Sims v. Carpenter, Frazier & Co.

69 S.E. 794, 68 W. Va. 223, 1910 W. Va. LEXIS 112
CourtWest Virginia Supreme Court
DecidedNovember 22, 1910
StatusPublished
Cited by22 cases

This text of 69 S.E. 794 (Sims v. Carpenter, Frazier & Co.) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sims v. Carpenter, Frazier & Co., 69 S.E. 794, 68 W. Va. 223, 1910 W. Va. LEXIS 112 (W. Va. 1910).

Opinions

POEEENBARGER, JüDGE:

In the circuit court of Cabell county, J. E. Sims recovered a judgment, against Carpenter, Frazier & .Co., for $2,600.00, in an action of assumpsit, brought to recover money alleged to be due from the defendants, principal contractors with’the Chesapeake & Ohio Eailway Company, to the plaintiff, a sub-contractor. Assigning a number of errors, the defendants obtained a writ of error.

The evidence having disclosed that E. P. Sims, a brother of the plaintiff, had become interested in the contract after it was made, the defendants moved to dismiss the action on the1 ground of a variance or non-joinder of necessary parties. The theory of the motion is not clearly stated, but it is immaterial. The subject matter of the contract was grading on certain sections of new roadbed, constructed by the C. & O. Eailway Co., in making certain alterations in its line between St. Albans and Barboursville. This work consisted of both excavation and filling. The contract was taken in the name of J. E. Sims. After it had been obtained and the use of a steam shovel became necessary, E. P. Sims aided his brother in the purchase of one with the understanding that' he should have a share of the profits to arise from certain portions of the work. We think the motion to dismiss was properly overruled. In actions at' law, founded upon contracts, the only necessary parties plaintiff are those who have the legal title or right involved. Clarkson v. Doddridge, 14 Grat. 42, 44; Crawford v. McDaniel, 1 Rob. 448; 4 Min. Ins. Part I, p. 450; 15 Enc. Pl. and Pr. 484. There are some statutory exceptions to this rule, but this case does not fall within any of them. The interest of E. P. Sims arose out of a contract between him and T. E. Sims, not between him and the defendants. Direct interest in the subject matter always gives standing in equity, but the rule in actions at law is narrower. There, the interest must be legal and direct, not merely equitable or indirect, unless some statute confers the remedy at law.

The principal matters in controversy consist of two items, one of which amounts to $515.97. Had Sims completed the work he agreed to do, there would be no controversy about this. [226]*226Original liability for it on the part of the defendants is not denied. It is a part of a percentage of money, due Sims lor work actually done, which the defendants retained as a means of compelling him to complete his contract. It was held under a provision usually inserted in building contracts for the purpose. In June, 1907, the railway companjr, under its contract with the defendants, rightfully suspended the work covered by its contract with them. They notified Sims of the suspension and he stopped 'work and removed his tools, machinery and appliances to a place in the State of Illinois where he obtained work from other parties, leaving the work he had contracted to do for the defendants incomplete. On the resumption of construction work on the C. & 0. Railway, in June, 1908, the defendants, after having demanded of Sims completion of the unfinished work, did it themselves, at a cost, they say, largely in excess of the amount of money retained, after having allowed him his contract price per cubic yard. Sims claims the defendant released him from further performance of the contract, on the suspension, ordered in June, 1907, in view of the fact that the work remaining to be done was not of sufficient magnitude to justify his coming back with his machinery, appliances and men. On the contrary, J. C. Carpenter, the head of the defendant firm, says Sims was not released. Admitting certain conversations with him, relating to the unfinished work, he says the understanding was that his firm would complete it for Sims and on his account, in case he should prefer not to come hack. On this point, Carpenter says “I told Mr. Sims a few days before he left — he remarked about The work not being enough to come back there and finish it’, and I told him, that if it did not suit him to come back there and finish the 'work, that I would finish it for him.” He says Sims assented to this proposition. Sims’ statement is as follows: “The conversation was along the C. & O. main line track, and Mr. Carpenter asked me ‘what kind of a piece of work I had’, and I told him, He asked me ‘what the price was’, and I told him, and he told ‘probably it would be all right, I 'was moving a lot of loose, and solid rock.’ I told him, ‘yes, but it was the best I could do’, and he said, ‘well, I hope you will have good luck; you won’t have enough here to come back for; when we get ready to start up, we 'will finish what you have got here; there won’t [227]*227Le enough to come Lack for/ ” líe had previously said he regarded his contract completed when the defendants ordered him to stop work. The contract, under which the defendants were working, 'reserved to the railway company the right to suspend the work at any time. Both admit that the subcontract was verbal, but their testimony is in direct conflict as to whether the terms of the principal contract should apply between the principal contractor and the sub-contractor. For the defendant in error, it is insisted that this state of the evidence gives rise to a question, lying wholly within the province of the jury to decide. For the plaintiff in error, it is insisted that the facts, circumstances and conduct, bearing on the question, are such that a verdict contrary thereto cannot be permitted to stand. This is the legal question involved and it extends to the next item in controversy, namely, compensation for something over 8,000 cubic .yards which the plaintiff claims to have taken out of a certain cut made to change the course of Mud River, in addition to the yardage allowed him by the defendants and to the defendants by the railway company.

The estimated amount of earth to be taken out of the cut known as the “river change” was 35,000 or 36,000 cubic yards. The final estimate, made by the railway company’s engineer after the completion of that work, and ' based upon actual measurements, shows 30,575 cubic yards. The plaintiff claims he removed 39,152 cubic yards. This claim is based upon a survey and estimate, made more than two years, after the completion of the work and after the river had been turned through' the cut, by an engineer employed by him. The theory of the defendants is that, assuming the measurements and calculations made by this engineer to have shown the quantity claimed, a large portion of the excavation had been made by the river after the cessation of work by Sims. It is also denied that the measurements and calculations are founded upon correct data. Shipe, the engineer, testified that the depth of that cut on the north side, as he took it for the purposes of his calculation, ranged from 16 to 21 feet. The defendant claims the depth of the cut on that side, as originally made, ran from 12 feet at one point to nothing or practically nothing. It seems not to be controverted that this cut was made in a hillside along the line of the new' roadbed of the railroad, sloping from the south [228]*228towards the railroad, and that, at one end, a small ridge or point, having a slighter declivity than the balance of the hillside, ran to the railroad, at which point the cut on the north side was about 12 feet. This is the contour of the ground as shown by the railway company’s engineer and the testimony of J. C. Carpenter. Some of the men who worked for Sims testified on the subject and they either substantially admitted the facts, as stated by the railway engineer and Carpenter, or their lack of knowledge of the condition of the ground in its natural state.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hollen v. Linger
151 S.E.2d 330 (West Virginia Supreme Court, 1966)
Campbell v. Campbell
124 S.E.2d 345 (West Virginia Supreme Court, 1962)
Preston County Coke Co. v. Preston County Light & Power Co.
119 S.E.2d 420 (West Virginia Supreme Court, 1961)
Mulroy v. Co-Operative Transit Company
95 S.E.2d 63 (West Virginia Supreme Court, 1956)
Muldoon v. Kepner
91 S.E.2d 727 (West Virginia Supreme Court, 1956)
Rees Electric Co. v. Mullens Smokeless Coal Co.
89 S.E.2d 619 (West Virginia Supreme Court, 1955)
Toppins v. Oshel
89 S.E.2d 359 (West Virginia Supreme Court, 1955)
Ward v. Smith
86 S.E.2d 539 (West Virginia Supreme Court, 1955)
Hartley v. Crede
82 S.E.2d 672 (West Virginia Supreme Court, 1954)
Ritz v. Kingdon
79 S.E.2d 123 (West Virginia Supreme Court, 1953)
Kap-Tex, Inc. v. Romans
67 S.E.2d 847 (West Virginia Supreme Court, 1951)
Vinson v. Home Insurance Co.
16 S.E.2d 924 (West Virginia Supreme Court, 1941)
Watson v. Aetna Casualty & Surety Co.
148 S.E. 322 (West Virginia Supreme Court, 1929)
Vaughan Construction Co. v. Virginian Railway Co.
103 S.E. 293 (West Virginia Supreme Court, 1920)
Hurricane Milling Co. v. Steel & Payne Co.
99 S.E. 490 (West Virginia Supreme Court, 1919)
State v. Rice
98 S.E. 432 (West Virginia Supreme Court, 1919)
Kelley v. Aetna Insurance
84 S.E. 502 (West Virginia Supreme Court, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
69 S.E. 794, 68 W. Va. 223, 1910 W. Va. LEXIS 112, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sims-v-carpenter-frazier-co-wva-1910.