Auburn Custom Millwork, Inc. v. Schmidt & Schmidt, Inc.

148 A.D.3d 1527, 50 N.Y.S.3d 635
Appellate Division of the Supreme Court of the State of New York·Decided March 24, 2017·Published·Cited by 11 cases

Opinion

Appeal and cross appeal from an order of the Supreme Court, Cayuga County (Matthew A. Rosenbaum, J.), entered February 25, 2016. The order, among other things, denied in part plaintiff’s motion for summary judgment and denied defendant’s cross motion for summary judgment.

It is hereby ordered that the order so appealed from is unanimously modified on the law by denying plaintiff’s motion in its entirety and vacating the award of damages, and as modified the order is affirmed without costs.

Memorandum: Defendant, a general contractor, entered into a contract with the Town of Charlton (Town) in August 2006 for the construction of a town hall building. The architect hired by the Town prepared detailed specifications for the project. Plaintiff, a manufacturer of architectural millwork, submitted [1528] a quote to defendant for the fabrication and delivery of custom millwork for the project. Defendant’s president, Walter Schmidt, issued an initial purchase order agreeing to the quoted price and setting forth certain conditions, including the requirement that plaintiff forward “submittals” of its product data and shop drawings. Upon the request of plaintiff’s owner and president, Christopher J. Colella, Schmidt subsequently issued a revised purchase order that removed a condition of the agreement that had purported to make the purchase order itself pending architect approval of the submittals, and replaced that condition with a different requirement. Plaintiff produced and delivered certain millwork, and then sent a first invoice to defendant in June 2007, which defendant paid. Plaintiff also produced and shipped custom millwork identified in a second invoice, which was issued in August 2007. In the meantime, apparently as a result of contentious relations between defendant and the Town and its architect, including difficulties in obtaining approved submittals, the Town terminated defendant’s contract for cause in September 2007. Defendant’s surety was called upon to facilitate completion of the project pursuant to defendant’s public improvement performance bond. Thereafter, plaintiff’s then-manager of accounts payable and receivable followed up with Schmidt by email in early October 2007 about the second invoice being unpaid and the fact that plaintiff had other completed material stored at its facility ready for the project. Schmidt replied the following day, requesting that plaintiff forward an itemized bill reflecting materials delivered and costs incurred to date for review by the bonding company. Plaintiff subsequently sent defendant a third invoice in October 2007. The remaining millwork identified in the third invoice was stored at plaintiff’s offices pending defendant’s request that it be shipped to the project.

Plaintiff subsequently commenced this action for breach of contract, unjust enrichment and an account stated, seeking to recover the amount of the unpaid second and third invoices plus interest and attorneys’ fees. Supreme Court, among other things, granted that part of plaintiff’s motion for summary judgment on the breach of contract cause of action and awarded plaintiff damages, denied that part of plaintiff’s motion seeking summary judgment on the account stated cause of action, and denied defendant’s cross motion for summary judgment dismissing the complaint. Defendant appeals, and plaintiff cross-appeals.

On its appeal, defendant contends that the court erred in granting plaintiff’s motion in part inasmuch as there are tri[1529] able issues of fact with respect to the breach of contract cause of action. We agree. “It is well settled that the elements of a breach of contract cause of action are ‘the existence of a contract, the plaintiffs performance under the contract, the defendant’s breach of that contract, and resulting damages’ ” (Niagara Foods, Inc. v Ferguson Elec. Serv. Co., Inc., 111 AD3d 1374, 1376 [2013], lv denied 22 NY3d 864 [2014]). It is undisputed that the revised purchase order constituted the contract between the parties. The parties dispute, however, whether the revised purchase order required that plaintiff comply with the procedure for obtaining architect approval of its submittals as set forth in the specifications and, if so, whether plaintiff performed its contractual obligations.

“[A] written agreement that is complete, clear and unambiguous on its face must be enforced according to the plain meaning of its terms” (Greenfield v Philles Records, 98 NY2d 562, 569 [2002]). “Whether a contract is ambiguous is a question of law and extrinsic evidence may not be considered unless the document itself is ambiguous” (South Rd. Assoc., LLC v International Bus. Machs. Corp., 4 NY3d 272, 278 [2005]; see Greenfield, 98 NY2d at 569). “The proper inquiry in determining whether a contract is ambiguous is whether the agreement on its face is reasonably susceptible of more than one interpretation [,] . . . [and a] party seeking summary judgment has the burden of establishing that the construction it favors is the only construction which can fairly be placed thereon” (Kibler v Gillard Constr., Inc., 53 AD3d 1040, 1042 [2008] [internal quotation marks omitted]).

Here, plaintiff failed to meet that burden. In relevant part, the initial purchase order issued by defendant following plaintiff’s quote required as the first condition that “Submit-tals . . . include (6) copies” of “Product Data” and “Shop Drawings”; specified in the second condition that the purchase order would be “pending architect approved submittals”; and requested in the sixth condition that submittals be forwarded at plaintiff’s first opportunity. Plaintiff thereafter requested a change to the language on the ground that the purchase order itself could not be made contingent on the architect’s approval of submittals because the parties would be under a binding agreement once plaintiff started shop drawings. In response, defendant issued the revised purchase order that retained the other conditions, but replaced the challenged language in the second condition with the requirement that “[a]ll work . . . comply with drawings and specifications.” Thus, on its face, the revised purchase order contemplated that plaintiff, as part of [1530] its contractual obligations, would be required to forward submittals; however, it did not provide any definite or precise language regarding the nature of the submittal procedure or the requirements thereof.

Free access — add to your briefcase to read the full text and ask questions with AI

Auburn Custom Millwork, Inc. v. Schmidt & Schmidt, Inc., 148 A.D.3d 1527, 50 N.Y.S.3d 635 (N.Y. Ct. App. 2017).

148 A.D.3d 1527 (Auburn Custom Millwork, Inc. v. Schmidt & Schmidt, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Weiner v. Weiner
2024 NY Slip Op 03611 (Appellate Division of the Supreme Court of New York, 2024)
Ali-Hasan v. St. Peter's Health Partners Med. Assoc., P.C.
2024 NY Slip Op 01966 (Appellate Division of the Supreme Court of New York, 2024)
Wilsey v. 7203 Rawson Rd., LLC
2022 NY Slip Op 02905 (Appellate Division of the Supreme Court of New York, 2022)
Dan's Hauling & Demo, Inc. v. GMMM Hickling, LLC
2021 NY Slip Op 02693 (Appellate Division of the Supreme Court of New York, 2021)
Founders Pavilion, Inc. v. Pavilion Operations, LLC
2021 NY Slip Op 01657 (Appellate Division of the Supreme Court of New York, 2021)
Hubbell, Inc. v. Lazy Swan Golf & Country Club LLC
2020 NY Slip Op 06182 (Appellate Division of the Supreme Court of New York, 2020)
Targeted Lease Capital, LLC v. Wheel Equip. Leasing, LLC
2020 NY Slip Op 05625 (Appellate Division of the Supreme Court of New York, 2020)
Proline Concrete of WNY, Inc. v. G.M. Crisalli & Assoc., Inc.
2019 NY Slip Op 8299 (Appellate Division of the Supreme Court of New York, 2019)