Bradley v. Sequoyah Fuels Corp.

847 F. Supp. 863, 9 I.E.R. Cas. (BNA) 449, 1994 U.S. Dist. LEXIS 3864, 1994 WL 102379
District Court, E.D. Oklahoma·Decided March 23, 1994·No. 93-252-S, 93-514-S·Published·Cited by 9 cases

Opinion

OPINION

SEAY, Chief Judge.

This is a consolidated action brought by plaintiffs against defendant, Sequoyah Fuels Corporation (“SFC”), pursuant to the provisions of the Worker Adjustment and Retraining Notification Act (the “WARN Act”), 29 U.S.C. §§ 2101-2109. The remaining plaintiffs in Case No. 93-252-S are Barbara Bradley, Linda Box, Stanley Brown, Jimmy Case- *864 bolt, Phyllis Clay, Edward Elbon, John Fox, Johnny Galatian, Dixie Harl, Randy Maxwell, Arthur Pearson, Coletta Peyton, Janet Ross, Marty Ross, Mike Sutterfield, Sue Smith, Graham Swearingen, Lawrence White, and Jesse Wilkerson. The remaining plaintiffs in Case No. 93-514-S are Randall Allen, Virginia Callison, Deborah A. Emerson, Don M. Goad, D.K. Isham, Rick Jackson, Patricia Linthicum, Donald Lyons, Paul E. Pewitt, Tammy L. Posch, William Shell, Thomas E. Smith, Dwayne Vernon, Jim Weemes, Lee Ann Allen, John W. Davis, and Perry D. Trotter. All plaintiffs were formerly employed by SFC at its commercial uranium conversion plant in Gore, Oklahoma, prior to the closing of the plant on November 30, 1992. 1 - Plaintiffs seek to recover backpay and benefits from SFC based on their contention that SFC violated the WARN Act by failing to give them sixty days’ advance written notice of the November 30, 1992, plant closing. SFC defends against plaintiffs’ claims by asserting that its failure to give the required sixty days’ notice was excused under the “business circumstances exception” of the WARN Act.

SFC previously moved the court for the entry of summary judgment in its favor based on its asserted defense of the “business circumstances exception”. The court found that there were genuine issues of material fact with respect to SFC’s defense and denied the motion. Thereafter, the court ordered the issue of liability bifurcated from the issue of relief. In accordance with the bifurcation order, the liability phase of this action came on for trial before the court on January 20 and 21, 1994. Based on the evidence presented, the court enters its findings and conclusions as required by Rule 52(a) of the Federal Rules of Civil Procedure.

Findings of Fact

Employment Status of Plaintiffs Posch and Lyons

Posch began her employment at SFC in September 1992, as a warehouse clerk. Her hiring was on a temporary basis and she was not afforded the work-related benefits provided to full-time employees. In the latter part of October 1992, Posch was required by SFC to transfer to a temporary employment agency, Allied Staffing Associates (“ASA”). Posch’s work activities and pay remained the same; however, from the latter part of October 1992, until her termination on November 30, 1992, Posch was officially employed by ASA and was paid by ASA.

Lyons began working at SFC on June 8, 1981, as a chemical operator and worked until April 1992, when he went on medical leave as a result of an on-the-job back injury. Lyons has been receiving worker’s compensation payments since April 1992, and he has approximately seventy to eighty weeks of payments remaining. At the time of his termination on December 9, 1992, and continuing up until the time of trial, Lyons had not been released to return to work by his doctors. Lyons testified that he is not sure if he will ever be physically capable of returning to work.

The October 1991 Shutdown

The Gore, Oklahoma, facility operated by SFC is a nuclear chemical processing facility which has as its primary process the purification and conversion of natural uranium concentrates into uranium hexafluoride (UFg) for use by nuclear power companies. The other process at the facility involves a chemical reduction of depleted UF6 into DUF4, a green powder that can be smelted into uranium metal. SFC is licensed to operate the Gore facility through the Nuclear Regulatory Commission’s (“NRC”) issuance of operating and bi-produet licenses. The NRC’s regulation and oversight of SFC’s operations over the past decade can best be described as pervasive and extensive. As the testimony at the trial established, SFC’s performance history has resulted in the existence of an adversarial relationship between SFC and the NRC with respect to the continued operation of the Gore facility.

*865 In September 1991, the Gore facility was shut down for routine maintenance. During the course of this shutdown, various safety issues were triggered when soil contamination was discovered in connection with the excavation of a tank. As a result, the NRC ordered the facility not to return to service. The NRC’s investigation uncovered significant operational deficiencies at the Gore facility and it imposed a shutdown in October 1991 that lasted until April 1992, at which time a phased start-up of the facility began. During the NRC ordered shutdown,' SFC employees were required to undergo extensive training with respect to operational procedures in order to achieve a safer and more controlled working environment. NRC inspectors were a constant presence at the Gore facility during this time. They engaged in an unprecedented around-the-clock monitoring and oversight of SFC’s activities.

No employees were laid off during this period even though no revenues were being generated from production. The employees were involved in maintenance activities as well as activities in connection with the revision of procedures to meet general NRC standards and specific standards set by the NRC related to the start-up. During the shutdown, SFC also made changes in its senior management, including its President and Vice-President. For the nine-month period between October 1991 and April 1992, SFC lost approximately $18 million in revenue. This loss reduced SFC’s net worth by one-third and put SFC in a very unstable financial situation. SFC lost its operating line of credit with Citibank. In order to meet its financial obligations, SFC received advances from its parent company, General Atomics.

The various phases of the start-up were completed without major incident and by June 1992, SFC had increased its production of UF6. 2 In September 1992, the NRC closed out its October 1991 shutdown order. This action by the NRC was an acknowledgement that SFC had taken the necessary corrective action to satisfy the requirements imposed on them under the NRC’s shutdown order. Essentially, the NRC gave SFC a “clean bill of health” for continuation of operations.

The November 17, 1992, Release of Nitrogen Dioxide

Shortly after SFC was released from the shackles of the October 1991 NRC order, an event occurred in the UF6 area which caused the NRC to order the immediate shutdown of the entire Gore facility. On November 17, 1992, a sudden and unexpected reaction in a digester resulted in the release of a plume of nitrogen dioxide, a hazardous, toxic and potentially lethal gas. The gas escaped the facility and formed a brown cloud that was being carried by a strong wind. Because the release was likely to affect the public, SFC declared a site area emergency, the second highest emergency level.

Free access — add to your briefcase to read the full text and ask questions with AI

Bradley v. Sequoyah Fuels Corp., 847 F. Supp. 863, 9 I.E.R. Cas. (BNA) 449, 1994 U.S. Dist. LEXIS 3864, 1994 WL 102379 (E.D. Okla. 1994).

847 F. Supp. 863 (Bradley v. Sequoyah Fuels Corp.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

University of Kentucky v. Bunnell
532 S.W.3d 658 (Court of Appeals of Kentucky, 2017)
Weekes-Walker v. Macon County Greyhound Park, Inc.
877 F. Supp. 2d 1192 (M.D. Alabama, 2012)
Allen v. Sybase, Inc.
468 F.3d 642 (Tenth Circuit, 2006)
Snider v. Commercial Financial Services, Inc.
288 B.R. 890 (N.D. Oklahoma, 2002)
Shannon v. Computer Associates International, Inc.
45 P.3d 345 (Court of Appeals of Arizona, 2002)
Strass v. Kaiser Foundation Health Plan of Mid-Atlantic
744 A.2d 1000 (District of Columbia Court of Appeals, 2000)
Steven Scott Kildea v. Electro-Wire Products, Inc.
144 F.3d 400 (Sixth Circuit, 1998)