Auburn Custom Millwork, Inc. v. Schmidt & Schmidt, Inc.

148 A.D.3d 1527, 50 N.Y.S.3d 635

This text of 148 A.D.3d 1527 (Auburn Custom Millwork, Inc. v. Schmidt & Schmidt, Inc.) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Auburn Custom Millwork, Inc. v. Schmidt & Schmidt, Inc., 148 A.D.3d 1527, 50 N.Y.S.3d 635 (N.Y. Ct. App. 2017).

Opinion

Appeal and cross appeal from an order of the Supreme Court, Cayuga County (Matthew A. Rosenbaum, J.), entered February 25, 2016. The order, among other things, denied in part plaintiff’s motion for summary judgment and denied defendant’s cross motion for summary judgment.

It is hereby ordered that the order so appealed from is unanimously modified on the law by denying plaintiff’s motion in its entirety and vacating the award of damages, and as modified the order is affirmed without costs.

Memorandum: Defendant, a general contractor, entered into a contract with the Town of Charlton (Town) in August 2006 for the construction of a town hall building. The architect hired by the Town prepared detailed specifications for the project. Plaintiff, a manufacturer of architectural millwork, submitted [1528]*1528a quote to defendant for the fabrication and delivery of custom millwork for the project. Defendant’s president, Walter Schmidt, issued an initial purchase order agreeing to the quoted price and setting forth certain conditions, including the requirement that plaintiff forward “submittals” of its product data and shop drawings. Upon the request of plaintiff’s owner and president, Christopher J. Colella, Schmidt subsequently issued a revised purchase order that removed a condition of the agreement that had purported to make the purchase order itself pending architect approval of the submittals, and replaced that condition with a different requirement. Plaintiff produced and delivered certain millwork, and then sent a first invoice to defendant in June 2007, which defendant paid. Plaintiff also produced and shipped custom millwork identified in a second invoice, which was issued in August 2007. In the meantime, apparently as a result of contentious relations between defendant and the Town and its architect, including difficulties in obtaining approved submittals, the Town terminated defendant’s contract for cause in September 2007. Defendant’s surety was called upon to facilitate completion of the project pursuant to defendant’s public improvement performance bond. Thereafter, plaintiff’s then-manager of accounts payable and receivable followed up with Schmidt by email in early October 2007 about the second invoice being unpaid and the fact that plaintiff had other completed material stored at its facility ready for the project. Schmidt replied the following day, requesting that plaintiff forward an itemized bill reflecting materials delivered and costs incurred to date for review by the bonding company. Plaintiff subsequently sent defendant a third invoice in October 2007. The remaining millwork identified in the third invoice was stored at plaintiff’s offices pending defendant’s request that it be shipped to the project.

Plaintiff subsequently commenced this action for breach of contract, unjust enrichment and an account stated, seeking to recover the amount of the unpaid second and third invoices plus interest and attorneys’ fees. Supreme Court, among other things, granted that part of plaintiff’s motion for summary judgment on the breach of contract cause of action and awarded plaintiff damages, denied that part of plaintiff’s motion seeking summary judgment on the account stated cause of action, and denied defendant’s cross motion for summary judgment dismissing the complaint. Defendant appeals, and plaintiff cross-appeals.

On its appeal, defendant contends that the court erred in granting plaintiff’s motion in part inasmuch as there are tri[1529]*1529able issues of fact with respect to the breach of contract cause of action. We agree. “It is well settled that the elements of a breach of contract cause of action are ‘the existence of a contract, the plaintiffs performance under the contract, the defendant’s breach of that contract, and resulting damages’ ” (Niagara Foods, Inc. v Ferguson Elec. Serv. Co., Inc., 111 AD3d 1374, 1376 [2013], lv denied 22 NY3d 864 [2014]). It is undisputed that the revised purchase order constituted the contract between the parties. The parties dispute, however, whether the revised purchase order required that plaintiff comply with the procedure for obtaining architect approval of its submittals as set forth in the specifications and, if so, whether plaintiff performed its contractual obligations.

“[A] written agreement that is complete, clear and unambiguous on its face must be enforced according to the plain meaning of its terms” (Greenfield v Philles Records, 98 NY2d 562, 569 [2002]). “Whether a contract is ambiguous is a question of law and extrinsic evidence may not be considered unless the document itself is ambiguous” (South Rd. Assoc., LLC v International Bus. Machs. Corp., 4 NY3d 272, 278 [2005]; see Greenfield, 98 NY2d at 569). “The proper inquiry in determining whether a contract is ambiguous is whether the agreement on its face is reasonably susceptible of more than one interpretation [,] . . . [and a] party seeking summary judgment has the burden of establishing that the construction it favors is the only construction which can fairly be placed thereon” (Kibler v Gillard Constr., Inc., 53 AD3d 1040, 1042 [2008] [internal quotation marks omitted]).

Here, plaintiff failed to meet that burden. In relevant part, the initial purchase order issued by defendant following plaintiff’s quote required as the first condition that “Submit-tals . . . include (6) copies” of “Product Data” and “Shop Drawings”; specified in the second condition that the purchase order would be “pending architect approved submittals”; and requested in the sixth condition that submittals be forwarded at plaintiff’s first opportunity. Plaintiff thereafter requested a change to the language on the ground that the purchase order itself could not be made contingent on the architect’s approval of submittals because the parties would be under a binding agreement once plaintiff started shop drawings. In response, defendant issued the revised purchase order that retained the other conditions, but replaced the challenged language in the second condition with the requirement that “[a]ll work . . . comply with drawings and specifications.” Thus, on its face, the revised purchase order contemplated that plaintiff, as part of [1530]*1530its contractual obligations, would be required to forward submittals; however, it did not provide any definite or precise language regarding the nature of the submittal procedure or the requirements thereof.

Plaintiff contends that the only fair construction of the contract is that it merely required that plaintiff’s work product comply with the specifications, but did not require plaintiff’s compliance with the administrative procedures contained therein, i.e., formal architect approval. We conclude, however, that the contract terms are ambiguous because there is a reasonable basis for a difference of opinion whether the revised purchase order, which required that plaintiff make submittals that included its shop drawings, also required that plaintiff comply with the requirements for obtaining architect approval of that work as set forth more fully in the specifications referenced in the second condition of the revised purchase order (see generally Greenfield, 98 NY2d at 570-571).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Greenfield v. Philles Records, Inc.
780 N.E.2d 166 (New York Court of Appeals, 2002)
Darby & Darby, P. C. v. VSI International, Inc.
739 N.E.2d 744 (New York Court of Appeals, 2000)
Chianis & Anderson Architects, PLLC v. Courterback Development Company, LLC
140 A.D.3d 1286 (Appellate Division of the Supreme Court of New York, 2016)
SCHWERZMANN & WISE, P.C. v. TOWN OF HOUNSFIELD
126 A.D.3d 1483 (Appellate Division of the Supreme Court of New York, 2015)
HAYWARD BAKER, INC. v. C.O. FALTER CONSTRUCTION CORP.
104 A.D.3d 1253 (Appellate Division of the Supreme Court of New York, 2013)
South Road Associates, LLC v. International Business Machines Corp.
826 N.E.2d 806 (New York Court of Appeals, 2005)
Interman Industrial Products, Ltd. v. R. S. M. Electron Power, Inc.
332 N.E.2d 859 (New York Court of Appeals, 1975)
Zuckerman v. City of New York
404 N.E.2d 718 (New York Court of Appeals, 1980)
Esposito v. Wright
28 A.D.3d 1142 (Appellate Division of the Supreme Court of New York, 2006)
Kibler v. Gillard Construction, Inc.
53 A.D.3d 1040 (Appellate Division of the Supreme Court of New York, 2008)
Seneca Pipe & Paving Co. v. South Seneca Central School District
83 A.D.3d 1540 (Appellate Division of the Supreme Court of New York, 2011)
McFadyen Consulting Group, Inc. v. Puritan's Pride, Inc.
87 A.D.3d 620 (Appellate Division of the Supreme Court of New York, 2011)
Andrews, Pusateri, Brandt, Shoemaker & Roberson, P.C. v. County of Niagara
91 A.D.3d 1287 (Appellate Division of the Supreme Court of New York, 2012)
Schenectady Air Systems, Inc. v. Campito Plumbing & Heating, Inc.
84 A.D.2d 863 (Appellate Division of the Supreme Court of New York, 1981)
Engineered Air, Division of Thermal Components, Inc. v. LeCesse Bros. Contracting, Inc.
149 A.D.2d 951 (Appellate Division of the Supreme Court of New York, 1989)
Micro-Link, LLC v. Town of Amherst
109 A.D.3d 1130 (Appellate Division of the Supreme Court of New York, 2013)
Construction & Marine Equipment Co. v. Thomas Crimmins Contracting Co.
195 A.D.2d 535 (Appellate Division of the Supreme Court of New York, 1993)
Hooper Handling, Inc. v. Jonmark Corp.
267 A.D.2d 1075 (Appellate Division of the Supreme Court of New York, 1999)
Bussanich v. 310 East 55th Street Tenants
282 A.D.2d 243 (Appellate Division of the Supreme Court of New York, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
148 A.D.3d 1527, 50 N.Y.S.3d 635, Counsel Stack Legal Research, https://law.counselstack.com/opinion/auburn-custom-millwork-inc-v-schmidt-schmidt-inc-nyappdiv-2017.