Shallow Brook Associates v. Dube

599 A.2d 132, 135 N.H. 40, 1991 N.H. LEXIS 141
CourtSupreme Court of New Hampshire
DecidedNovember 8, 1991
DocketNo. 90-503
StatusPublished
Cited by18 cases

This text of 599 A.2d 132 (Shallow Brook Associates v. Dube) is published on Counsel Stack Legal Research, covering Supreme Court of New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shallow Brook Associates v. Dube, 599 A.2d 132, 135 N.H. 40, 1991 N.H. LEXIS 141 (N.H. 1991).

Opinion

THAYER, J.

This is an appeal from the Superior Court’s (Goode, J.) denial of the plaintiff’s amended “Motion to Cite for Contempt and Sanctions,” which motion argued that the defendants violated the court’s earlier order to specifically perform a real estate pur[42]*42chase and sale contract. The plaintiff-buyer, Shallow Brook Associates, maintains that the court erred in ruling that it breached the contract when it failed to tender payment before a closing date set by the defendant-sellers, Ronald and Pauline Dube. The plaintiff also challenges the court’s enforcement of the contract’s liquidated damages clause to include a deposit made after the contract’s formation. We affirm.

On December 18, 1984, the defendants agreed to sell a 45-acre parcel of land in Merrimack and Bedford to the plaintiff’s predecessor in interest for $690,000. A $75,000 deposit was paid, and December 31,1985, was set as the closing date. The buyer failed to perform at the appointed date, but paid an additional $75,000 deposit as consideration for extending the time for closing. Although further attempts to close were made on both sides, none succeeded. Finally, in 1989, the buyer filed a petition for specific performance and stated that it was ready, willing, and able to complete the sale. The Superior Court (Goode, J.) granted the petition, finding that time had not been “of the essence,” and notified the parties of its decision on December 18, 1989. The court set no date for performance of the five-year-old contract. No appeal was taken from that court order.

In late January 1990, one of the plaintiff’s principals, Michael Callahan, telephoned his loan officer and requested a loan of $150,000, the amount needed for closing the parties’ contract. Callahan testified that he assumed the official would simply transfer the money to his account, as he had done several times before. Times had changed in the banking industry, however, and the official replied that Callahan would first have to obtain an appraisal of the property and an environmental survey, and then present his request to a bank committee. Callahan made no attempt to obtain either the appraisal or the survey, and abandoned his quest for bank financing.

The first communication between the parties following the court’s order of specific performance occurred on February 7, 1990, when the defendants’ counsel, Theodore Wadleigh, telephoned the plaintiff’s counsel, William Kelley, to schedule a closing. Kelley declined to suggest a date, and in response Wadleigh wrote on February 14, 1990, that he had scheduled a closing for March 1, 1990. Kelley replied two days later that “Mr. Callahan is hopeful that he will be in a position to close on this transaction on or about April 1,1990. He is not in a position to close on March 1, 1990 . . . .” When Wadleigh received this letter, he wrote back: “It still remains Mr. Dube’s position that you close on or before March 1,1990, or the contract will be terminated and the deposit forfeited.”

[43]*43March 1,1990, saw no closing on the parties’ contract, and a week later the plaintiff was still unable to predict when it would have the necessary funds to close. Wadleigh wrote to Kelley on March 9, maintaining that the defendants considered the contract terminated, but offering to return the $150,000 deposit if the plaintiff executed a release of the agreement by March 16. The plaintiff did not accept this offer, and instead notified the defendants on March 14 that it had finally obtained the needed funds and could close on March 16. The defendants, however, refused to close.

The plaintiff then filed a “Motion to Cite for Contempt and Sanctions,” claiming that the defendants were in violation of the court’s order of specific performance. The motion asked the court to hold the defendants in contempt, levy sanctions against them, and make “appropriate enforcement orders.” The defendants objected to the motion, and a September hearing was scheduled. Just before the hearing, the plaintiff filed a motion to amend its previous motion. It alleged that, due to the defendants’ refusal to close, the plaintiff had lost its financing commitment and was unable to secure alternative funding. The motion ended with a prayer to vacate the court’s order of specific performance, re-open the case for a determination of damages, and order the defendants to refund the $150,000 deposit.

The court denied the plaintiff’s requests for relief, ruling that “[t]he plaintiff having conceded his financial inability to proceed on March 1, or at any reasonably certain time in the foreseeable future, such an admitted inability constituted a material breach justifying defendants’ termination of the agreement.” In reaching this conclusion, the court found that “the selection of March 1,1990 finalizing a transaction that commenced in December of 1984 and by any reasonable standard should have concluded, as originally scheduled, in December of 1985 was fair, just and appropriate under the circumstances.” It is noteworthy that the court found incredible the plaintiff’s assertion that it “was ready, willing and able to perform [its] obligations under the agreement from March 16, 1990, through September 1, 1990.”

Turning to the issue of liquidated damages, the court ruled enforceable the contract’s provision allowing forfeiture of “all deposits” upon the buyer’s breach, because:

“(1) the damages resulting from plaintiff’s breach are uncertain and difficult to prove; (2) there was an intent, by virtue of its inclusion in the agreement, on the part of the parties to liquidate such damages in advance; and (3) the [44]*44amount agreed upon (i.e. ‘all deposits’) was reasonable and not disproportionate to the presumable loss or injury. See Langlois v. Maloney, 95 N.H. 408, 412-413.”

“[A]ll deposits,” the court concluded, meant both $75,000 deposits.

On appeal, the plaintiff argues first that defendants’ position is tantamount to a collateral attack on the court’s original order for specific performance. We disagree, and hold instead that the plaintiff forfeited its right to specific performance by failing to tender payment within a reasonable time after the court’s order.

“Where the decree is that the purchaser shall receive a deed when he makes a tender of the price, but no time is fixed for such tender, a reasonable time is intended . . . .” 81A C.J.S. Specific Performance § 217, at 205 (1977); see also Lancaster v. Simmons, 621 S.W.2d 935, 943-44 (Mo. Ct. App. 1981) (when specific performance is ordered, successful party must timely tender performance; reasonable time is implied when court gives no deadline). “Where the party in whose favor the decree is rendered fails to perform a condition thereof on which the rights decreed depend, he is not entitled to enforce such rights against the opposite party and the latter is entitled to be relieved of the decree ....” 81A C.J.S. Specific Performance § 217, at 204 (1977); see also Delray Beach Whitehouse Apts., Inc. v. Hoffman, 257 So. 2d 550, 556 (Fla. 1972); Lancaster v. Simmons, supra at 944; Rosenstein v. Burr, 83 N.J. Eq. 491, 492-93, 90 A. 1037, 1038 (1914); Clark v. Hall, 7 Paige Ch. 382, 385 (N.Y. Ch. 1839); Bennett v. Copeland, 149 Tex. 474, 480, 235 S.W.2d 605

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mahmoud Chatila v. Charles Smith, III & a.
Supreme Court of New Hampshire, 2025
Miltner Insurance Services, LLC v. Roberts
Court of Appeals of Iowa, 2024
Peter Schmidt v. Steven Wolhandler
Supreme Court of New Hampshire, 2020
Holloway Automotive Group v. Steven Giacalone
154 A.3d 1246 (Supreme Court of New Hampshire, 2017)
Holloway Automotive Group v. Lucic
35 A.3d 577 (Supreme Court of New Hampshire, 2011)
In Re Market Center East Retail Property, Inc.
433 B.R. 335 (D. New Mexico, 2010)
Orr v. Goodwin
953 A.2d 1190 (Supreme Court of New Hampshire, 2008)
Barrie School v. Patch
933 A.2d 382 (Court of Appeals of Maryland, 2007)
TAL Financial Corp. v. CSC Consulting, Inc.
844 N.E.2d 1085 (Massachusetts Supreme Judicial Court, 2006)
General Linen Services, Inc. v. Franconia Investment Associates, L.P.
842 A.2d 105 (Supreme Court of New Hampshire, 2004)
Bair v. Axiom Design, L.L.C.
2001 UT 20 (Utah Supreme Court, 2001)
Guiliano v. Cleo, Inc.
995 S.W.2d 88 (Tennessee Supreme Court, 1999)
Guliano v. Cleo
Tennessee Supreme Court, 1999
O'BRIAN v. Langley School
507 S.E.2d 363 (Supreme Court of Virginia, 1998)
Kelly v. Marx
694 N.E.2d 869 (Massachusetts Appeals Court, 1998)
Nash Family Investment Properties v. Town of Hudson
660 A.2d 1102 (Supreme Court of New Hampshire, 1995)
Mattvidi Associates Ltd. Partnership v. Nationsbank of Virginia, N.A.
639 A.2d 228 (Court of Special Appeals of Maryland, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
599 A.2d 132, 135 N.H. 40, 1991 N.H. LEXIS 141, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shallow-brook-associates-v-dube-nh-1991.