Sharble v. Kuehnle-Wilson, Inc.

59 A.2d 58, 359 Pa. 494, 1948 Pa. LEXIS 426
CourtSupreme Court of Pennsylvania
DecidedApril 22, 1948
DocketAppeals, 74 and 75
StatusPublished
Cited by18 cases

This text of 59 A.2d 58 (Sharble v. Kuehnle-Wilson, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Sharble v. Kuehnle-Wilson, Inc., 59 A.2d 58, 359 Pa. 494, 1948 Pa. LEXIS 426 (Pa. 1948).

Opinion

Opinion by

Mr. Justice Drew,

Plaintiffs, Joseph C. Sharble and Charles Hooker, brought individual suits in trespass to recover damages for injuries sustained by them while laying a steel roof on the machine shop of the Heppenstall-Eddystone Corporation at Eddystone, Pennsylvania. These actions were instituted against defendants, Heppenstall-Eddystone Corporation, Raymond Concrete Pile Company, and Kuehnle-Wilson, Inc. The suits were tried together, and, after the jury retired but before verdicts were returned, plaintiffs took voluntary nonsuits as to the first two defendants. The jury rendered verdicts in favor of plaintiffs and against defendant, Kuehnle-Wilson, Inc. Defendant’s motions for judgment n. o. v. and for a new trial having been dismissed and judgments having been entered on the verdicts, these appeals followed.

Viewing the testimony in the light most favorable to plaintiffs, as we are required to do under these circumstances, the following pertinent facts appear: Both plaintiffs were sheet metal workers employed by Eric Welding Company, a subcontractor, in putting a Holorib steel roof on an extension to a building, owned by defendant, Heppenstall-Eddystone Corporation, and being erected by defendant, Raymond Concrete Pile Company. The other defendant, Kuehnle-Wilson, Inc., was the painting subcontractor under the general contract. Neither subcontractor, Eric Welding Company or Kuehnle-Wilson, Inc., had authority or control over the work or the employees of the other.

The building being erected was of steel framework, with steel uprights and cross pieces, forming the sides. It was approximately 1,000 feet long, 87 feet wide and 50 feet high. A ventilating monitor ran lengthwise along the peak of the roof. The roof structure was supported by steel girders, which extended, 16 feet apart, from the *497 eaves to the monitor. Each 16-foot space between these roof girders is known as a bay. Purlins, or small beams about 2 inches wide across the top, ran across each bay, at 6-foot intervals, parellel with the eaves, and connected the girders. The purlins constituted the framework on which the steel roof ivas to be laid. The roof slanted downward from the monitor to the eaves at a pitch or drop of about 4 feet over a distance of 46 feet, or approximately 6 inches in 6 feet.

The Holorib steel roof consisted of prefabricated sections of light gauge sheet steel, the sheets being used in this construction being 6 feet long and 18 inches wide. Two wedge-shaped ribs were pressed lengthwise in each sheet, with a third full rib, U-shaped, running down one long side and a half rib, L-shaped, down the other side. The half rib, shaped like an “L”, was designed to fit into the U-shaped rib extending down the side of the sheet laid next to it, making a substantially continuous surface on the weather side of the roof.

In laying these sheets, it was the custom to place them at right angles to the side of the building, beginning at the end wall at the lower edge, or eave. They are laid rib-side down, across the eave girder and first purlin. After the first sheet is laid, the next one is placed along side with its “L” side overlapping into the “U” side of the first sheet, and so on until all 12 sheets in the first run or course across the first bay are laid. The second run in that bay is then laid, and so on up to the monitor until the first bay is finished. The first sheet of the run is securely anchored when laid, by being spot-welded to the eave girder and to the first purlin. The other sheets in that run are held in place merely by the interlocking process along the sides, until the run is completed, then they are driven into position with a mallet and welded to the building superstructure. The sheets in the second and any succeeding bay are not welded until the entire run across that bay is placed in position and fully adjusted. In laying these sheets sue *498 cessively from one side of a bay to the other, it is necessary for the roofers to walk on the sheets they have just laid.

The employees of the Eric Welding Company had completed and tack-welded the entire first bay of the roof. As it is customary to have the purlins, girders and other structural metal work of the roof painted before the sheets are laid, Lundy, superintendent of the Eric Welding Company roofers, on July 19, 1942, requested Loftus, foreman of the painters employed by defendant, Kuehnle-Wilson, Inc., to get the second bay ready for the roofing men to lay the additional metal roofing. Following that request, Loftus the next day caused several bays to be painted adjoining the first bay on which the roofing sheets had been laid. On July 21, 1942, he informed Lundy that these bays had been painted, that they were ready for use and it was all right for the roofers to work on them. In the early afternoon of that day, Lundy sent three sheet metal workers, both plaintiffs and one Greenhalg, on the roof to lay the roofing sheets across the second bay. Greenhalg received the sheets as they were hoisted from the ground, took them off the pulley and carried them to plaintiffs, who started to lay them.

Plaintiffs interlocked the first sheet of the first, or eave, run in the second bay into the last sheet of the first run in the first bay, and proceeded to lay the additional sheets, interlocking them one with the other. About 2 o’clock in the afternoon, when these roofers were laying the sixth sheet in that run, that sheet and the others which they had just laid, slipped off the purlin. Plaintiffs fell to the floor and were seriously injured.

Defendant contends that the learned court below erred in not entering judgments in its favor, notwithstanding the verdicts, alleging the evidence offered by plaintiffs was entirely inadequate to prove negligence on its part, and for the further reason plaintiffs were guilty of contributory negligence as a matter of law.

*499 It is clear that defendant, Kuehnle-Wilson, Inc., owed the duty of ordinary care in the conduct of the work of painting the roof superstructure so as not to expose the employees of Eric Welding Company, the roofing subcontractor, to unnecessary danger. When Lundy, the latter’s superintendent, was informed by Loftus, defendant’s foreman, that the roof steel had been painted and was ready, Loftus knew that the roofers would be brought in contact with the roof girders and purlins, which had recently been painted, and that they might be seriously injured if they attempted to lay metal sheets over paint which had not dried sufficiently. In this connection, in Grogan v. J. H. Hinkle & Co., Inc., 70 Pa. Superior Ct. 585, 588, the Superior Court, speaking through Judge Kephart, later Chief Justice of this Court, said: “. . . it is the duty of independent or different masters engaged about the same general employment to use such ordinary care and diligence in the conduct and prosecution of their several contracts or employments so as not to expose the servants of the master working with them to danger and if injury results to the servants of either, through failure to exercise such care and diligence, the master whose servants caused the injury will be liable in damages: Johnston v. Ott Bros., 155 Pa. 17; Alexander v. Maryland Steel Co., 189 Pa. 582; Kitchin v. Riter-Conley Co., . . . [207 Pa. 558]; Urban v. Focht, 231 Pa. 623.” See also Bisson v. John B. Kelly, Inc., 314 Pa.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

COTE v. SCHNELL INDUSTRIES
M.D. Pennsylvania, 2021
McKenzie v. Cost Bros., Inc.
394 A.2d 559 (Superior Court of Pennsylvania, 1978)
Happel v. Johnson
62 Pa. D. & C.2d 587 (Northampton County Court of Common Pleas, 1972)
Connor v. Hawk
128 A.2d 566 (Supreme Court of Pennsylvania, 1957)
Freas v. GUBER
117 A.2d 814 (Superior Court of Pennsylvania, 1955)
Freund v. Hyman
103 A.2d 658 (Supreme Court of Pennsylvania, 1954)
Schentzel v. Philadelphia National League Club
96 A.2d 181 (Superior Court of Pennsylvania, 1953)
Blake v. Fried
95 A.2d 360 (Superior Court of Pennsylvania, 1953)
Wagner v. Somerset County Memorial Park, Inc.
93 A.2d 440 (Supreme Court of Pennsylvania, 1953)
Lanni v. Pennsylvania Railroad
88 A.2d 887 (Supreme Court of Pennsylvania, 1952)
Sarne v. Baltimore & Ohio Railroad
87 A.2d 264 (Supreme Court of Pennsylvania, 1952)
KRAMER v. MEYER
76 A.2d 481 (Superior Court of Pennsylvania, 1950)
Moran v. Pittsburgh-Des Moines Steel Co.
86 F. Supp. 255 (W.D. Pennsylvania, 1949)
Dillon v. William S. Scull Co.
64 A.2d 525 (Superior Court of Pennsylvania, 1948)
Polk v. Steel Workers Organizing Committee
62 A.2d 850 (Supreme Court of Pennsylvania, 1948)

Cite This Page — Counsel Stack

Bluebook (online)
59 A.2d 58, 359 Pa. 494, 1948 Pa. LEXIS 426, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sharble-v-kuehnle-wilson-inc-pa-1948.