Shermco Industries, Inc. And Peter A. Sherman v. Secretary of the Air Force

613 F.2d 1314, 27 Cont. Cas. Fed. 80,280, 1980 U.S. App. LEXIS 19498
CourtCourt of Appeals for the Fifth Circuit
DecidedMarch 19, 1980
Docket78-2499
StatusPublished
Cited by21 cases

This text of 613 F.2d 1314 (Shermco Industries, Inc. And Peter A. Sherman v. Secretary of the Air Force) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shermco Industries, Inc. And Peter A. Sherman v. Secretary of the Air Force, 613 F.2d 1314, 27 Cont. Cas. Fed. 80,280, 1980 U.S. App. LEXIS 19498 (5th Cir. 1980).

Opinion

JOHN R. BROWN, Circuit Judge:

After its bid for a contract to overhaul airborne generators was rejected by the Air Force, Appellee Shermco Industries, Inc. (Shermco) filed a protest with the General Accounting Office (GAO) and requested from the Air Force the production of several documents in connection with this pro *1316 test. The Air Force produced all but seven of these documents and Shermeo sued for their disclosure under the Freedom of Information Act, 5 U.S.C. § 552 (1977) (FOIA). The District Court ordered the production of the documents, holding that the exemptions of 5 U.S.C. §§ 552(b)(4) and (5) were inapplicable. 1 We reverse.

I. Factual Background

In 1976, Shermeo had a five-year contract with the Air Force to overhaul airborne generators at McClellan Air Force Base near Sacramento, California. The Air Force terminated the contract in its third year, citing “quality problems,” and solicited offers from a number of contractors, including Shermeo, to continue the work. On October 14,1976, Shermeo was informed that Tayko Industries, Inc. (Tayko) was the lowest acceptable bidder and that Shermco’s bid was rejected. On October 22, 1976, Shermeo filed a protest with the GAO pursuant to 4 CFR Part 20 (1979). Shermeo and its president made several requests to the Air Force for information concerning Tayko’s bid to help Shermeo implement its protest. These requests included ones made under FOIA and the Privacy Act. 2 The Air Force produced twenty-four of the requested items but withheld seven others — three legal memoranda which had been attached to the Air Force’s response to the protest, the contracting officer’s recommendation prepared in connection with the protest, 3 and three documents containing Tayko’s basic pricing information, including “items, quantities and unit prices.” On November 10, 1977, Shermeo filed suit against the Secretary of the Air Force to obtain these documents, pursuant to FOIA and the Privacy Act.

The District Court held that FOIA required the disclosure of all seven documents requested. The Secretary appeals this holding and we reverse. 4

11. The Cost Proposals And Exemption 4

The Air Force’s basis for the withholding of Tayko’s cost proposals was Exemption 4 of FOIA, 5 U.S.C. § 552(b)(4), which provides that the Government is not required to disclose

trade secrets and commercial or financial information obtained from a person and privileged or confidential .

The Air Force argued that because there had not been a final award of the contract, this information should remain confidential until a final award was made. To disclose this information before a final decision was made would make it more difficult for the Air Force to make its final decision and would be prejudicial to the low bidder, undermining his competitive advantage.

*1317 The District Court conceded that the decision was not yet technically final (452 F.Supp. at 322) and that, if there were no final award, Exemption 4 would apply (id. at 324). However, the Court found that, for purposes of FOIA, the decision was final (id. at 322), and that “[a]ny need for secrecy [was] no longer present because the award [would] be made either to the successful bidder or the protester . . . .” Id. at 324. Therefore, the Court concluded, the cost proposals were no longer confidential nor exempt.

The purpose of Exemption 4 is twofold — to protect the interests of individuals who disclose confidential information to government agencies and to protect the Government as well. National Parks and Conservation Association v. Morton, 162 U.S.App.D.C. 223, 228, 498 F.2d 765, 770 (D.C. Cir. 1974). 5 This information concerning Tayko’s cost proposals, in the hands of a competitor prior to the time of a final .award, would jeopardize the Air Force’s ability to discern clearly which bidder could do the best job for the lowest price. Moreover, the nondisclosure of this information is in keeping with the Armed Services Procurement Regulations (ASPR) policy prohibiting bidding with knowledge of competing bids. 6 Nondisclosure prior to final award also encourages competing bidders to enter bids which accurately reflect their capabilities and their costs; this secrecy protects the bargaining power of each competitor’s bid. Absent the assurance of this confidentiality, bidders might be reluctant to disclose such information to the procuring government agency.

On appeal, the Air Force reasserts the same argument — that their selection of Tayko as the lowest acceptable bidder did not amount to a final award. To support this contention it cites GAO briefing papers stating that the effect of a GAO ruling in favor of a protestor in a pre-award protest is not necessarily that he will be awarded the contract. It may mean the contract bidding will be reopened to choose the next lowest responsible bidder. Therefore, the reasons for withholding the cost proposals pursuant to Exemption 4 still exist.

We feel that the District Court misunderstood the bid protest procedure when it characterized the award as a final decision. The October 14th notice to Shermco was of a proposed award to Tayko; it was not a final decision. The District Court’s statement that there was no need for secrecy because the award would be made either to Tayko or to Shermco is contrary to GAO protest procedure. It is amply clear from the record and from oral argument that there is a possibility that if the protest were to succeed either before the GAO, the SBA or some other forum, the bidding could be reopened. Thus, the Tayko pricing infor *1318 mation is covered by Exemption 4 and should not have been disclosed. 7

III. The Legal Memoranda And Exemption 5

The refusal of the Air Force to disclose three legal memoranda attached to its response to Shermco’s protest was based on Exemption 5 of FOIA, 5 U.S.C. § 552(b)(5):

inter-agency or intra-agency memorandums or letters which would not be available by law to a party other than an agency in litigation with the agency

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Khine v. U.S. Dep't of Homeland Sec.
334 F. Supp. 3d 324 (D.C. Circuit, 2018)
Gahagan v. United States Citizenship & Immigration Services
147 F. Supp. 3d 613 (E.D. Louisiana, 2015)
National Security Counselors v. Central Intelligence Agency
898 F. Supp. 2d 233 (District of Columbia, 2012)
Mobley v. Department of Justice
845 F. Supp. 2d 120 (District of Columbia, 2012)
Michaelis, Montanari & Johnson v. Superior Court
136 P.3d 194 (California Supreme Court, 2006)
Stromberg Metal Works, Inc. v. University of Maryland
887 A.2d 1085 (Court of Special Appeals of Maryland, 2005)
Jowett, Inc. v. Department of Navy
729 F. Supp. 871 (District of Columbia, 1989)
Triax Co. v. United States
33 Cont. Cas. Fed. 74,663 (Court of Claims, 1986)
Landfair v. United States Department of the Army
645 F. Supp. 325 (District of Columbia, 1986)
Virginia Transformer Corp. v. U.S. Department of Energy
628 F. Supp. 944 (W.D. Virginia, 1986)
J. H. Lawrence Co. v. Smith
545 F. Supp. 421 (D. Maryland, 1982)
Chilivis v. Securities & Exchange Commission
673 F.2d 1205 (Eleventh Circuit, 1982)
National Western Life Insurance v. United States
512 F. Supp. 454 (N.D. Texas, 1980)
Cliff v. Internal Revenue Service
496 F. Supp. 568 (S.D. New York, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
613 F.2d 1314, 27 Cont. Cas. Fed. 80,280, 1980 U.S. App. LEXIS 19498, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shermco-industries-inc-and-peter-a-sherman-v-secretary-of-the-air-force-ca5-1980.