Shannon v. Computer Associates International, Inc.

45 P.3d 345, 202 Ariz. 348, 18 I.E.R. Cas. (BNA) 1278, 372 Ariz. Adv. Rep. 21, 2002 Ariz. App. LEXIS 59
CourtCourt of Appeals of Arizona
DecidedApril 30, 2002
Docket1 CA-CV 01-0321
StatusPublished
Cited by1 cases

This text of 45 P.3d 345 (Shannon v. Computer Associates International, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shannon v. Computer Associates International, Inc., 45 P.3d 345, 202 Ariz. 348, 18 I.E.R. Cas. (BNA) 1278, 372 Ariz. Adv. Rep. 21, 2002 Ariz. App. LEXIS 59 (Ark. Ct. App. 2002).

Opinion

OPINION

EHRLICH, Judge.

¶ 1 Michael J. Shannon arranged to terminate his employment with Platinum Technology and signed a contract to become an independent contractor doing work for Platinum. Immediately thereafter, Platinum announced a mass layoff of its employees, whereupon Shannon sought from Platinum back pay pursuant to the federal Worker Adjustment and Retraining Notification (“WARN”) Act. When his request was denied, he sued. The trial court ruled that Shannon was entitled to such pay. For reasons discussed below, we conclude to the contrary; we therefore reverse the judgment in Shannon’s favor.

BACKGROUND

¶ 2 Shannon was hired by Mastering Computers and continued when the employer became Platinum Technology. He presented seminar’s on computer-software use throughout the United States.

¶ 3 On February 5, 1999, Shannon told his direct supervisor that he “might need” to resign. The supervisor informed Ted Hernandez, a managing supervisor, who met with Shannon. Hernandez offered Shannon a $5000 annual raise, which Shannon declined. Hernandez then suggested that Shannon could give the seminars as an independent contractor. Shannon agreed and, on the same day, he signed an independent-contractor agreement titled “Agreement of New Consultant” that changed his status from employee to independent contractor effective March 1, 1999, with payment to be on a per-seminar basis. Hernandez kept Shannon on the payroll until the end of February so that Shannon’s income would continue until he began the March seminars under contract.

¶4 Eight seminars were scheduled for March 1999, and, pursuant to the agreement, Shannon was to be paid $750 for each one he taught. Hernandez advised Shannon that there were no seminars scheduled after March and that there were “no guarantees.” Additionally, the contract provided that Platinum did not agree to retain Shannon for any specified duration and that it could terminate Shannon’s engagement at any time for any or no reason.

¶5 On February 25, 1999, Platinum announced to employees there would be mass layoff the next day. Platinum paid Shannon through February 26, but it decided not to utilize his services for the scheduled March seminars. The company honored the fourteen-day cancellation provision of the independent-contractor agreement, paying Shannon for the seminar that was scheduled during that time.

¶ 6 On March 1, Shannon received a letter from Platinum advising him that, as a result of the permanent reduction in workforce, his employment was terminated effective February 26, 1999, and that he would receive his regular salary and benefits for sixty days as required by the WARN Act, 29 U.S.C. § 2101 et seq. (1994). When Shannon did not receive those benefits, Platinum took the position that the letter had been sent in error due to the fact that Shannon was on the payroll through the end of February.

¶ 7 Shannon sued Platinum, Mastering Computers and Computer Associates International, Inc., which he believed had acquired Platinum (collectively “Platinum”), seeking unpaid wages, back pay for a violation of the *351 WARN Act and damages for breach of the independent-contractor agreement. The case was heard by an arbitrator, who found in favor of Shannon and awarded him $9166.68 for sixty days of back pay, plus additional amounts for attorneys’ fees, prejudgment interest and costs.

¶ 8 Platinum appealed the arbitration award. Each side filed a motion for summary judgment.

¶9 Judge B. Michael Dann granted summary judgment in favor of Shannon on the WARN Act claim but only for the two days in February for which Shannon remained an employee after the February 26 layoffs. Judge Dann then denied both motions for summary judgment on the question of Platinum’s liability for back pay under the WARN Act for March 1 and thereafter to a total of sixty days. The judge reasoned that, if Platinum had given the notice required by the Act, Shannon might have elected to continue as an employee rather than switching to independent-contractor status, thus raising an issue of fact. Summary judgment was granted in favor of Platinum on Shannon’s claim for breach of contract.

¶ 10 Shannon moved to amend his complaint to add a claim for rescission of the independent-contractor agreement. Judge Robert D. Myers, who was assigned the case after Judge Dann retired, granted the motion. He also denied motions for reconsideration filed by both Shannon and Platinum.

¶ 11 Platinum moved for partial summary judgment on the rescission claim, and Shannon moved for summary judgment on his WARN Act damages. The case was subsequently assigned to Judge Roger W. Kaufman, who denied Platinum’s motion regarding rescission. He also ruled that Shannon was entitled to the presumptive sixty days of back pay from the time he received actual notice of termination. Judge Kaufman thus awarded Shannon $8739.73 in back pay and $17,500 in attorneys’ fees. Platinum appealed from the judgment.

DISCUSSION

A. WARN Act Damages

¶ 12 In 1988, Congress enacted the WARN Act, which provides that an employer with more than 100 full-time employees

shall not order a plant closing or mass layoff until the end of a 60-day period after the employer serves written notice of such an order.

29 U.S.C. § 2102(a)(Supp.1999). The notice must be given to

each representative of the affected employees as of the time of the notice or, if there is no such representative at that time, to each affected employee.

29 U.S.C. § 2102(a)(1) (1994). The purpose of the Act is to ensure that “workers receive advance notice of plant closures and mass layoffs that affect their jobs.” Marques v. Telles Ranch, Inc., 131 F.3d 1331, 1333 (9th Cir.1997).

¶ 13 The WARN Act further provides that an employer that orders a qualifying plant closing or mass layoff without the required notice

shall be liable to each aggrieved employee who suffers an employment loss as a result of such closing or layoff for ... back pay for each day of violation at a rate of compensation not less than the higher of ... the average regular rate received by such employee during the last 3 years of the employee’s employment; or ... the final regular rate received by such employee

as well as certain employee benefits. 29 U.S.C. § 2104(a)(1)(A), (B). The employer’s liability is “calculated for the period of the violation, up to a maximum of 60 days.... ” 29 U.S.C. § 2104(a)(1).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re First Magnus Financial Corp.
390 B.R. 667 (D. Arizona, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
45 P.3d 345, 202 Ariz. 348, 18 I.E.R. Cas. (BNA) 1278, 372 Ariz. Adv. Rep. 21, 2002 Ariz. App. LEXIS 59, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shannon-v-computer-associates-international-inc-arizctapp-2002.