Sierra Club v. Van Antwerp

661 F.3d 1147, 398 U.S. App. D.C. 233, 2011 WL 5924561
CourtCourt of Appeals for the D.C. Circuit
DecidedNovember 29, 2011
Docket10-5284, 10-5297, 10-5345
StatusPublished
Cited by34 cases

This text of 661 F.3d 1147 (Sierra Club v. Van Antwerp) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sierra Club v. Van Antwerp, 661 F.3d 1147, 398 U.S. App. D.C. 233, 2011 WL 5924561 (D.C. Cir. 2011).

Opinion

Opinion for the Court filed by Senior Circuit Judge WILLIAMS.

WILLIAMS, Senior Circuit Judge:

In 2007 the U.S. Army Corps of Engineers issued a permit authorizing the discharge of dredge and fill material into specified wetlands outside Tampa, Florida; it thereby enabled construction of a large mall. A number of firms are involved on the permittee’s side in these appeals, but we will simplify by referring to them all, as well as the project, as “CCTC,” standing for “Cypress Creek Town Center.” Three environmental groups (collectively referred to as the “Sierra Club”) brought suit in district court to challenge issuance of the permit. (The suit names the heads of the Department of the Interior and the U.S. Fish and Wildlife Service as well, but we treat the Corps as a stand-in for all federal *1150 defendants.) Plaintiffs invoked three statutes: the National Environmental Policy Act (“NEPA”), the Clean Water Act (“CWA”), and the Endangered Species Act (“ESA”). After some complications described below, the district court issued a decision finding that the Corps had not fully complied with its obligations under NEPA and the CWA, but rejecting the plaintiffs’ ESA claim. It granted summary judgment for the Sierra Club on the first two claims and for the Corps on the third. Sierra Club v. Van Antwerp, 719 F.Supp.2d 58 (D.D.C.2010).

CCTC and the Corps appealed, and the Sierra Club cross-appealed. We affirm in part, reverse in part, and remand, concluding that the Corps did satisfy the demands of the three relevant statutes, except for failing to respond, in its treatment of the NEPA and ESA requirements, to a material contention as to the project’s impact on an endangered species, the eastern indigo snake.

Because CCTC proposed to discharge dredge and fill material into wetlands classified as “waters of the United States,” it was required to secure a permit from the Corps under § 404 of the CWA, 33 U.S.C. §§ 1311(a), 1362(7). The Corps originally issued the permit in 2007, allowing CCTC to discharge such material into about 54 acres of wetlands. In exchange, the Corps required various conservation measures, including the preservation, creation, or enhancement of wetlands on about 13 acres of the project site and nearly 120 acres offsite. The Sierra Club filed suit in October 2007, but soon thereafter the Corps observed two unauthorized discharges of “sediments and turbid water” from the project site into nearby Cypress Creek, and accordingly suspended the permit. The district court granted the Corps’s request to remand the case to it for a reevaluation of the permit. After issuing a new public notice, the Corps determined that the discharges were the product of “human error” rather than a flaw with the project itself. It reinstated the permit in September 2009, but required additional “corrective measures.” The Sierra Club filed a revised complaint challenging the new permit. The district court granted split summary judgments as noted above.

As we review grants of summary judgment de novo, we are on this appeal in reality reviewing the decision of the Corps, not that of the district court. Natural Resources Defense Council v. Daley, 209 F.3d 747, 752 (D.C.Cir.2000). Our review is governed by the usual standards of 5 U.S.C. § 706(2)(A) and Motor Vehicle Mfrs. Ass’n v. State Farm, 463 U.S. 29, 103 S.Ct. 2856, 77 L.Ed.2d 443 (1983).

* * *

CWA. The governing regulations bar the Corps from granting a CWA fill permit when “[tjhere is a practicable alternative to the proposed discharge that would have less adverse effect on the aquatic ecosystem.” 40 C.F.R. § 230.12(a)(3)®. They specify that “[a]n alternative is practicable if it is available and capable of being done after taking into consideration cost, existing technology, and logistics in light of overall project purposes.” 40 C.F.R. § 230.10(a)(2). If (as here) a project’s purpose does not require proximity to water, “practicable alternatives that do not involve special aquatic sites [such as wetlands, see id. § 230.41] are presumed to be available.” Id. § 230.10(a)(3). The Sierra Club contended (and contends here) that in fact there were practicable alternatives' — other sites, or alternative ways of using the CCTC site — having less adverse effect. The Corps rejected these claims. Resolution of the practicability issue turns on four subissues: (1) use of the site’s fair market value as its cost, rather than *1151 CCTC’s (lower) out-of-pocket cost; (2) failure on the Corps’s part to update the fair market value in its second look at the permit (which took place after the onset of the global financial meltdown in 2008); (3) the Corps’s use of 8% as the minimum rate of return necessary for an alternative to be considered practicable; and (4) CCTC’s intention to provide more parking per 1000 square feet of retail space than is provided on average, locally and indeed nationally.

For any given minimum rate of return, assumption of a lower cost for the site (see J.A. 613-36, 1660) will tend to render “practicable” less intensive uses, i.e., uses inflicting less ecological damage. This fact drives the Sierra Club’s argument for acquisition cost, which in this case happened to be lower than fair market value. But the Sierra Club’s contention that the regulation required the Corps to use the developer’s acquisition cost is ill-founded.

First, as a matter of simple language, opportunity cost (the value the owner could realize by a current sale) is a well-recognized form of cost. This is obviously true in economics, and the practicability test, though certainly neither a cost-benefit test nor an efficiency test, nonetheless encompasses economic factors. And courts have recognized opportunity cost as a variant of “cost.” Thus, the Supreme Court, in upholding the Federal Communications Commission’s decision to set certain rates “on a forward-looking basis untied to [the providers’] investment,” cited opportunity cost by way of analogy. Verizon v. FCC, 535 U.S. 467, 475, 499 n. 17, 122 S.Ct. 1646, 152 L.Ed.2d 701 (2002); see also Natural Gas Clearinghouse v. FERC, 108 F.3d 397, 400 (D.C.Cir.1997). Second, the regulations’ evaluation of alternatives requires consideration of cost on both sides of the comparison, and the cost of an alternative project site would presumably be that site’s market value. The comparison would be meaningful only if the Corps used the same metric for all options. Third, 40 C.F.R. § 230

Free access — add to your briefcase to read the full text and ask questions with AI

Related

International Dark-Sky Association, Inc. v. FCC
106 F.4th 1206 (D.C. Circuit, 2024)
Wildearth Guardians v. Jewell
District of Columbia, 2019
WildEarth Guardians v. Zinke
368 F. Supp. 3d 41 (D.C. Circuit, 2019)
Fisheries Survival Fund v. Jewell
District of Columbia, 2018
Am. Rivers v. Fed. Energy Regulatory Comm'n
895 F.3d 32 (D.C. Circuit, 2018)
Nat'l Parks Conservation Ass'n v. Semonite
311 F. Supp. 3d 350 (D.C. Circuit, 2018)
Oceana, Inc. v. Pritzker
275 F. Supp. 3d 270 (District of Columbia, 2017)
Standing Rock Sioux Tribe v. United States Army Corps of Engineers
255 F. Supp. 3d 101 (District of Columbia, 2017)
Natural Resources Defense Council v. National Park Service
250 F. Supp. 3d 1260 (M.D. Florida, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
661 F.3d 1147, 398 U.S. App. D.C. 233, 2011 WL 5924561, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sierra-club-v-van-antwerp-cadc-2011.