Siemens Government Technologies, Inc.

CourtArmed Services Board of Contract Appeals
DecidedMay 24, 2022
DocketASBCA No. 62601, 62602
StatusPublished

This text of Siemens Government Technologies, Inc. (Siemens Government Technologies, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Siemens Government Technologies, Inc., (asbca 2022).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeals of - ) ) Siemens Government Technologies, Inc. ) ASBCA Nos. 62601, 62602 ) Under Contract No. DE-AM36-09GO29041 ) T.O. No. N39430-18-F-9924 )

APPEARANCES FOR THE APPELLANT: Andy Liu, Esq. Robert S. Nichols, Esq. Andrew J. Victor, Esq. Sam Van Kopp, Esq. Nichols Liu LLP Washington, DC

APPEARANCES FOR THE GOVERNMENT: Craig D. Jensen, Esq. Navy Chief Trial Attorney Robyn L. Hamady, Esq. Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE D’ALESSANDRIS ON THE GOVERNMENT’S MOTION TO DISMISS AND MOTION FOR SUMMARY JUDGMENT

Appellant, Siemens Government Technologies, Inc. (Siemens or SGT) entered into a master Indefinite Delivery Indefinite Quantity (IDIQ) Energy Savings Performance Contract with the Department of Energy (DOE). Pursuant to the master contract, government agencies can request that Siemens propose energy savings measures to the agency. Depending on the results of Siemens’ investigation, the agency can enter into a contract (task order) with Siemens where Siemens will perform energy upgrades and recoup its expenses based on a specified share of the energy savings realized by the agency. The government agency benefits from the program by obtaining energy upgrades without incurring the upfront costs.

In September 2014, the Navy (Navy or government) issued a request to Siemens to perform a preliminary assessment of certain facilities in Europe, Africa, and Southwest Asia. Due to the greater expense of performing the energy audits in foreign countries, Siemens requested assurances from the Navy that it would be compensated for the costs of its preliminary investigations. The Navy declined to provide any assurances, and reminded Siemens that the DOE master contract provided that the contractor would not be compensated for work performed in locations that were not subsequently covered by a task order. Siemens performed preliminary investigations in six locations in Bahrain, Djibouti, Greece, Italy (2 locations), and Spain. However, after sending its workers to Camp Lemonnier, Djibouti and Souda Bay, Greece, Siemens discovered that the Navy facilities had already initiated work on certain energy upgrades that made the upgrades contemplated by Siemens non-viable. The Navy ultimately entered into a task order for three of the remaining projects. Siemens filed a claim with the Navy for the costs it incurred at Camp Lemonnier and Souda Bay, asserting a breach of the duty of good faith and fair dealing, superior knowledge, and entitlement pursuant to quantum meruit. The Navy contracting officer denied Siemens’ claims, and Siemens appealed to the Board. For the reasons stated below, we deny Siemens’ appeals.

STATEMENT OF FACTS FOR PURPOSES OF THE MOTION

A. The DOE Master Contract

On October 11, 2007, the Department of Energy issued Contract DE-AM36- 09GO29041 (DOE master contract) to Siemens Government Services, Inc. now known as Siemens Government Technologies (R4, tab 1). The DOE master contract allows federal agencies, such as the Navy, to issue task orders for Energy Savings Performance Contract (ESPC) work whereby Energy Savings Contractors (ESCOs) propose and validate Energy Savings Measures (ESMs) (also referred to as Energy Conservation Measures (ECMs)), that, if accepted and included in an agency-issued task order, would reduce energy and operating costs (42 U.S.C. § 8287, et seq.; Federal Acquisition Regulation (FAR) § 2.101; FAR § 23.205; R4, tab 10 at GOV322). An energy savings performance contract allows a federal agency to obtain energy savings and facility improvements with no up-front capital costs; and, in return, the energy savings contractor is paid from the agency’s cost savings. See FAR § 23.205(b)(1).

The DOE master contract provides that a task order is “[t]he obligating document that provides the details and requirements for the order of an energy savings performance contract project, placed against an established master indefinite delivery/indefinite quantity contract” (R4, tab 10 at GOV398). Section C.11 “GOVERNMENT PROJECTS” provides in relevant part: “[t]he agency shall notify the contractor when agency projects are to be implemented that may impact the installation or operations of contractor-installed ECMs” (id. at GOV334).

Section H outlines the steps leading to a task order award: (1) agency contracting officer issues a Notice of Opportunity; (2) ESCO submits an Expression of Interest 1 (EOI); (3) ESCO submits a Preliminary Assessment (PA); (4) agency

1 An Expression of Interest is defined as “[a]n IDIQ contract holder’s written response to an agency Contracting Officer’s notification of a potential ESPC task order 2 contracting officer issues a Notice of Intent to Award (NOI or NOITA); (5) the agency contracting officer issues a Task Order Request For Proposals (TO RFP); (6) the ESCO submits an Investment Grade Audit (IGA); (7) the ESCO submits a Final Proposal Based on the IGA; and (8) award of Task Order (id. at GOV350-64).

The DOE master contract defines a “preliminary assessment” as a procedure that may include an energy cost savings evaluation as part of developing preliminary technical and price proposals before the agency issues a notice of intent to award a task order. “Although a PA may include a technical concept and price assessment, it is not a binding offer and does not include the text of a financing agreement” (id. at GOV397). Section H.4.1 of the DOE master contract states: “[t]he agency will not be liable for any costs associated with PA audits or preparation of the PA unless the project addressed by the PA later becomes a TO award” (id. at GOV354).

An Investment Grade Audit (IGA) is: “[a] procedure which may include, but is not limited to, a detailed analysis of the energy cost savings and energy unit savings potential, building conditions, energy consumption, and hours of use or occupancy for a facility, for the purposes of preparing final technical and price Proposals” (id. at GOV396). Section H.5 addresses IGA requirements. It states: “[f]ollowing issuance by the agency of the NOI, the selected contractor shall conduct an Investment Grade Audit (IGA) of facilities and energy systems at the project site to substantiate the contractor’s ability to achieve the estimated total cost savings . . . ” (id. at GOV357). Section H.6, “Requirements for Proposal and Proposal Review for Task Orders,” states at H.6.1. that “[t]he contractor shall submit a Proposal, consisting of technical and price components . . . for each task order . . .” (id. at GOV0357). Proposal is defined as “a written, binding offer from a contractor that includes technical and price Proposals and the text of any financing agreement (including a lease acquisition)” (id. at GOV397).

Section H.6.2 provides that “[p]roposals will be reviewed in accordance with the instructions set forth in the TO RFP. The agency will not be responsible for any costs incurred, such as Proposal preparation costs or the costs incurred in conducting the IGA, unless a TO is awarded or authorized by the agency CO” (id. at GOV358). Section H.6.3 provides that “Proposals” include Price and Technical proposals (id. at GOV358-62). The price proposal requires “supporting documents” including “project-level expenses” from project development through award of the task order (id. at GOV361). “Project development” is defined as including “all work activities that occur after the agency issues a notice of intent to award task order” including “direct costs associated with the development of an IGA” (id. at GOV397).

that expresses its interesting [sic] in pursuing an ESPC project” (R4, tab 10 at GOV394). 3 B. The Navy’s Request for Preliminary Assessment

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Pure Gold, Inc. v. Syntex (u.s.a.), Inc.
739 F.2d 624 (Federal Circuit, 1984)
The United States v. Amdahl Corporation
786 F.2d 387 (Federal Circuit, 1986)
Mingus Constructors, Inc. v. The United States
812 F.2d 1387 (Federal Circuit, 1987)
Prineville Sawmill Company, Inc. v. The United States
859 F.2d 905 (Federal Circuit, 1988)
C. Sanchez and Son, Incorporated v. United States
6 F.3d 1539 (Federal Circuit, 1993)
Trauma Service Group v. United States
104 F.3d 1321 (Federal Circuit, 1997)
Scott Timber Co. v. United States
692 F.3d 1365 (Federal Circuit, 2012)
bell/heery v. United States
739 F.3d 1324 (Federal Circuit, 2014)
Dobyns v. United States
915 F.3d 733 (Federal Circuit, 2019)
Safeguard Base Operations, LLC v. United States
989 F.3d 1326 (Federal Circuit, 2021)
American Ship Building Co. v. United States
654 F.2d 75 (Court of Claims, 1981)
Tug Hill Construction, Inc. v. McHugh
622 F. App'x 914 (Federal Circuit, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
Siemens Government Technologies, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/siemens-government-technologies-inc-asbca-2022.