Skanska U.S. Bldg. Inc. v. Atl. Yards B2 Owner, LLC

98 N.E.3d 720, 74 N.Y.S.3d 805, 31 N.Y.3d 1002
CourtCourt for the Trial of Impeachments and Correction of Errors
DecidedApril 26, 2018
DocketNo. 38
StatusPublished
Cited by31 cases

This text of 98 N.E.3d 720 (Skanska U.S. Bldg. Inc. v. Atl. Yards B2 Owner, LLC) is published on Counsel Stack Legal Research, covering Court for the Trial of Impeachments and Correction of Errors primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Skanska U.S. Bldg. Inc. v. Atl. Yards B2 Owner, LLC, 98 N.E.3d 720, 74 N.Y.S.3d 805, 31 N.Y.3d 1002 (N.Y. Super. Ct. 2018).

Opinion

MEMORANDUM.

***1004**806The order of the Appellate Division, insofar as appealed from, should be affirmed, with costs, and the certified question answered in the affirmative. We conclude that the courts below properly dismissed plaintiff Skanska USA Building Inc.'s claim that defendant Atlantic Yards B2 Owner, LLC (B2 Owner) breached the Construction Management and Fabrication Services Agreement (the CM Agreement) by allegedly failing to comply with Lien Law § 5. Plaintiff failed to allege the existence of any provision in the CM Agreement requiring compliance with that statute.

In July 2006, the New York State Urban Development Corporation d/b/a Empire State Development (ESD), a public benefit corporation, adopted a plan for Atlantic Yards, a 22-acre mixed-use development project in Brooklyn. ESD, which is not a party to this action, entered into a Development Agreement with nonparty entities affiliated with B2 Owner to develop the project site. ESD also entered into a Lease Agreement with FC Atlantic Yards B2, LLC (Tenant), another nonparty affiliate of B2 Owner, to lease a parcel of land within the Atlantic Yards site to Tenant. Under the Lease Agreement, Tenant agreed that certain buildings would be constructed on the leased premises, including the B2 Building, a proposed 34-floor residential high-rise. Plaintiff is not a party to either the Development Agreement or the Lease Agreement. Those agreements required Tenant to "satisfy all requirements of Section 5 of the New York State Lien Law... as such requirements and law are interpreted from time to time *722by [ESD]." Pursuant to the terms of the Lease Agreement, nonparty Forest City Enterprise, Inc. (FCE), a minority owner of B2 Owner, made a ***1005Guaranty in favor of ESD which, among other things, guaranteed Tenant's completion of the construction work and that Tenant would use all monies disbursed by the lender to pay all costs, expenses, and liabilities-including construction costs-incurred in connection with the guaranteed work.

Plaintiff and B2 Owner separately entered into the CM Agreement, pursuant to which plaintiff agreed to construct the B2 Building in exchange for approximately $116 million. B2 Owner issued to plaintiff a "Notice to Proceed" under the CM Agreement, setting the substantial completion deadline for the B2 Building. Construction was delayed for reasons disputed by the parties. After the deadline passed, plaintiff sent B2 Owner a notice of its intent to terminate the CM Agreement asserting, among other things, that B2 Owner breached the CM Agreement by failing to post a bond or undertaking in violation of Lien Law § 5. That statute provides, in relevant part, that where there is no public fund to finance a public improvement with an estimated cost in excess of $250,000, "the chief financial officer of the public owner shall require the private entity for whom the public improvement is being made to post, or cause to be posted, a bond or other form of undertaking guaranteeing prompt payment of moneys due to the contractor, his or her subcontractors and to all persons furnishing labor or materials" ( Lien Law § 5 ).

Plaintiff subsequently stopped work on the B2 Building and purported to terminate the CM Agreement. Thereafter, plaintiff commenced this action against B2 Owner and Forest City Ratner Companies, LLC (FCRC), asserting, among other things, a claim for breach of the CM Agreement premised on B2 Owner's alleged **807failure to comply with Lien Law § 5.1 Defendants moved to dismiss that claim pursuant to CPLR 3211(a)(1) and (7), and Supreme Court granted the motion.

Upon plaintiff's appeal, the Appellate Division, with two Justices dissenting in part, modified and, as so modified, affirmed ( 146 A.D.3d 1, 40 N.Y.S.3d 46 [1st Dept. 2016] ). As relevant here, the Appellate Division affirmed the dismissal of plaintiff's contract ***1006claim based on the alleged violation of Lien Law § 5.2 The Court held that the Guaranty issued by FCE satisfied the mandate of section 5, while the dissenting Justices would have held that the Guaranty did not qualify as an "other form of undertaking" within the meaning of the statute. The Appellate Division granted plaintiff leave to appeal, certifying the question of whether its order was properly made ( 2017 N.Y. Slip Op. 66053[U], 2017 WL 830227 [1st Dept.2017] ).

It is axiomatic that, "when parties set down their agreement in a clear, complete document, their writing should as a rule be enforced according to its terms" ( W.W.W. Assoc. v. Giancontieri, 77 N.Y.2d 157, 162, 565 N.Y.S.2d 440, 566 N.E.2d 639 [1990] ; see Reiss v. Financial Performance Corp., 97 N.Y.2d 195, 198, 738 N.Y.S.2d 658, 764 N.E.2d 958 [2001] ). In that regard, "[c]ourts may not, through their interpretation of a contract, add or excise terms or distort the meaning of any particular *723words or phrases, thereby creating a new contract under the guise of interpreting the parties' own agreements" ( Nomura Home Equity Loan, Inc., Series 2006-FM2 v. Nomura Credit & Capital, Inc., 30 N.Y.3d 572, 581, 69 N.Y.S.3d 520, 92 N.E.3d 743 [2017] ). "We have ... emphasized this rule's special import 'in ... context [s] ... where commercial certainty is a paramount concern, and where ... the instrument [at issue] was negotiated between sophisticated ... business people ... at arm's length' " ( Vermont Teddy Bear Co. v. 538 Madison Realty Co.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sawyer v. 1120 Fifth Ave. Corp.
2025 NY Slip Op 02890 (Appellate Division of the Supreme Court of New York, 2025)
Iberdrola Energy Projects v. Oaktree Capital Mgt. L.P.
2024 NY Slip Op 03798 (Appellate Division of the Supreme Court of New York, 2024)
G & Y Maintenance Corp. v. Core Cont. Constr. LLC
2023 NY Slip Op 02061 (Appellate Division of the Supreme Court of New York, 2023)
Kostyatnikov v. HFZ Capital Group LLC
183 N.Y.S.3d 15 (Appellate Division of the Supreme Court of New York, 2023)
Etage Real Estate LLC v. Stern
211 A.D.3d 632 (Appellate Division of the Supreme Court of New York, 2022)
Rich v. J.A. Madison, LLC
211 A.D.3d 652 (Appellate Division of the Supreme Court of New York, 2022)
ZL Elmhurst, LLC v. Sunshine Elmhurst Real Estate
161 N.Y.S.3d 779 (Appellate Division of the Supreme Court of New York, 2022)
Parlux Fragrances, LLC v. S. Carter Enters., LLC
204 A.D.3d 72 (Appellate Division of the Supreme Court of New York, 2022)
Dan's Hauling & Demo, Inc. v. GMMM Hickling, LLC
2021 NY Slip Op 02693 (Appellate Division of the Supreme Court of New York, 2021)
World Wide Packaging, LLC v. Cargo Cosmetics, LLC
2021 NY Slip Op 02088 (Appellate Division of the Supreme Court of New York, 2021)
Walsam 316, LLC v. 316 Bowery Realty Corp.
2021 NY Slip Op 00399 (Appellate Division of the Supreme Court of New York, 2021)
A Great Choice Lawncare & Landscaping, LLC v. Carlini
2018 NY Slip Op 8984 (Appellate Division of the Supreme Court of New York, 2018)
Newmont Mining Corp. v. Anglogold Ashanti Ltd.
344 F. Supp. 3d 724 (S.D. Illinois, 2018)
Skanska USA Bldg. Inc. v. Atlantic Yards B2 Owner, LLC
31 N.Y.3d 1002 (New York Court of Appeals, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
98 N.E.3d 720, 74 N.Y.S.3d 805, 31 N.Y.3d 1002, Counsel Stack Legal Research, https://law.counselstack.com/opinion/skanska-us-bldg-inc-v-atl-yards-b2-owner-llc-nycterr-2018.