Dan's Hauling & Demo, Inc. v. GMMM Hickling, LLC
This text of 2021 NY Slip Op 02693 (Dan's Hauling & Demo, Inc. v. GMMM Hickling, LLC) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
| Dan's Hauling & Demo, Inc. v GMMM Hickling, LLC |
| 2021 NY Slip Op 02693 |
| Decided on April 30, 2021 |
| Appellate Division, Fourth Department |
| Published by New York State Law Reporting Bureau pursuant to Judiciary Law § 431. |
| This opinion is uncorrected and subject to revision before publication in the Official Reports. |
Decided on April 30, 2021 SUPREME COURT OF THE STATE OF NEW YORK Appellate Division, Fourth Judicial Department
PRESENT: PERADOTTO, J.P., CARNI, NEMOYER, WINSLOW, AND BANNISTER, JJ.
1068 CA 19-01886
v
GMMM HICKLING, LLC, HICKLING POWER DEVELOPMENT, LLC, POWER DEVELOPMENT HOLDINGS, LLC, AND JOHN PACHECO, DEFENDANTS-RESPONDENTS.
THE STEELE LAW FIRM, P.C., OSWEGO (KIMBERLY A. STEELE OF COUNSEL), FOR PLAINTIFF-APPELLANT.
GOLDBERG SEGALLA LLP, ROCHESTER (JAMES M. PAULINO, II, OF COUNSEL), FOR DEFENDANTS-RESPONDENTS.
Appeal from an order of the Supreme Court, Steuben County (Matthew A. Rosenbaum, J.), entered October 3, 2019. The order, among other things, denied the cross motion of plaintiff seeking, inter alia, summary judgment on the breach of contract cause of action and granted defendants summary judgment dismissing that cause of action.
It is hereby ORDERED that the order so appealed from is unanimously modified on the law by vacating the second ordering paragraph and reinstating the first cause of action, and as modified the order is affirmed without costs.
Memorandum: This appeal arises from an asset purchase and sale agreement (agreement) between plaintiff and defendants in which plaintiff agreed to remove hazardous materials from defendants' power plant, perform demolition work, and pay a sum of money to defendants, and in exchange plaintiff could remove salvaged metal generated by the project, which plaintiff would then sell to others. Pursuant to the agreement, plaintiff agreed to pay defendants the "purchase price" in four installments. As relevant here, the agreement's payment clause states: "First Installment: Due and payable on the earlier of (i) 30 calendar days after completion of the Abatement or commencement of the Demolition portion of the Work, whichever occurs first; and (ii) the Removal . . . of 3,500 tons of Salvaged Metals . . . from the Property."
While the project was underway, defendants terminated the agreement pursuant to the payment clause on the ground that over 30 days had passed after the commencement of demolition and plaintiff had failed to make the first installment payment. On appeal, it is not disputed that the abatement work had not been completed and that plaintiff had not removed 3,500 tons of salvaged metals from the property.
Plaintiff thereafter initiated this action, asserting, inter alia, a breach of contract cause of action based on allegations that defendants breached the agreement by terminating it before plaintiff's first installment became due. According to plaintiff's interpretation of the payment clause, its obligation to make the first installment payment required two triggering events: (1) 30 days passing from either the completion of the abatement or the commencement of demolition, whichever occurred first; and (2) the removal of 3,500 tons of salvaged metals from the project. Plaintiff alleged that its payment obligation had not triggered because it had not removed 3,500 tons of salvaged metals.
Defendants answered and asserted various counterclaims, including a counterclaim for breach of contract. According to defendants' interpretation of the payment clause, plaintiff's obligation to make the first installment payment required one triggering event, which could be either: (1) 30 days passing from the completion of abatement; (2) 30 days passing from the [*2]commencement of demolition; or (3) removal of 3,500 tons of salvaged metals. In other words, defendants applied the phrase "on the earlier of" in the payment clause to mean the earlier of romanette "i" or romanette "ii," whereas plaintiff applied "on the earlier of" to apply only to the two events described within romanette "i," rendering both romanette "i" and "ii" necessary prerequisites to its first installment obligation.
Shortly after plaintiff commenced this action, Supreme Court granted plaintiff's request for preliminary injunctive relief and directed defendants to, inter alia, allow plaintiff back onto the property to continue its work pursuant to the agreement.
Following other motion practice not at issue on appeal, plaintiff cross-moved for, among other things, summary judgment on the complaint or, alternatively, on the issue of liability only, and an order holding defendants in contempt of the court's order granting preliminary injunctive relief.
The court, inter alia, denied plaintiff's cross motion for summary judgment and, sua sponte, searched the record and granted defendants summary judgment dismissing plaintiff's breach of contract cause of action and on their first counterclaim, for breach of contract. In its decision, the court adopted defendants' interpretation of the payment clause, holding that plaintiff's obligation to pay triggered, as relevant here, upon the earlier of 30 days passing from the start of demolition or the removal of 3,500 tons of salvaged metals. Plaintiff appeals.
Contrary to plaintiff's contention, plaintiff failed to meet its initial burden on its cross motion for summary judgment. " 'The words and phrases used by the parties must, as in all cases involving contract interpretation, be given their plain meaning' " (Ellington v EMI Music, Inc., 24 NY3d 239, 244 [2014]). " '[A] written agreement that is complete, clear and unambiguous on its face must be enforced according to the plain meaning of its terms' " (Auburn Custom Millwork, Inc. v Schmidt & Schmidt, Inc., 148 AD3d 1527, 1529 [4th Dept 2017]; see Skanska USA Bldg. Inc. v Atlantic Yards B2 Owner, LLC, 31 NY3d 1002, 1006 [2018], rearg denied 31 NY3d 1141 [2018]). " 'Whether a contract is ambiguous is a question of law and extrinsic evidence may not be considered unless the document itself is ambiguous' " (Auburn Custom Millwork, Inc., 148 AD3d at 1529; see generally Tomhannock, LLC v Roustabout Resources, LLC, 33 NY3d 1080, 1082 [2019]; Maven Tech., LLC v Vasile, 147 AD3d 1377, 1378 [4th Dept 2017]). "An agreement is unambiguous if the language it uses has a definite and precise meaning, unattended by danger of misconception in the purport of the [agreement] itself, and concerning which there is no reasonable basis for a difference of opinion" (Ellington, 24 NY3d at 244 [internal quotation marks omitted]). "Ambiguity in a contract arises where the contract, read as a whole, fails to disclose its purpose and the parties' intent . . . , or where specific language is susceptible of two reasonable interpretations" (id.; see Ames v County of Monroe, 162 AD3d 1724, 1726 [4th Dept 2018]). If a contract is ambiguous, "extrinsic or parol evidence may be then permitted to determine the parties' intent as to the meaning of that language" (Ames, 162 AD3d at 1726 [internal quotation marks omitted]). "[A] party seeking summary judgment has the burden of establishing that the construction it favors is the only construction which can fairly be placed thereon" (Auburn Custom Millwork, Inc.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
2021 NY Slip Op 02693, 147 N.Y.S.3d 805, 193 A.D.3d 1404, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dans-hauling-demo-inc-v-gmmm-hickling-llc-nyappdiv-2021.