Pat Stevens and Cheryl Stevens v. Jon Avent

Court of Appeals of Texas·Decided February 9, 2022·No. 07-20-00265-CV·Published

Opinion

In The

Court of Appeals

Seventh District of Texas at Amarillo

No. 07-20-00265-CV

PAT STEVENS AND CHERYL STEVENS, APPELLANTS V.

JOHN AVENT, APPELLEE

On Appeal from the 72nd District Court Lubbock County, Texas

Trial Court No. 2018-533,023; Honorable Ruben G. Reyes, Presiding

February 9, 2022

MEMORANDUM OPINION

Before QUINN, C.J., and PIRTLE and DOSS, JJ.

Following a bench trial in this breach of contract litigation, Appellants, Pat Stevens and Cheryl Stevens, appeal from the trial court’s judgment awarding Appellee, John Avent, $41,423.23 in economic damages and $15,275.00 in attorney’s fees in his suit for breach of contract. By their original brief, the Stevenses present three issues challenging the judgment. However, during oral submission of this appeal, counsel for the Stevenses

declared that issue two was being abandoned. By their first issue, the Stevenses challenge the legal sufficiency of the evidence to establish that Avent’s damages were reasonable and necessary due to lack of expert testimony and because no other evidence supported the award. By their third issue, they also assert the evidence is legally insufficient to establish that Avent timely “presented” his attorney’s fees claim. We affirm.

BACKGROUND On February 6, 2018, John Avent, a homeowner, entered into a contract with Pat and Cheryl Stevens for an outdoor remodeling project on a newly purchased home. The agreed-on price of the renovation was $45,000.00 with an estimated completion date of April 1, 2018. Avent paid a $15,000.00 deposit and the contract provided for two additional payments of $15,000.00.

Avent also had hired another contractor, Mike Larson, to renovate an indoor bathroom and bedroom. After a disagreement, Avent fired Larson. On February 27, the Stevenses offered to have the indoor renovations completed at cost and Avent accepted. The parties amended their original contract which increased the second payment from $15,000.00 to $27,000.00. Avent paid the Stevenses $27,000.00.

As of May 23, 2018, the estimated completion date had passed and Avent was “panicking” and waiting on a brick mason for the outdoor renovations. He suggested the name of an alternate brick mason to Pat Stevens, and he was subsequently hired. The brickwork was completed in mid-June. The Stevenses did not pay the subcontractor and the burden fell on Avent to pay him.

Regarding the interior renovation project, Avent testified the Stevenses fired a subcontractor in March due to poor workmanship but arranged for another subcontractor, David Guerrero, to complete the work. According to Avent, Guerrero’s work was also unsatisfactory. Guerrero had not properly installed a shower and had also damaged some marble tile. Avent was also concerned about a significant amount of glue that Guerrero had dropped on his living room floor. According to Pat Stevens, Avent fired Guerrero.

When the terms of the original contract were not fulfilled and some of the work was substandard, in July 2018, Avent terminated the contract with the Stevenses. To complete the renovations, Avent was forced to hire and pay his own contractors. He also had to pay two of the Stevenses’ unpaid subcontractors. Avent testified he hired Kevin Kouth with Smartscapes of Lubbock to complete the outdoor renovations at a cost of $13,772.00. 1 Avent also hired a contractor to complete the bathroom renovations at a cost of $8,580.00, two electricians at a cost of $2,038.02, and a tile and flooring business to repair and replace damaged floors at a cost of $8,933.21. 2 Avent also issued checks to two of the Stevenses’ unpaid subcontractors for $500.00 and $7,600.00. 3 He testified that he compensated the Stevenses’ unpaid subcontractors to avoid having a mechanic’s

1During his testimony, Avent was asked if the amount paid to Kouth was for “remedial work,” to which he answered affirmatively.

The amounts are supported by Avent’s testimony as well as invoices and canceled checks which 2

were admitted into evidence.

3 Avent notes in his brief that the $8,100 he paid to compensate unpaid subcontractors does not

reflect any remedial damages but was instead for services rendered to, but not paid for by the Stevenses. As such, he contends that portion of the damages award should not be disturbed on appeal. Our disposition renders his claim moot.

and materialmen’s lien filed against his property. He testified all of the amounts he spent were “attributed to what Mr. Stevens was supposed to finish.”

Once the project was complete, Avent sued the Stevenses for, among other claims, breach of contract. The Stevenses counterclaimed for breach of contract alleging that notwithstanding their substantial performance, Avent terminated the contracts before completion and failed to pay them the balance of the agreed-on amounts.

During trial, in addition to his own testimony, Avent presented Kouth as an expert witness to demonstrate the necessity of the repairs and reasonableness of the amounts paid. Kouth’s testimony was met with numerous objections and contradictory rulings by the trial court throughout the trial. The rulings relevant to Kouth’s testimony will be discussed in the analysis of the Stevenses’ issue on damages.

Kouth testified he had “13 years solid in the construction aspect of things” in outdoor kitchens and living spaces. At the time of trial, he was a general contractor with the City of Lubbock. He was familiar with preparing bids and estimates for projects and was also familiar with standards of workmanship and the reasonableness of costs and pricing in the Lubbock area.

According to Kouth, when he was hired by Avent, much of the outdoor renovation project was incomplete. When questioned on the reasonableness of the costs to finish the project, Kouth testified they were “very reasonable.” He also confirmed that the costs to “fix the Stevens [sic] problems” were necessary. Following Kouth’s direct examination, counsel for the Stevenses announced he had no questions for the witness.

Pat Stevens testified at trial and acknowledged that his original contract with Avent was for $45,000.00, with an estimated completion date of April 1, 2018. Regarding the $7,600.00 paid to the brick mason by Avent, Stevens testified that he never agreed to pay him because he was not one of his subcontractors. He also denied that Avent had asked him to pay the brick mason.

Stevens admitted that he was dissatisfied with the quality of the work performed on the shower by his subcontractors and he “shut it down.” He then hired Guerrero whom he said Avent was “very pleased with,” although Avent later complained about edges of the tile that “were raised a little bit.” According to Stevens, Avent fired Guerrero without his knowledge and retained another contractor to continue the indoor renovations. Stevens claimed he was not given an opportunity to remedy any alleged defects.

At the conclusion of all the testimony, the trial court asked for briefing on the issue of whether Kouth’s testimony as a fact witness only could support Avent’s claim for remedial damages. Subsequently, the trial court entered judgment in favor of Avent for $41,423.23 (the sum of Avent’s out-of-pocket expenses to which he testified to complete the contract).

After entry of the judgment, the Stevenses requested the trial court to enter Findings of Fact and Conclusions of Law. As relevant to this appeal, the trial court made the following finding:

9. The total reasonable and necessary cost of repairs to complete the project, remedy the defects in the Stevens [sic] workmanship, to compensate unpaid subcontractors, and to accomplish a satisfactory condition was $41,423.23. These damages are broken down into three categories as follows:

(1) The cost of repair and completion for the outdoor living space (recovery sought under [Avent’s] breach of contract and breach of implied warranty claims):

Alvin Holder Electric $723.02 Neill Electric $1,315.00 Smartscapes of Lubbock $13,772.00

Free access — add to your briefcase to read the full text and ask questions with AI

Pat Stevens and Cheryl Stevens v. Jon Avent, (Tex. Ct. App. 2022).

Pat Stevens and Cheryl Stevens v. Jon Avent (Pat Stevens and Cheryl Stevens v. Jon Avent) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Ford Motor Co. v. Ridgway
135 S.W.3d 598 (Texas Supreme Court, 2004)
Horizon/CMS Healthcare Corporation v. Auld
34 S.W.3d 887 (Texas Supreme Court, 2000)
Alan Reuber Chevrolet, Inc. v. Grady Chevrolet, Ltd.
287 S.W.3d 877 (Court of Appeals of Texas, 2009)
Dean Foods Co. v. Anderson
178 S.W.3d 449 (Court of Appeals of Texas, 2005)
Ron Craft Chevrolet, Inc. v. Davis
836 S.W.2d 672 (Court of Appeals of Texas, 1992)
Catalina v. Blasdel
881 S.W.2d 295 (Texas Supreme Court, 1994)
Penrod Drilling Corp. v. Williams
868 S.W.2d 294 (Texas Supreme Court, 1993)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Tull v. Tull
159 S.W.3d 758 (Court of Appeals of Texas, 2005)
Carrow v. Bayliner Marine Corp.
781 S.W.2d 691 (Court of Appeals of Texas, 1989)
WORTHAM BROS., INC. v. Haffner
347 S.W.3d 356 (Court of Appeals of Texas, 2011)
CCC Group, Inc. v. South Central Cement, Ltd.
450 S.W.3d 191 (Court of Appeals of Texas, 2014)
Jamie Genender and Critter Stuff, LLC v. USA Store Fixtures, LLC
451 S.W.3d 916 (Court of Appeals of Texas, 2014)
Greg Gibson and Christine Gibson v. Jose Fernando Cuellar
440 S.W.3d 150 (Court of Appeals of Texas, 2013)
Peter Pjetrovic v. Home Depot
411 S.W.3d 639 (Court of Appeals of Texas, 2013)
McGinty v. Hennen
372 S.W.3d 625 (Texas Supreme Court, 2012)
In re Nalle Plastics Family Ltd. Partnership
406 S.W.3d 168 (Texas Supreme Court, 2013)