Shin-Con Development Corp. v. L.P. Investments, Ltd.

270 S.W.3d 759, 2008 Tex. App. LEXIS 8768, 2008 WL 4966795
CourtCourt of Appeals of Texas
DecidedNovember 24, 2008
Docket05-07-01108-CV
StatusPublished
Cited by19 cases

This text of 270 S.W.3d 759 (Shin-Con Development Corp. v. L.P. Investments, Ltd.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shin-Con Development Corp. v. L.P. Investments, Ltd., 270 S.W.3d 759, 2008 Tex. App. LEXIS 8768, 2008 WL 4966795 (Tex. Ct. App. 2008).

Opinion

OPINION

Opinion by Justice MORRIS.

This is an appeal of a breach of contract case tried before a jury. The trial court rendered judgment in accordance with the jury’s verdict and awarded “liquidated damages” plus attorney’s fees and costs to I.P. Investments, Ltd. In twelve issues, Shin-Con Development Corporation and Hwan Soo Lee challenge the enforceability of the underlying contract, the damages award, the jury charge, the legal and fac *763 tual sufficiency of the evidence, the exclusion of their expert witness testimony, and the award of attorney’s fees. For the reasons that follow, we conclude the trial court erred in calculating damages, but we find no merit in appellants’ remaining issues. Accordingly, we reverse the part the trial court’s judgment awarding I.P. Investments, Ltd. “liquidated damages” in the amount of $883,179.42 and render judgment in favor of I.P. Investments, Ltd. and against Shin-Con Development Corporation and Hwan Soo Lee for $576,275 in accordance with this opinion. We affirm the trial court’s judgment in all other respects.

I.

At trial, the following facts were undisputed. Appellants and appellee own adjacent commercial property tracts, each of which contains a shopping center and parking lot. 1 The parties discussed exchanging easements to facilitate the traffic between the two properties. Appellants’ tract, however, was encumbered by a vendor’s lien, and the lienholders would not readily consent to the granting of an easement.

In November 1993, appellants and ap-pellee signed a 30-month license agreement permitting vehicular and pedestrian access between their tracts along a shared boundary. 2 The license agreement granted each party the right to drive vehicles across, walk across, and traverse across the parking and driveway areas of each other’s tract. Additionally, appellee agreed to pay appellants $50,000, and appellants agreed to remove a fence that was obstructing access between the shopping centers and to construct a driveway connecting the tracts. There were additional provisions with respect to permitted and prohibited barriers along the boundary. The license agreement further states:

This license agreement is to set forth the terms and conditions agreed upon for the repairs and construction of improvements to the property, removal of certain impediments to the movement of vehicular and pedestrian traffic, for the execution of a mutual easement agreement, and for other cooperative and financial agreements among the parties.

Attached to the license agreement as “Exhibit C” was a document indicating that the license agreement was entered into “in contemplation of the Mutual Easement Agreement” and listing items forming the “basic contents of the Mutual Agreement to be effective in the future.” 3 Among other things, “Exhibit C” provided that appellee would pay appellants a total of $300,000 for the mutual easement agreement. It also confirmed that the $50,000 appellee paid appellants under the license agreement was the down payment for the *764 “Mutual Agreement” and that another $100,000 would be paid to appellants once they obtained the lienholders’ signatures “verifying their agreement” and after the “Permanent Agreement” was entered into by the parties. It further provided that sixty days after the $100,000 payment, an additional $150,000 would be paid at ten percent per annum for ten years. 4

In December 1993, appellee gave appellants $30,000, and appellants executed a promissory note providing, among other things, that in the event of a default, the parties’ license agreement would be extended an additional forty months. In 1995, appellee gave appellants another $105,000, and the parties executed an addendum to their 1993 license agreement. The 1995 addendum provided that if appellants failed to obtain title to their property and execute a “permanent easement agreement” to appellee by January 31, 2003, they would forfeit the $185,000 they had received from appellees and pay eighteen percent annual interest on the unpaid balance from the date the addendum was signed. The addendum further provided that the license agreement “shall be extended to August 31, 2015.” On the same day the addendum was signed, appellants also executed an unsecured promissory note to appellee for $185,000 to be repaid on demand no later than February 5, 2003. 5 The note provided an annual percentage rate of eighteen percent per an-num on the unpaid principal from the date of the note and an annual interest rate on the “matured, unpaid amounts” of eighteen percent per annum. Appellants received a release of vendor’s lien from their lienhold-ers in 1998. Appellants did not, however, execute a “permanent easement agreement” by the January 31, 2003 deadline. Nor did they return to appellee the $185,000 plus interest.

Appellee filed this suit seeking, among other things, $185,000 plus accrued interest and attorney’s fees. Appellants filed a counterclaim asserting claims of breach of contract, fraud, quantum meruit, and unjust enrichment. The matter proceeded to trial. Appellee argued appellants owed it $185,000 plus interest because they failed to execute a permanent easement for ap-pellee’s benefit by January 31, 2003. Appellants, on the other hand, contended that because the addendum merely set a deadline for the parties to reach and finalize a future mutual permanent easement agreement, it was merely an agreement to agree and appellee was entitled to nothing on its claims. 6

Pursuant to special questions, the jury found that the parties had agreed that a permanent easement was to be created, appellants failed to comply with the agreement, and appellee did not fail to comply with the agreement. The issue of dam *765 ages was not presented to the jury. The trial court rendered judgment in accordance with the jury’s liability verdict and awarded appellee $883,179.42 in “liquidated damages,” $7,325.58 in court costs, and $135,000 in attorney’s fees. This appeal followed.

II.

In their first issue, appellants contend there is no enforceable contract between the parties because the alleged agreement lacks certain essential terms and is merely an agreement to agree in the future. Appellants also assert the parties’ agreement is not enforceable because it violates the statute of frauds.

Whether an alleged agreement constitutes an enforceable contract is generally a question of law. Searcy v. DDA, Inc., 201 S.W.3d 319, 322 (Tex.App.-Dallas 2006, no pet). To be legally enforceable, an agreement must be sufficiently definite to allow a court to understand what the promisor undertook. See T.O. Stanley Boot Co., Inc. v. Bank of El Paso, 847 S.W.2d 218, 221 (Tex.1992).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Quintero v. Urban Infraconstruction
2026 Tex. Bus. 3 (Texas Business Court, 2026)
Pat Stevens and Cheryl Stevens v. Jon Avent
Court of Appeals of Texas, 2022
Marrs & Smith Partnership v. Sombrero Oil & Gas Co.
511 S.W.3d 53 (Court of Appeals of Texas, 2014)
Clouse v. Levin
339 S.W.3d 766 (Court of Appeals of Texas, 2011)
Cate v. Woods
299 S.W.3d 149 (Court of Appeals of Texas, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
270 S.W.3d 759, 2008 Tex. App. LEXIS 8768, 2008 WL 4966795, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shin-con-development-corp-v-lp-investments-ltd-texapp-2008.