Shrewsbury Plumbing v. Pasch, T.

Superior Court of Pennsylvania·Decided September 11, 2026·No. 1629 MDA 2025·Unpublished·Kunselman

Opinion

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT O.P. 65.37

STANLEY HILL TRADING AS : IN THE SUPERIOR COURT OF SHREWSBURY PLUMBING AND : PENNSYLVANIA HEATING :

:

v. :

:

THE PASCH COMPANIES, INC., AND :

PADDOCK 55, LP :

:

Appellants : No. 1629 MDA 2025

Appeal from the Judgment Entered November 14, 2025 In the Court of Common Pleas of York County Civil Division at No(s):

2023-SU-001510

BEFORE: KUNSELMAN, J., LANE, J., and FORD ELLIOTT, P.J.E.* MEMORANDUM BY KUNSELMAN, J.: FILED: SEPTEMBER 11, 2026 After a bench trial in this breach-of-contract action, the Defendants, the Pasch Companies, Inc. and Paddock 55, LP (collectively, “the Builders”), appeal from the $224,514.65 judgment entered in favor of Stanley Hill. The evidence shows that Mr. Hill established an enforceable oral agreement. The trial court properly rejected the Builders’ affirmative defense that additional contractual provisions excused their obligation to pay. It also properly applied the Contractor and Subcontractor Payment Act. Accordingly, we affirm.

Timothy Pasch owned and operated the Builders, which constructed and sold homes in The Paddock at Equine Meadows development in York County. The Builders managed all phases of construction; issued purchase orders and

* Retired Senior Judge assigned to the Superior Court.

checks; and employed the project manager, Michael Gordon, who scheduled, oversaw, and directed subcontractor work.

Around 2017, Mr. Hill gave Mr. Gordon a quote to perform the underground, rough-in, and finish plumbing for houses in the development, which the Builders accepted. See N.T., 6/30/2025, at 14, 17. The parties agreed on a base rate for houses with basements and a separate rate for houses built on slabs. See id. at 41.

Over the next five years, Mr. Hill performed plumbing work on 76 of the Builders’ houses at the development. The Builders paid Mr. Hill for the first 57 homes without dispute.

The ordinary practice of the parties was that as each home was constructed and plumbing work was needed, Kalene O’Connell, the Builders’ office administrator, would prepare a written purchase order outlining the scope of the plumbing for that home. The purchase orders included the expected final cost to the Builders, based on the agreed-upon set rates for the two types of houses. Project Manager Gordon oversaw all the work at the development and directed Mr. Hill on when and where to begin work on each house as the properties were developed. See id. at 71, 154-55, 179. Mr. Hill then obtained the necessary permits for each home, mobilized his workers, and proceeded to plumb each property through final inspection.

As development neared completion and timelines and deadlines grew more pressing, Mr. Gordon directed Mr. Hill to begin work on homes even though purchase orders were still pending and had not yet been issued. See

id. at 23-24, 156-57; See also N.T., 7/1/2025, at 231. Mr. Hill never began plumbing work on a house without direction from someone acting for the Builders. See N.T., 6/30/2025 at 156-57. According to Keith Lutz, York Township’s Code Enforcement Officer, Mr. Hill pulled the permits for the at- issue houses in his business’ name, performed the work, and satisfied inspection requirements for each house. No other plumbers sought new permits to finish or redo any of Mr. Hill’s work, and the township issued no such replacement permits. See id. at 28-32. The Builders ultimately sold the completed homes to homebuyers. See id. at 50.

Of the 20 at-issue invoices, only three properties lacked corresponding purchase orders.1 The remaining at-issue invoices billed the Builders for amounts higher than the pre-work purchase orders indicated. These price discrepancies arose because some homes required more than the standard 50 feet of copper included in the preliminary figure, some sewer mains unexpectedly required special fittings to reduce six-inch lines to four inches, and some homebuyers requested upgrades. See id. at 58, 68, 188. In those instances, the Builders approved the additional charges. See id. at 58-59, 80, 99-100, 123-24.

Mr. Hill submitted the invoices promptly after completing the work. See id. at 141; see also N.T., 7/1/2025, at 230-231. In the months that followed,

1 16 homes had purchase orders, three did not. One additional at-issue invoice

was for extra work performed and not for the full scope of plumbing on a house. That invoice also did not have a corresponding purchase order.

Mr. Hill repeatedly sought payment and sent and resent unpaid invoices. During this period, the Builders did not inform Mr. Hill that they withheld payment because of a lack of a corresponding purchase order, discrepancies between invoice and purchase order amounts, or billing delays. See N.T., 6/30/2025, at 51-52, 55. Because the Builders ignored the invoices, Mr. Hill initiated this suit.

Mr. Hill alleged that the parties’ oral agreement set the base rate for the two types of houses, required him to obtain permits and provide materials and plumbing work on houses as directed by the Builders, and required the Builders to pay for satisfactory work performed. Mr. Hill further alleged that the Builders improperly withheld $132,440.43 for 20 invoices covering 19 houses and one invoice for extra work at The Paddock at Equine Meadows. Additionally, Hill alleged that Mr. Pasch orally contracted with Mr. Hill to perform plumbing work on Mr. Pasch’s private residence and that Mr. Pasch withheld $3,341.15 owed for that work.

In addition to breach-of-contract damages, Mr. Hill’s suit sought interest, damages, and fees under the Contractor and Subcontractor Payment Act (“CASPA”), 73 P.S. § 501 et seq.

In their answer and new matter, the Builders asserted an affirmative defense that their obligation to pay Mr. Hill was excused because the oral contract for plumbing work also contained three additional terms governing their obligation to pay: 1) no payment would be owed for any work completed on a house without a signed purchase order before the work commenced; 2)

no payment would be owed for any work completed if Mr. Hill later submitted a final invoice that did not precisely match the amount on the signed purchase order for that house; and 3) no payment would be owed for any work completed if Mr. Hill failed to submit final invoices within a reasonable time after the work was completed.

The Builders asserted that Mr. Hill submitted three invoices for work on houses, and an additional invoice for extra work, without a corresponding purchase order, so they had no obligation to pay. The Builders also claimed that for several homes for which a purchase order was issued, the amount ultimately invoiced by Mr. Hill did not match the amount pre-approved on the purchase order, so they were not obligated to pay. Finally, the Builders asserted that many of Mr. Hill’s final invoices were not submitted within a reasonable time after the work concluded, so no payment was owed.

The trial court held a two-day bench trial. At the conclusion of the trial, the court ruled in Mr. Hill’s favor, awarding him $3,341.15 against Mr. Pasch individually for work performed on his private residence, and $224,514.65 against the Builders for the work at the Paddocks at Equine Meadows. The trial court calculated Mr. Hill’s damages against the Builders as follows: $132,440.43 as principal damages for payment owed on all 20 outstanding invoices; $34,434.40 for 1% monthly interest for 26 months under CASPA on those 20 invoices; $27,639.82 for CASPA damages, calculated as a 1% per

month penalty for 26 months only on 16 of the invoices for which a purchase order was issued; and $30,000 in attorney’s fees under CASPA.2 The Builders filed a post-trial motion for judgment notwithstanding the verdict (JNOV) or for a new trial. On October 14, 2025, the trial court denied post-trial relief. Judgment was entered on November 14, 2025, and this timely appeal followed.

Free access — add to your briefcase to read the full text and ask questions with AI

Shrewsbury Plumbing v. Pasch, T., (Pa. Ct. App. 2026).

Shrewsbury Plumbing v. Pasch, T. (Shrewsbury Plumbing v. Pasch, T.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Zimmerman v. Harrisburg Fudd I, L.P.
984 A.2d 497 (Superior Court of Pennsylvania, 2009)
Lewis v. Spitler
403 A.2d 994 (Superior Court of Pennsylvania, 1979)
John B. Conomos, Inc. v. Sun Co., Inc.
831 A.2d 696 (Superior Court of Pennsylvania, 2003)
Zavatchen v. RHF Holdings, Inc.
907 A.2d 607 (Superior Court of Pennsylvania, 2006)
Johnston the Florist, Inc. v. TEDCO Construction Corp.
657 A.2d 511 (Superior Court of Pennsylvania, 1995)
Prieto Corp. v. Gambone Construction Co.
100 A.3d 602 (Superior Court of Pennsylvania, 2014)
Haan, D. and P. v. Wells, J.
103 A.3d 60 (Superior Court of Pennsylvania, 2014)