Shoreham Developers, Inc. v. Randolph Hills, Inc.

305 A.2d 465, 269 Md. 291, 1973 Md. LEXIS 825
CourtCourt of Appeals of Maryland
DecidedJune 7, 1973
Docket[No. 301, September Term, 1972.]
StatusPublished
Cited by17 cases

This text of 305 A.2d 465 (Shoreham Developers, Inc. v. Randolph Hills, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shoreham Developers, Inc. v. Randolph Hills, Inc., 305 A.2d 465, 269 Md. 291, 1973 Md. LEXIS 825 (Md. 1973).

Opinion

Digges, J.,

delivered the opinion of the Court.

Randolph Hills, Inc. (RHI), appellee, must be a firm believer in the old adage, “If at first you don’t succeed, try, try again.” For, despite having already suffered two defeats before this Court in closely allied litigation, it continues to wage war. Unfortunately, we must, once again remand the case for still another legal skirmish.

The appeal here represents the third visit to the Court of Appeals for this dispute 1 which started on June 22, 1962, *293 when RHI, by its president, Morris Perlmutter, entered into a contract with Shoreham Developers, Inc., appellant. On the same day, Perlmutter Bros., Inc. also entered into an agreement with Shoreham. The stock of both RHI and Perlmutter Bros., Inc. is owned by the Perlmutter family. 2 Under the terms of the RHI-Shoreham contract, appellant agreed to purchase a 32.61 acre parcel of land in Montgomery County for $351,000. By the latter contract Shoreham agreed to pay Perlmutter Bros., Inc. $162,000 to develop the raw acreage into 108 finished lots, with the understanding that the $162,000 would be reduced by $4,750 for each lot less than 108. 3

As is chronicled in our prior decisions related to this controversy, RHI experienced considerable delays in performing its contract and, after failing in an effort to persuade Shoreham to abandon the project, finally refused to settle under the sales agreement. This refusal prompted Shoreham’s first action — a suit for specific performance. But, the trial court dismissed the bill of complaint at the close of the complainant’s case. In Shoreham v. Randolph Hills, 248 Md. 267, 235 A. 2d 735 (1967), we concluded that a prima facie case had been established and, therefore, reversed the order of dismissal and remanded the case for further proceedings.

Following remand, a decree was entered against RHI in May 1968 directing it to specifically perform the sales agreement. In February 1969 appellee complied by conveying the 32.61 acre parcel to Shoreham. At settlement, pursuant to their agreement, appellant gave RHI a down *294 payment of $50,000 and, to evidence the balance of the purchase price, executed and delivered a deferred purchase money note secured by a first deed of trust. Additionally, as security for the payment of the $162,000 contract price that would be owed when the raw acreage was converted into finished lots, Shoreham executed and delivered a note in that amount secured by a second deed of trust on the property. But, the difficulties between RHI and Shoreham were far from over. In September 1969, when the work contemplated by the “finishing contract” had not been begun, Shoreham, and its president, Theodore N. Lerner, instituted a new equity action in the Circuit Court for Montgomery County. The bill of complaint in that suit, after being amended, contained seven “counts.” 4 As summarized by Judge Singley for the Court in Randolph Hills v. Shoreham, 266 Md. 182, 185-86, 292 A. 2d 662 (1972):

“The first Count sought a cancellation of the $162,000.00 note given by Shoreham to Perlmutter at the closing and of the deed of trust securing the note. Count II sought a cancellation of the deed of trust securing the $162,000.00 note on the theory that it constituted a cloud on title. Count III asked a reformation of the $162,000.00 note and of a note for $301,000.00 given RHI to the end that interest would not commence to run on either until 21 months after Perlmutter commenced to develop the 32.61 acre parcel as contemplated by the finishing contract. Count IV claimed damages for the breach of the Perlmutter contract. Count V sought the imposition of a constructive trust on $16,752.30 which RHI had received for a right of way for a sewer across part of the 32.61 acre tract subsequent to the 1962 contract but prior to the 1969 closing. Count VI sought to have Shoreham exonerated from any liability on a $30,000.00 road construction contract on which RHI allegedly obligated *295 Shoreham, without its knowledge or consent. Count VII sought to impose a constructive trust on $43,700.00, being part of an award of $50,000.00 as consequential or severance damages attributed to the tract of land not taken in condemnation, of which the 32.61 acres was a part, received by RHI after the execution of the contract but prior to closing.
Only Counts I, II, V and VII (the latter having been added by a later amendment) survived RHI’s demurrer. Summary judgment was entered for Shoreham on Counts I and II, because Perlmutter’s refusal to perform the finishing contract was not disputed, but was denied on Counts V and VII. RHI’s motion for summary judgment on all four Counts was denied. The order granting Shoreham’s motion for summary judgment directed that the case go to trial on Counts V and VII.
At trial on Counts V and VII, Shoreham offered no testimony, and the chancellor limited the evidence to be offered by RHI to the question of expenses incurred in connection with the payment received for the right of way and the recovery of severance damages, which RHI found it impossible to prove. As a consequence, a decree was entered, which provided in part for the payment by RHI to Shoreham of the $16,752.30 claimed in Count V and the $43,700.00 claimed in Count VII, with interest in each case, and costs.”

RHI appealed from the entry of that decree but to no avail as this Court affirmed it. All of this, however, is only important as background; what is really relevant to the present dispute is what happened to the claim for damages for breach of contract contained in Count IV after that count failed to survive RHI’s demurrer.

By Count IV of its bill of complaint, Shoreham sought to obtain $250,000 in damages, claiming that this amount represented the additional sum appellant will now be forced *296 to expend in order to obtain the same work it contracted in 1962 with RHI to perform for $162,000. Appellee demurred to this count claiming in pertinent part that:

“Count IV is further defective in that this is an action for a breach of contract for which there is an adequate remedy at law, this being a suit for money damages. Defendants would be greatly prejudiced if this action were allowed to remain in equity as said Defendants would then be denied a right to jury trial.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

NCO Financial Systems, Inc. v. Montgomery Park, LLC
842 F.3d 816 (Fourth Circuit, 2016)
Walter v. Atlantic Builders Group, Inc.
951 A.2d 94 (Court of Special Appeals of Maryland, 2008)
North American Specialty Insurance v. Boston Medical Group
906 A.2d 1042 (Court of Special Appeals of Maryland, 2006)
Hogue v. Sam's Club
114 F. Supp. 2d 389 (D. Maryland, 2000)
Shallow Run Ltd. Partnership v. State Highway Administration
686 A.2d 1113 (Court of Special Appeals of Maryland, 1996)
Rowland v. Harrison
577 A.2d 51 (Court of Appeals of Maryland, 1990)
Yesteryears, Inc. v. Waldorf Restaurant, Inc.
730 F. Supp. 1341 (D. Maryland, 1989)
Cassidy v. Board of Education
557 A.2d 227 (Court of Appeals of Maryland, 1989)
Preissman v. Mayor of Baltimore
497 A.2d 826 (Court of Special Appeals of Maryland, 1985)
Freestate Land Corp. v. Bostetter
440 A.2d 380 (Court of Appeals of Maryland, 1982)
Thrifty Diversified, Inc. v. Searles
429 A.2d 270 (Court of Special Appeals of Maryland, 1981)
Lewis v. Lewis
428 A.2d 454 (Court of Appeals of Maryland, 1981)
Surratts Associates v. Prince George's County
408 A.2d 1323 (Court of Appeals of Maryland, 1979)
Annapolis Urban Renewal Authority v. Interlink, Inc.
405 A.2d 313 (Court of Special Appeals of Maryland, 1979)
Washington Homes, Inc. v. Interstate Land Development Co.
382 A.2d 555 (Court of Appeals of Maryland, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
305 A.2d 465, 269 Md. 291, 1973 Md. LEXIS 825, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shoreham-developers-inc-v-randolph-hills-inc-md-1973.