Shiffer v. CBS Corp.

240 Cal. App. 4th 246, 192 Cal. Rptr. 3d 346, 2015 Cal. App. LEXIS 788
CourtCalifornia Court of Appeal
DecidedSeptember 8, 2015
DocketA139388
StatusPublished
Cited by32 cases

This text of 240 Cal. App. 4th 246 (Shiffer v. CBS Corp.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shiffer v. CBS Corp., 240 Cal. App. 4th 246, 192 Cal. Rptr. 3d 346, 2015 Cal. App. LEXIS 788 (Cal. Ct. App. 2015).

Opinion

Opinion

BANKE, J.

In this asbestos case, plaintiffs James Shiffer and his wife sued CBS Corporation, whose predecessor, Westinghouse, provided a turbine set and asbestos-containing insulation for a power plant where Shiffer worked for several months in 1969 and 1970. The trial court granted summary judgment to CBS. We affirm. Plaintiffs failed to produce evidence raising a triable issue that Shiffer suffered bystander exposure to Westinghouse asbestos while at the plant. The trial court also properly denied plaintiffs’ motions for reconsideration and a new trial, because evidence of potential harm from re-entrainment of asbestos was not new and could have been presented in opposition to the original summary judgment motion.

Background

Plaintiffs sued numerous entities that allegedly caused Shiffer to be exposed to asbestos, eventually resulting in his developing mesothelioma. As to defendant CBS, they alleged Shiffer was exposed to asbestos-containing materials at the Ginna power plant in Rochester, New York, in the summer of 1969. Shifter’s then employer, Pacific Gas & Electric, had sent him to Ginna in July of that year to train employees on the operation of Westinghouse equipment being installed in the plant.

Westinghouse had sold Ginna a turbine generator set and insulation, including blanket, block, and plastic insulation for the turbine and certain *249 related piping, namely crossover and cross-under piping. Westinghouse began shipping the equipment in July of 1968, a year before Shiffer arrived. Installation took place during 1968 and 1969. CBS’s person most knowledgeable for the case, Douglas Ware, conceded at his deposition that the blanket, block, and plastic insulation, including that used on crossover and cross-under piping, contained asbestos.

Reports, each labeled “Field Report, Westinghouse Form” and “Steam Service Department,” recorded progress on the installation. With respect to the insulation work, these reports stated the following: During the week of May 12, 1969, insulators were on strike and the high-pressure turbine cylinder and crossover pipes were not yet insulated. By the week of June 9, a team of insulators was back on the job. Insulators continued work on the high-pressure turbine cylinder and crossover pipes through the weeks of June 16, July 7, July 14, and July 21. But as of June 24 — before Shiffer arrived in July — -the turbine had been “hot functional” and the main, two-inch-thick layer of insulation would have been in place. During the week of July 21, work continued on the “insulation of H.R, Crossover and Crossunder piping, drains, and glands.” As the project entered the week of August 4, “insulators [were] near completion of insulation of the high-pressure and cross-over piping.” The final report in the record, for the week of August 11, suggests insulation was still incomplete, stating “due to job conditions, only two insulators are working on the Turbine contract.”

At his September 2012 deposition, Shiffer testified that when he arrived at Ginna in July of 1969, “all of the major components in the plant were installed” but “there was the last stages of construction going on.” His “recollection [was] that the turbine insulation specifically was already put on.” As he would “wander around the plant . . . there was a small amount of insulation. It would have been piping insulation. . . . But the main turbine insulation or steam line insulation was already installed.” He then reiterated “the turbine and its insulation were already installed.” And again: the generators/heat exchanges “were insulated prior to my arrival”; the “main steam lines were . . . already insulated,” though he saw “drains and smaller auxiliary lines” getting insulated. Although Shiffer observed these things while walking the plant, his workstation was in another building, separate from the turbine building.

Plaintiffs took Ware’s deposition six months later, on March 5, 2013, and Ware, as noted, conceded the presence of asbestos in the crossover and cross-under pipe insulation. There is nothing from Ware, however, about the nature of the insulation of any other kinds of pipes. Ware took no issue with the installation progress revealed in the previously produced Westinghouse progress reports.

*250 Shiffer then filed a declaration dated March 13, 2013 (nearly two weeks after Ware’s deposition), in opposition to CBS’s motion for summary judgment. In it, Shiffer was far less specific about his observations than he had been during his deposition six months earlier. Shiffer stated that when he arrived at Ginna in July 1969, “construction” was still in progress, including “insulators insulating piping in the turbine building.” He further declared he had to enter the turbine building almost every day to educate himself about the plant to better conduct his training work.

There is no dispute Shiffer did not repair or maintain any Westinghouse equipment, and did not install or remove any insulation material himself. Nor is there any dispute that no already installed insulation was removed or disturbed during Shiffer’s time at Ginna.

Plaintiffs’ expert, Charles Ay, declared the installation of piping insulation containing asbestos creates “large amounts of respirable asbestos dust as the material is cut, manipulated, and handled.” Ay further opined, based on his training, education and experience, the insulation work documented on the Westinghouse forms would have “created magnitudes of asbestos-containing dust throughout the work area.” The trial court excluded this latter statement on objection it was vague and speculative. Though Ay reviewed other discoveiy materials, he admittedly did not review Shiffer’s deposition testimony or his declaration.

Another of plaintiffs’ experts, Christopher Depasquale, considered Shiffer’s declaration in which Shiffer stated he had observed construction at Ginna, including the insulation of piping in the turbine building, and had spent time in this area while educating himself and conducting training. Assuming insulation work continued into August 1969, as documented by the Westinghouse work reports, Depasquale opined Shiffer was exposed to “hazardous” levels of respiratory asbestos as a bystander. The trial court excluded this opinion on objections that it lacked foundation. Though Depasquale reviewed Shiffer’s declaration, he did not review his deposition testimony.

Plaintiffs also submitted the declaration of Barry Horn, a medical doctor who had examined Shiffer. According to Horn, Shiffer’s “exposure from the continuing work on the turbines at the Ginna plant while he was present in the facility, including the asbestos-containing insulation on the Westinghouse equipment was a substantial contributing factor to the total aggregate dose of Mr. Shiffer’s asbestos exposure.” Horn further opined “[ejach and every exposure to asbestos experienced by a person with mesothelioma is a substantial contributing factor in the development of the disease.” Horn reviewed Shiffer’s summary judgment declaration, but like Depasquale and Ay, did not consider Shifter’s deposition testimony. The trial court did not rely upon and did not address the admissibility of Horn’s declaration.

*251 In its written order granting summary judgment to CBS, the trial court stated Shiffer “failed to submit evidence ...

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Scoggins v. ViacomCBS CA1/4
California Court of Appeal, 2025
Mitchell v. Hutchinson
California Court of Appeal, 2025
Mitchell v. Hutchinson CA4/3
California Court of Appeal, 2025
Easterling v. Henkels & McCoy CA2/6
California Court of Appeal, 2025
Hernandez v. Nunez CA4/2
California Court of Appeal, 2025
Hughes v. Farmers Insurance Exchange CA2/7
California Court of Appeal, 2024
Bui v. Ky
California Court of Appeal, 2024
Speck v. 3M Company
N.D. California, 2024
Simonyans v. Torbati CA2/2
California Court of Appeal, 2024
Fair v. WV 23 Jumpstart CA1/3
California Court of Appeal, 2024
Bird v. Great American Chicken Corp. CA2/2
California Court of Appeal, 2023
Ochoa v. SPX Cooling Technologies CA1/1
California Court of Appeal, 2023
People v. Lundberg CA4/2
California Court of Appeal, 2022
People v. Sandoval CA2/5
California Court of Appeal, 2022
Limpin v. San Diego Housing Commission CA4/1
California Court of Appeal, 2022
Sabetian v. Fluor Enterprises CA2/7
California Court of Appeal, 2021
Torres v. Design Group Facility Soultions, Inc.
California Court of Appeal, 2020
Bingener v. City of Los Angeles
California Court of Appeal, 2020
Berg v. Colgate-Palmolive Co.
California Court of Appeal, 2019

Cite This Page — Counsel Stack

Bluebook (online)
240 Cal. App. 4th 246, 192 Cal. Rptr. 3d 346, 2015 Cal. App. LEXIS 788, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shiffer-v-cbs-corp-calctapp-2015.