Shaw v. L.A. Socci, Inc.

587 A.2d 429, 24 Conn. App. 223, 1991 Conn. App. LEXIS 72
CourtConnecticut Appellate Court
DecidedMarch 12, 1991
Docket8915
StatusPublished
Cited by27 cases

This text of 587 A.2d 429 (Shaw v. L.A. Socci, Inc.) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shaw v. L.A. Socci, Inc., 587 A.2d 429, 24 Conn. App. 223, 1991 Conn. App. LEXIS 72 (Colo. Ct. App. 1991).

Opinion

Foti, J.

The defendant appeals from the judgment rendered in favor of the plaintiffs. By their complaint, the plaintiffs sought reimbursement for the cost of a [225]*225swimming pool cover, and for additional amounts required to complete or repair work either not performed by the defendant, or done in a deficient manner. The defendant, by its counterclaim, sought an unpaid balance due, including claimed additional options, in the amount of $6095.51. The defendant alleges that the court improperly (1) held that General Statutes § 20-429 (a) (6) is a special defense to its counterclaim, and (2) failed to consider adequately the defendant’s objections to the factual findings. We reverse the trial court’s judgment in part.

This action was referred to an attorney factfinder.1 A hearing was conducted by the factfinder, and findings of fact were Issued on December 13, 1989. The factfinder found that on October 6,1986, the plaintiffs, Katherine A. Shaw and Marian B. Keegan, entered into a contract with the defendant, L.A. Socci, Inc. This contract provided that the defendant would remodel the plaintiffs’ swimming pool according to certain specifications for the sum of $14,950. It was further found that the plaintiffs had paid the full contract price, which included handwritten extras for a total of $20,000, and had also expended $2409.27 to complete work unfinished by the defendant and to repair work of deficient quality that the defendant had performed. The plaintiffs paid $3500 for additional options and also spent $1662 for a new pool cover that was to have been furnished by the defendant. The factfinder recommended that judgment be rendered for the plaintiffs in the amount of $4071.57. He also recommended that the court deny the defendant’s counterclaim because the plaintiffs had asserted a valid special defense under the Home [226]*226Improvement Act, General Statutes § 20-429 (a) (6).2 The trial court accepted these recommendations and rendered judgment accordingly.3

The defendant claims, the plaintiffs concede, and we agree that the plaintiffs were not entitled to the statutory special defense recommended by the factfinder and accepted by the trial court. General Statutes § 20-429 (a) (6) was enacted in 1988 as part of Public Acts 1988, No. 88-269, § 9.4 It was not part of the Home Improvement Act as it existed in 1986 when this contract was formed. Therefore, it cannot be a valid special defense to the defendant’s counterclaim.

The plaintiffs argue, however, that we should affirm the trial court’s judgment in their favor on the defendant’s counterclaim because, although the grounds relied on by the trial court were improper, the court’s decision was supported by other proper grounds. The plaintiffs argue that General Statutes § 20-429 (a)5 barred the counterclaim even as it existed in October, 1986. [227]*227The provision, now codified as General Statutes § 20-429 (a) (3), requires a home improvement contract to contain the entirety of the parties’ agreement. The plaintiffs argue that because the written contract did not reduce the parties’ entire agreement to writing, the contract cannot be enforced by the defendant through his counterclaim.6

It is not clear whether the written contract of October 6,1986, which indisputedly amounted to $20,000, is the entire agreement of the parties. Also, it is not clear what is meant by “additional options” and “additional work” under the “terms of the written contract” as is claimed by the defendant’s counterclaim. The record is, therefore, inadequate to allow us to determine whether there is the requisite factual basis to determine the ultimate question necessary for the alternate ground, namely, whether the parties’ entire agreement was reduced to writing.

We would affirm the judgment even if based on erroneous grounds “if the same result is required by law.” A&H Corporation v. Bridgeport, 180 Conn. 435, 443, 430 A.2d 25 (1980); see also East Hartford v. East Hartford Municipal Employees Union, Inc., 206 Conn. 643, 646-47, 539 A.2d 125 (1988); Golab v. New Britain, 205 Conn. 17, 27, 529 A.2d 1297 (1987); Herrmann v. Summer Plaza Corporation, 201 Conn. 263, 274, 513 A.2d 1211 (1986). We cannot, however, affirm the deci[228]*228sion based on the statute cited by the plaintiff. The record shows that this statute was never considered by the factfinder, and both the factfinder’s report and the court’s memorandum of decision are devoid of factual support for the plaintiffs’ position.7 Therefore, we cannot determine whether the trial court would have been forced to conclude that the parties’ entire agreement was not reduced to writing. Although “this court is authorized to rely upon alternative grounds supported by the record to sustain a judgment”; Henderson v. Department of Motor Vehicles, 202 Conn. 453, 461, 521 A.2d 1040 (1987); in this case, the record is insufficient to permit us to employ the alternative ground and does not supply justification to affirm. The judgment for the plaintiffs on the defendant’s counterclaim must, therefore, be set aside, and a new hearing held regarding it on remand.8

The defendant next claims that the court did not properly “attend to its objections” to the factual findings. The defendants filed objections to two of the factual findings pursuant to Practice Book § 546H.9 The defendant objected to the finding that a new pool cover was included in the contract price, and the finding that a new contractor was hired to remedy defective work. [229]*229The bases of these objections was the defendant’s contention that the findings were conclusory and not supported by the evidence, and that the trial court had not adequately reviewed the findings of the factfinder.

The trial court addressed the defendant’s objections in the memorandum of decision: “The defendant has filed objections to the acceptance of the factfinder’s recommendation. Two of the objections in essence ask that the court substitute its own findings of fact for those of the factfinder. This request must be denied in the light of the very recent decision in Wilcox Trucking, Inc. v. Mansour Builders, Inc., 20 Conn. App. 420, 423, 567 A.2d 1250 (1989), cert. denied, 214 Conn. 804, 573 A.2d 318 (1990).” The court relied on the language from Wilcox that “[i]n a contract action findings of fact should be overturned only when they are clearly erroneous.”

It is not our function to review the findings of the factfinder initially to determine whether those findings were properly reached on the basis of subordinate facts found. That initial review is the duty of the trial court. Nothing in the record indicates that the trial court did not fulfill its duty. In

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Blacker v. Crapo
964 A.2d 1241 (Connecticut Appellate Court, 2009)
City Fish Market, Inc. v. Varipapa, No. Cv01-0508994s (Mar. 18, 2002) Ct Page 3428
2002 Conn. Super. Ct. 3427 (Connecticut Superior Court, 2002)
Butler v. Freedom Choice Mtge. and Noe, No. Cv98-0578124 (Jan. 18, 2001)
2001 Conn. Super. Ct. 612 (Connecticut Superior Court, 2001)
Rosano v. Capurso, No. Cv97-0484322s (Mar. 13, 2000)
2000 Conn. Super. Ct. 4685 (Connecticut Superior Court, 2000)
John M. Glover Agency v. Rdb Building, No. Cv 97-0162410 (Jul. 2, 1999)
1999 Conn. Super. Ct. 9185 (Connecticut Superior Court, 1999)
Schulman v. Smalley, No. Cv 97-0159732 (Nov. 12, 1998)
1998 Conn. Super. Ct. 13049 (Connecticut Superior Court, 1998)
Up Technology, Inc. v. Mga, Inc., No. Cv 95-0148-221 (Apr. 30, 1998)
1998 Conn. Super. Ct. 5302 (Connecticut Superior Court, 1998)
Tam Commun. v. Essex Motor Sports Int'l, No. Cv 96-0154 571 (Apr. 29, 1998)
1998 Conn. Super. Ct. 5246 (Connecticut Superior Court, 1998)
Greater N.Y Mut. Ins. v. Locust Ave. A., No. Cv 96-0153 949 (Apr. 29, 1998)
1998 Conn. Super. Ct. 5153 (Connecticut Superior Court, 1998)
G P Air Cond. v. Davidoff of Geneva, No. Cv 96-0154047 (Apr. 9, 1998)
1998 Conn. Super. Ct. 4579 (Connecticut Superior Court, 1998)
A.J. Clarke Management Corp. v. Gladstone, No. 96-0152454 (Jan. 12, 1998)
1998 Conn. Super. Ct. 236 (Connecticut Superior Court, 1998)
Port Miolla Associates v. Cgr Productions, No. Cv96 0150088 (May 9, 1997)
1997 Conn. Super. Ct. 5949 (Connecticut Superior Court, 1997)
Precision Hose v. Prime Time Leasing Serv., No. Cv93 0133934 (Apr. 23, 1996)
1996 Conn. Super. Ct. 3616 (Connecticut Superior Court, 1996)
Stamford Hospital v. Dragan, No. Cv90 0110563 (Feb. 22, 1996)
1996 Conn. Super. Ct. 1365-MMM (Connecticut Superior Court, 1996)
Walter C. King Assoc. v. New Canaan Alarm, No. Cv92 0127607 (Aug. 29, 1995)
1995 Conn. Super. Ct. 9853 (Connecticut Superior Court, 1995)
Lamplighter Electric, Inc. v. Brown, No. 31 42 13 (Apr. 5, 1995)
1995 Conn. Super. Ct. 3986 (Connecticut Superior Court, 1995)
Citibank v. Klahr, No. Cv93 0134685 (Mar. 15, 1995)
1995 Conn. Super. Ct. 2285 (Connecticut Superior Court, 1995)
Great Amer. Ins. v. Deming Luscomb, No. Cv90 037 85 67 S (Mar. 10, 1995)
1995 Conn. Super. Ct. 2210 (Connecticut Superior Court, 1995)
Oriental Rug Gallery v. Labrasciano, No. Cv 93 0131963 (Jan. 26, 1995)
1995 Conn. Super. Ct. 425 (Connecticut Superior Court, 1995)
Meyer Hill Lynch Corp. v. Systrak, Inc., No. 34 20 59 (Nov. 22, 1993)
1993 Conn. Super. Ct. 10112 (Connecticut Superior Court, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
587 A.2d 429, 24 Conn. App. 223, 1991 Conn. App. LEXIS 72, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shaw-v-la-socci-inc-connappct-1991.