Signature Designs Group, LLC v. Wayne Ramko and Donna Ramko

CourtCourt of Appeals of Tennessee
DecidedJune 29, 2012
DocketM2011-01086-COA-R3-CV
StatusPublished

This text of Signature Designs Group, LLC v. Wayne Ramko and Donna Ramko (Signature Designs Group, LLC v. Wayne Ramko and Donna Ramko) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Signature Designs Group, LLC v. Wayne Ramko and Donna Ramko, (Tenn. Ct. App. 2012).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE December 15, 2011 Session

SIGNATURE DESIGNS GROUP, LLC v. WAYNE RAMKO AND DONNA RAMKO

An Appeal from the Chancery Court for Rutherford County No. 08-0582CV Robert E. Corlew, III, Chancellor

_________________________________

No. M2011-01086-COA-R3-CV - Filed June 29, 2012

This case involves an alleged breach of a construction contract. The plaintiff contractor entered into a fixed priced contract to build a custom home for the defendant homeowners. During the construction, the contractor told the homeowners that the project was under budget, and that they could apply the cushion in the budget toward upgrades. Many upgrades and additions outside the scope of the original contract were made. The project ended up over budget, and the homeowners refused to pay more than the fixed price of the contract. The contractor filed this lawsuit, alleging breach of contract. The homeowners counterclaimed for breach of contract, violation of the Tennessee Consumer Protection Act, and fraudulent and/or negligent misrepresentation. After a bench trial, the trial court awarded the contractor some of the upgrade costs and dismissed the homeowners’ counterclaims. The homeowners now appeal. We reverse the award for the cost of the upgrades and remand for specific findings as to each upgrade or addition. In all other respects, the trial court’s order is affirmed.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court is Affirmed in Part, Reversed in Part, and Remanded

H OLLY M. K IRBY, J., delivered the Opinion of the Court, in which A LAN E. H IGHERS, P.J., W.S., and J. S TEVEN S TAFFORD, J., joined.

G. Sumner R. Bouldin, Jr., Murfreesboro, Tennessee, for the Defendant/Appellants Wayne Ramko and Donna Ramko

Mary Beth Hagan, Murfreesboro, Tennessee, for the Plaintiff/Appellee Signature Designs Group, LLC OPINION

F ACTS AND P ROCEEDINGS B ELOW

Plaintiff/Appellee Signature Designs Group, LLC (“SDG”), is a residential home contractor. Defendant/Appellants Wayne Ramko and his wife, Donna Ramko (collectively, “the Ramkos”), approached SDG to have a custom home built. The Ramkos worked with SDG representative Kenneth Cheng (“Mr. Cheng”) to reach an agreement. He remained their primary contact while the home was being built.

On June 15, 2007,1 SDG and the Ramkos entered into a Custom Home Agreement (“Agreement”), a contract prepared by SDG, for SDG to build the Ramkos a home on a lot on Ridgebend Drive in Murfreesboro, Rutherford County, Tennessee.2 The Agreement provided that the home would be built for a fixed priced of $320,000, which would include a $34,000 builder’s service fee payable in three installments.3 The Agreement was a “fixed price” contract.4

SDG also provided the Ramkos a list that described the standard materials used by SDG in its homes. This list was incorporated by reference into the Agreement. The Agreement stated that any requests for changes or alterations to the residence (“change orders”) would be “set forth in writing and delivered to Builder.”

As the Ramkos’ home was being built, SDG made several additions to the project and upgraded some materials used in the project, either at the suggestion of Mr. Cheng or at the

1 The contract actually bears two dates. The June 15, 2007 date is the date on which the Ramkos agreed to hire SDG to build their home. On July 10, 2007, the lender’s alterations were made and the construction loan was closed. 2 The lot was purchased from a third party prior to the parties entering into the construction contract. 3 The contract initially had a total purchase price of $390,000, which included $70,000 for the purchase of the lot. At the lender’s request, this was crossed out and the fixed price of the contract was changed to $320,000, excluding the amount for the lot. 4 Generally, a construction contract is either a “fixed price” contract or a “cost plus” contract. In a “fixed price” contract, the contractor is entitled only to the “fixed price” provided in the contract so long as the materials used and tasks performed are within the scope of the Agreement. Thus, the contractor’s profit equals the “fixed price” minus the cost of construction. A “cost plus” contract, however, is based on a builder’s actual costs, and the amount paid by the owner is “a fixed fee or a percentage added to the actual cost incurred.” Forrest Constr. Co., LLC v. Laughlin, 337 S.W.3d 211, 221 (Tenn. Ct. App. 2009) (quoting Black's Law Dictionary Abridged (7th ed. 2000)).

-2- request of the Ramkos. Despite the contractual provision requiring all change orders to be in writing, these modifications were not reduced to writing. The circumstances surrounding these changes and the parties’ statements to each other about the changes are the subject of much dispute in this case. It is undisputed that, at the beginning of the project, Mr. Cheng told the Ramkos that the project had started out under budget, and that they had a “cushion” that they could apply toward upgrades. According to the Ramkos, Mr. Cheng encouraged upgrades throughout the project, assuring the Ramkos that they had a $20,000 cushion with which to work. The Ramkos claim that they repeatedly cautioned Mr. Cheng that the project needed to stay within the original budget, and that Mr. Cheng responded with assurances that the changes were within his budget and would not result in any extra expense to the Ramkos over the agreed-upon fixed price. The record shows that the Ramkos purchased many items for the home themselves and that they performed some of the work; they claim that they did this in order to make sure that they stayed within the budget. For example, Mr. Ramko purchased and laid tile in the house, and he purchased a foldout ironing board, installed it, and did the necessary electrical wiring. The Ramkos sought reimbursement from SDG for some of the materials they purchased themselves.

According to Mr. Cheng, however, the Ramkos requested substantial upgrades throughout the project, and they assured Mr. Cheng that they understood that they were responsible for all upgrades that were not contemplated in the original contract. Mr. Cheng identified at least eighteen upgrades requested by the Ramkos that were not contemplated in the $320,000 fixed-amount figure in the Agreement. Mr. Cheng conceded that some of the upgrades requested by the Ramkos were suggested by him, but he noted that the Ramkos were free to reject his suggestions.

Mr. Cheng and the Ramkos met periodically throughout the project, approximately every two weeks, to discuss the progress and planning of the construction. Mr. Cheng maintained an internal spreadsheet to keep track of the amounts paid for the different elements of the project. The spreadsheets included the estimated cost of each item; the actual cost of each item was added to the spreadsheets as purchases were made. At their periodic meetings, Mr. Cheng gave the Ramkos copies of the spreadsheets. On a September 2007 spreadsheet, entered into evidence, the total estimated cost to build the home added up to approximately $298,000, though this total amount did not appear on the spreadsheet. Notably, the $34,000 builder’s fee was not included in the estimated costs on the spreadsheet. Therefore, the total of the projected cost of the house on the spreadsheet plus the builder’s fee exceeded the Agreement’s fixed price of $320,000 by several thousand dollars.

In December 2007, as the project neared completion, Mr. Ramko noticed that the spreadsheet Mr. Cheng had furnished him did not include the builder’s fee as one of the estimated costs. Once Mr. Ramko added up the actual costs of the items listed on the spreadsheet and then

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Troy Mitchell v. Fayetteville Public Utilities
368 S.W.3d 442 (Tennessee Supreme Court, 2012)
Hughes v. Metropolitan Government of Nashville & Davidson County
340 S.W.3d 352 (Tennessee Supreme Court, 2011)
Forrest Construction Co. v. Laughlin
337 S.W.3d 211 (Court of Appeals of Tennessee, 2009)
Jones v. LeMoyne-Owen College
308 S.W.3d 894 (Court of Appeals of Tennessee, 2009)
Ingram v. Cendant Mobility Financial Corp.
215 S.W.3d 367 (Court of Appeals of Tennessee, 2006)
Mosley v. McCanless
207 S.W.3d 247 (Court of Appeals of Tennessee, 2006)
Holladay v. Speed
208 S.W.3d 408 (Court of Appeals of Tennessee, 2005)
Cracker Barrel Old Country Store, Inc. v. Epperson
284 S.W.3d 303 (Tennessee Supreme Court, 2009)
Staubach Retail Services-Southeast, LLC v. H.G. Hill Realty Co.
160 S.W.3d 521 (Tennessee Supreme Court, 2005)
Berryhill v. Rhodes
21 S.W.3d 188 (Tennessee Supreme Court, 2000)
Marcus v. Marcus
993 S.W.2d 596 (Tennessee Supreme Court, 1999)
Bisson v. Ward
628 A.2d 1256 (Supreme Court of Vermont, 1993)
Metropolitan Government of Nashville & Davidson County v. McKinney
852 S.W.2d 233 (Court of Appeals of Tennessee, 1992)
Doe v. HCA Health Services of Tennessee, Inc.
46 S.W.3d 191 (Tennessee Supreme Court, 2001)
Allen v. Neal
396 S.W.2d 344 (Tennessee Supreme Court, 1965)
Fayne v. Vincent
301 S.W.3d 162 (Tennessee Supreme Court, 2009)
Union Carbide Corp. v. Huddleston
854 S.W.2d 87 (Tennessee Supreme Court, 1993)
Cothron v. Scott
446 S.W.2d 533 (Court of Appeals of Tennessee, 1969)
Smith v. Scott Lewis Chevrolet, Inc.
843 S.W.2d 9 (Court of Appeals of Tennessee, 1992)
Moore Construction Co. v. Clarksville Department of Electricity
707 S.W.2d 1 (Court of Appeals of Tennessee, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
Signature Designs Group, LLC v. Wayne Ramko and Donna Ramko, Counsel Stack Legal Research, https://law.counselstack.com/opinion/signature-designs-group-llc-v-wayne-ramko-and-donn-tennctapp-2012.