent by reason of faulty design if he performed in compliance with plans and specifications furnished to him by the owner, nor is United Masonry to be found negligent by reason of faulty design if they performed in compliance with plans and specifications furnished to them pursuant to their agreement with Gorman unless they negligently failed to discover a variation between those plans and the plans specified in the contract between the owner and Gorman, or, if they discovered such a variation, unless they were negligent with respect thereto.

Instruction No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State of Washington v. Blake Alexander Badgley
Court of Appeals of Washington, 2023
Rekhter v. Dep't of Soc. & Health Servs.
Washington Supreme Court, 2014
Rekhter v. Department of Social & Health Services
323 P.3d 1036 (Washington Supreme Court, 2014)
Bouten Construction Co. v. H.F. Magnuson Co.
992 P.2d 751 (Idaho Supreme Court, 1999)
AKER VERDAL A/S v. Neil F. Lampson, Inc.
828 P.2d 610 (Court of Appeals of Washington, 1992)
Maryhill Museum of Fine Arts v. Emil's Concrete Construction Co.
751 P.2d 866 (Court of Appeals of Washington, 1988)
Tri-M Erectors, Inc. v. Donald M. Drake Co.
618 P.2d 1341 (Court of Appeals of Washington, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
508 P.2d 1381, 8 Wash. App. 775, 1973 Wash. App. LEXIS 1505, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ski-acres-development-co-v-douglas-g-gorman-inc-washctapp-1973.