Shebby Dredging Co. v. Smith Bros., Inc.

469 F. Supp. 1279, 1979 U.S. Dist. LEXIS 12511
CourtDistrict Court, D. Maryland
DecidedMay 9, 1979
DocketCiv. H-77-1545, H-77-1546
StatusPublished
Cited by6 cases

This text of 469 F. Supp. 1279 (Shebby Dredging Co. v. Smith Bros., Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shebby Dredging Co. v. Smith Bros., Inc., 469 F. Supp. 1279, 1979 U.S. Dist. LEXIS 12511 (D. Md. 1979).

Opinion

ALEXANDER HARVEY, II, District Judge:

In the early morning hours of April 2, 1977, the dredge MARILYN sank in approximately twenty feet of water, as it was heading into Hooper Strait in the Chesapeake Bay, near the mouth of the Honga River. At the time, the MARILYN was being towed by the tug HAWK.

The sinking of this dredge has resulted in filing of two separate civil actions, both of which are now before the Court for decision. The owner of the dredge MARILYN is Shebby Dredging Co., Inc. (hereinafter “Shebby”), a family-owned corporation engaged in the dredging business. Shebby filed suit in this Court under Rule 9(h), naming as defendants Smith Bros., Inc. (hereinafter “Smith Bros.”) and one of its employees, Michael D. Smith, who was the master of the tug HAWK when the sinking occurred. Smith Bros., a marine contractor, does pile driving, salvage and other marine work and is the owner of the HAWK. In the complaint it filed in Civil No. H-77-1545, Shebby has alleged that while the MARILYN was being towed by the HAWK on April 1 and April 2, 1977, the defendants conducted the towing operation in a negligent manner, and Shebby has asserted that such negligence was the proximate cause of the sinking of the dredge in the early morning hours of April 2, 1977. In this action, Shebby is seeking damages in the amount of $71,924.13 for costs incurred in raising the dredge, for costs incurred in repairing and refurbishing the dredge once it was raised, and for additional damages sustained by Shebby when it rented another dredge to complete a job which it had contracted to undertake with the dredge MARILYN.

In denying liability, defendants in Civil No. H-77-1545 assert that they fully performed their duty to exercise such reasonable care and maritime skill in the towing operation as a prudent navigator would employ in the performance of similar services. These defendants have further asserted that they are not liable to Shebby for damages resulting from the sinking because the dredge itself was unseaworthy and because the master of the dredge was in command of the towing operation and should be held responsible for any action taken which led to the sinking.

Smith Bros, itself filed a suit against Shebby in the District Court of Maryland for Anne Arundel County, seeking to recover $1,931.82, allegedly due for towing services rendered. That action was removed to this Court pursuant to 28 U.S.C. § 1333, and has been docketed as Civil No. H-77-1546. The two cases have been consolidated and tried together, pursuant to Rule 42(a), F.R. Civ.P.

The non-jury trial lasted some four days, and the evidence pertaining to many of the issues was sharply conflicting. In making its findings, the Court has given due regard to the credibility of the witnesses. This Court’s findings of fact and conclusions of law, under Rule 52(a), F.R.Civ.P., are embodied herein, whether or not expressly so characterized.

I

The Facts

Frank J. Shebby and his wife operate a small dredging business which they have incorporated. Frank Shebby is the President and is responsible for all details concerning dredging operations, and his wife, Betty R. Shebby, the Vice President, is in charge of the books and records. Frank Shebby himself designed and built the dredge MARILYN some twenty years ago. Various improvements and repairs of the dredge were made from time to time since it was built, but the evidence indicates that at the time of the sinking in early April of 1977, the MARILYN was not in good shape. Indeed, it had previously sunk on two prior occasions, although never while under tow.

*1282 From October 1976 until March 1, 1977, the MARILYN was located at Joppatowne, Harford County, Maryland, where it had been doing work during the fall months. The winter of 1976-1977 was a particularly severe one in the Maryland area, and the dredge had been locked in the ice for several months at its Joppatowne location. On January 3, 1977, Shebby had entered into a contract with Somerset County for the performance of certain dredging work in Dames Quarter Creek, Dames Quarter, Maryland. Shebby had bid on the job and had been awarded the contract at a price of $93,430.00. The contract required that the work be done between January 20, 1977 and June 1, 1977.

The evidence indicates that Frank Shebby operated his dredging business in a somewhat casual and disorganized manner. In late March 1977, with only a few months left to complete the Dames Quarter job, Frank Shebby made arrangements for transporting the MARILYN and other necessary equipment across Chesapeake Bay, from Joppatowne in Harford County on the Western Shore of the Bay to Dames Quarter Creek in Somerset County on the Eastern Shore of the Bay. Besides the dredge, he intended to take along a small tugboat which he owned (the BETTY R), a fuel barge, a derrick or work barge, approximately 1,000 feet of floating pipe and a small skiff or work boat. Arrangements for the towing of this flotilla from the Western to the Eastern Shore of Maryland were quite haphazard. At times, Shebby’s small boat, the BETTY R, itself did the towing or assisted in the towing. At other times, two other firms performed the towing operations, Mohawk Marine Services, Inc. and Smith Bros. At all times, Shebby’s employee, Roland M. Sellers, acted as master of the MARILYN and accompanied the flotilla.

The first part of the towing operation was performed by the MOHAWK, a power boat owned by Mohawk Marine, assisted by the BETTY R. A 50-foot Vineyard cruiser, the MOHAWK is essentially a pleasure boat, and with the assistance of Shebby’s own small tugboat, the BETTY R, it managed with some difficulty to tow the flotilla consisting of the MARILYN and related equipment from Joppatowne across the Bay to Lowe’s Wharf, which is located in Talbot County. Sellers had been in charge of the dredge and its related equipment, and he was quite unhappy with the towing operation across the Bay, mainly because of the lack of power of the MOHAWK. MOHAWK personnel were told that they were no longer needed, and Frank Shebby then undertook to try to find another means for completing the trip down the Bay to the dredging site in Somerset County.

On March 27, 1977, Frank Shebby telephoned Kenneth W. Smith, the President of Smith Bros., a firm located in Galesville, Maryland, which does marine construction and other related work. Frank Shebby asked Mr. Smith if he could furnish a tug to tow the flotilla down the Bay to the job site in Somerset County. Smith declined because he did not then have a licensed tug operator available. Shebby suggested that he himself would provide a tug captain, but Smith said he did not want a stranger on board one of his tugs. Unable to secure anyone else to perform the towing operation and anxious to begin his Somerset County job at once, Frank Shebby called Smith back several days later and pleaded with him to undertake the towing operation. Smith finally relented and agreed to furnish the tug HAWK, with his nephew, Michael D. Smith, as the captain and Robert Bast, another employee, as the deckhand. The parties orally agreed on a contract price of $45 per hour, plus time and a half for each of the men on board in excess of ten hours.

The towing job was to start the next day, March 31, 1977. However, the wind was blowing too hard that day, and it was not until April 1 that the towing operation actually commenced.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
469 F. Supp. 1279, 1979 U.S. Dist. LEXIS 12511, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shebby-dredging-co-v-smith-bros-inc-mdd-1979.