Sigmon Coal Co. v. Tennessee Valley Authority

359 F. Supp. 2d 686, 2004 U.S. Dist. LEXIS 27702, 2004 WL 3222666
CourtDistrict Court, E.D. Tennessee
DecidedAugust 23, 2004
Docket3:00-cv-00095
StatusPublished
Cited by1 cases

This text of 359 F. Supp. 2d 686 (Sigmon Coal Co. v. Tennessee Valley Authority) is published on Counsel Stack Legal Research, covering District Court, E.D. Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sigmon Coal Co. v. Tennessee Valley Authority, 359 F. Supp. 2d 686, 2004 U.S. Dist. LEXIS 27702, 2004 WL 3222666 (E.D. Tenn. 2004).

Opinion

FINDINGS OF FACT AND CONCLUSIONS OF LAW

PHILLIPS, District Judge. *689 District Judge.

*687 This is an action for breach of a coal supply contract between Sigmon Coal Company, Inc. (Sigmon), and the Tennessee Valley Authority (TVA). The court tried this civil action without a jury commencing on September 2, 2003. Following the trial, the parties filed proposed findings of fact and conclusions of law. Having heard the testimony at trial, having reviewed the exhibits introduced into evidence, and having considered the parties’ proposed findings and conclusions, the following are the court’s findings of fact and conclusions of law pursuant to Federal Rule of Civil Procedure 52(a).

Findings of Fact

This action arises out of a 10-year coal supply contract between TVA and Sigmon. *688 The court’s jurisdiction is based upon the Contract Disputes Act of 1978(CDA), as amended, 41 U.S.C. § 601 et seq. In 1990, TVA issued a Request for Proposals seeking coal supply offers for various TVA fossil plants over periods ranging up to ten years. Sigmon employed Diversified Energy, Inc., (Diversified) as an agent to assist Sigmon in responding to the Request for Proposals and in contract administration. In November 1990, TVA issued an award letter for the purchase of coal from Sigmon for delivery to TVA’s Colbert Steam Plant beginning January 1, 1992.

Subsequent to the November award letter, TVA prepared contract documents in June 1991 and sent those documents for execution to Sigmon’s agent, Diversified. Diversified’s President, Randy Edgemon, executed the contract documents and returned them to TVA. Section 29 of the contract designates the award letter as one of the documents that constitutes the contract.

The November award letter was initially prepared by TVA’s James Bach. The letter was reviewed and edited by TVA’s Larry Mize, and was reviewed by attorney Lon Young in the TVA Office of the General Counsel. The November 1990 award letter stated:

The delivery term of this contract will be for ten (10) years. However, as provided under Section 2, Term, the contract can be reopened by either party ninety (90) days prior to the fifth anniversary date of the commencement of deliveries.

The 1990 Contract documents that followed the November award letter were also prepared by Mr. Bach for TVA. The 1990 Contract documents, on the other hand, contained a reopener provision different from that stated in the award letter:

Term. Deliveries shall begin on January 1, 1992, and shall continue for 10 year(s) unless terminated by agreement or as otherwise provided herein. Provided, however, this contract may be reopened by either party nine (9) months prior to the fifth year anniversary of the delivery commencement date for the purpose of renegotiating price and other terms and conditions, or solely for the purpose of terminating deliveries. The party desiring to exercise such reopener shall give the other party written notice at least ninety (90) days prior to the anniversary date. If the reopener provision has been exercised, this contract will terminate on the said anniversary date unless TVA and the Contractor have mutually agreed in writing six (6) months prior to the said anniversary date to continue this contract. Neither party shall be under any obligation or liability to extend this contract if either party desires to terminate deliveries in accordance herewith, (emphasis added.)

For reasons unrelated to the reopener provision, TVA terminated the Contract in 1992 and litigation ensued. That litigation was resolved by a 1994 settlement which resulted in the Contract being reinstated through the issuance of Contract Supplement 18. Supplement 18 modified the reo-pener provision by deleting the November 1990 award letter from the documents that became the 1994 Contract.

On September 29, 1998, TVA provided written notice to Sigmon that it was reopening the Contract. Sigmon responded that TVA’s notice was untimely because under the Contract, as modified by Supplement 18, notice to reopen had to be given ninety (90) days prior to the fourth anniversary. TVA took the position that notice was timely if given nine (9) months prior to the fifth anniversary. The parties negotiated in 1999 for the continuation of the Contract, but did not reach an agreement on a price. Sigmon’s lowest offer to *689 TVA was $27.60 per ton, which TVA rejected because it could purchase comparable coal for lower prices from other suppliers. TVA subsequently gave notice on August 13, 1999 that the 1994 Contract would terminate effective August 15, 1999.

By letter dated September 8, 1999, Sig-mon sought a decision from the TVA Contracting Officer (CO) that TVA had breached the Contract by not providing proper notice of reopener and by not negotiating in good faith to continue the Contract. On December 10, 1999, the CO denied Sigmon’s request for relief. The instant litigation commenced in February 2000 and was assigned to the Honorable Leon Jordan, United States District Judge.

In a memorandum opinion entered July 16, 2001, Judge Jordan found that the written contract prepared by TVA, as amended by Supplement 18 and subsequent supplements “is the contract between the parties.” As amended by Supplement 18, the Contract no longer included the November 1990 award letter and instead contained the reopener provision quoted above, that the

contract may be reopened by either party nine (9) months prior to the fifth year anniversary of the delivery commencement date for the purpose of renegotiating price and other terms and conditions, or solely for the purpose of terminating deliveries. The party desiring to exercise such reopener shall give the other party written notice at least ninety (90) days prior to the anniversary date, (emphasis added.)

The sentence emphasized in bold is at the center of the current dispute between the parties.

The reopener provision in the 1994 Contract carried forward language from the original 1990 Contract. The period of time to give notice of a desire to reopen, the reopener date, and the negotiation period all remained the same as in the 1990 Contract. Supplement 18 specifically deleted from the 1990 Contract the November 1990 award letter which stated that the Contract could be reopened ninety (90) days before the fifth anniversary, (emphasis added.)

With the deletion of the award letter from the Contract, Sigmon understood the reopener provision to set forth a two-step procedure. First, the notice of desire to reopen the 1994 Contract was required to be given 90 days before the fourth anniversary of the Contract. Then, the Contract would actually be reopened and negotiation would begin nine months before the fifth anniversary.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Acosta v. Allen
W.D. Kentucky, 2022

Cite This Page — Counsel Stack

Bluebook (online)
359 F. Supp. 2d 686, 2004 U.S. Dist. LEXIS 27702, 2004 WL 3222666, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sigmon-coal-co-v-tennessee-valley-authority-tned-2004.