Shaker v. Butler

2020 IL App (1st) 190967-U
CourtAppellate Court of Illinois
DecidedMarch 16, 2020
Docket1-19-0967
StatusUnpublished

This text of 2020 IL App (1st) 190967-U (Shaker v. Butler) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shaker v. Butler, 2020 IL App (1st) 190967-U (Ill. Ct. App. 2020).

Opinion

2020 IL App (1st) 190967-U

FIFTH DIVISION March 16, 2020 No. 1-19-0967

NOTICE: This order was filed under Supreme Court Rule 23 and may not be cited as precedent by any party except in the limited circumstances allowed under Rule 23(e)(1). ______________________________________________________________________________ IN THE APPELLATE COURT OF ILLINOIS FIRST DISTRICT ______________________________________________________________________________ AMANDA SHAKER and ADAM PETRZELKA, ) Appeal from the ) Circuit Court of Plaintiffs-Appellees, ) Cook County. ) v. ) ) No. 2017 L 7786 ) JAMES BUTLER d/b/a JIM BUTLER CONSTRUCTION ) and BUTLER CONSTRUCTION, INC., ) Honorable ) Yvonne Coleman, Defendants-Appellants. ) Judge, presiding.

JUSTICE DELORT delivered the judgment of the court. Presiding Justice Hoffman and Justice Rochford concurred in the judgment.

ORDER

¶1 Held: In this residential construction case, the court did not err in finding that defendant materially breached the contract’s “time is of the essence” clause, notwithstanding defendants’ contention that plaintiffs had waived that provision. However, a portion of the circuit court’s award of damages was not supported by competent evidence. We reduce the damages award and affirm the judgment as modified.

¶2 I. BACKGROUND

¶3 Amanda Shaker and her husband Adam Petrzelka (collectively “plaintiffs”) filed a one-

count verified complaint for breach of contract against James Butler and his construction company No. 1-19-0967

(collectively “Butler”). The complaint alleged that the plaintiffs incurred $33,651.17 in damages

when Butler failed to timely complete renovations on their house.

¶4 Butler filed a counterclaim, alleging that the plaintiffs breached the contract by terminating

him before he could finish the work. The circuit court referred the case to mandatory arbitration.

See Ill. S. Ct. R. 86 (eff. Jan. 1, 1994); Cook County Cir. Ct. R. 25.1 (Dec. 1, 2014). After the

arbitrator entered an award in Butler’s favor, plaintiffs timely rejected the award. Plaintiffs twice

moved to amend their complaint, seeking to add tort claims related to allegedly fraudulent

documents produced in discovery. However, the court did not rule on those motions before trial.

¶5 At trial, Petrzelka testified that he and Shaker purchased a house in Oak Park, Illinois and

entered a contract with Butler to renovate it. Butler was to be the general contractor and the

renovations were to include electrical and plumbing updates, removal of several walls, and other

upgrades. The contract, an unsigned copy of which was entered into evidence, included a start date

of November 15, 2016 and a substantial completion date of March 31, 2017. 1 The contract price

was $166,800, of which plaintiffs eventually paid a total of approximately $150,000.

¶6 Petrzelka testified that the plans called for certain windows to be bricked in. However,

Butler’s initial estimates did not include that work. Before the renovation began, Butler informed

Petrzelka that the masonry work would cost extra. Petrzelka also testified that, during the

renovations, plaintiffs decided that an additional wall should be removed, extra tile be installed,

and several doors should be replaced. Petrzelka did not know how much time these changes added

to the total project. There were no written “change orders” for these extra tasks.

1 In the contract, the substantial completion date is listed as “3-31-2016”. The parties agree that this is a scrivener’s error and that the intended date was March 31, 2017. 2 No. 1-19-0967

¶7 Petrzelka testified that on February 2, 2017, the house failed a walk-through inspection. To

remedy the issues, their architect had to draft new plans, which he completed by February 5. To

pass inspection, a support beam needed to be installed over a widened doorway. Petrzelka testified

that the failed inspection did not stop the renovation work. He testified that, between the time of

the failed inspection and the resolution of the beam issue, Butler connected the water supply and

installed windows and insulation.

¶8 The contract also included a clause stating that the “[t]ime limits stated in the Contract

Documents are of the essence of the Contract.” Petrzelka testified that the completion date was

important to plaintiffs because they were planning on selling their old house and moving directly

into the new one. Sometime after entering the contract with Butler, they listed and found a buyer

for their old house and set a closing date of April 13, 2017. Throughout the course of the

renovation, Butler repeatedly assured plaintiffs that he intended to meet the March 31 completion

date. Nevertheless, within a few weeks of the scheduled completion date, it became clear to

plaintiffs that the work would not be finished in time.

¶9 On April 3, 2017, three days after the scheduled completion date, Petrzelka requested an

“updated timeline” from Butler. Butler replied in an email that a crew of painters was meant to

start on April 10, and that the new target date was April 25. The email stated, in part, “I also know

I’m over the date I said in the beginning, not because you added work. It’s mainly because of

different trades taking a little longer than others that went faster than expected.” On April 8,

plaintiffs put most of their personal property into storage at a cost of about $125 per day.

¶ 10 Petrzelka testified that, despite Butler’s assurances that a “whole crew of painters” would

begin work on the house on April 10, when he visited the house that day, nobody was working.

3 No. 1-19-0967

By the end of that week, only a single painter had done any work on the property. Petrzelka

received another email from Butler stating that the painters would begin in earnest on April 17.

¶ 11 On the morning of April 17, Petrzelka again visited the house. He found that only two

painters were working and that they did not have any paint with them; they were simply filling

nail holes. He contacted Butler by text message and informed him that he had decided to terminate

the contract. Two days later, Shaker’s father, an attorney, sent a letter to Butler memorializing the

termination.

¶ 12 Petrzelka testified that a great deal of work remained to be done on the house after the

termination. Among other things, the unfinished work included painting, installing light fixtures

and electrical outlets, connecting appliances and air conditioning units, connecting the water and

installing plumbing fixtures, and finishing some windows. To complete that work, Petrzelka hired

various contractors, including painters, electricians, and plumbers, and performed some work

himself. Plaintiffs were finally able to move into the house on June 23, 2017, nearly three months

after the contractual substantial completion date.

¶ 13 Petrzelka testified that he hired other contractors and spent approximately 350 hours of his

own time to finish the renovations. He testified that “between what [he] paid the subcontractors

plus materials that [he] had purchased to finish the work was just over $33,000.” 2 He also testified

that the contract allotted $20,000 for “Basement Finish”. When asked whether “that project” was

completed, he answered, “It was not.” The only other testimony about the work done (or left

Free access — add to your briefcase to read the full text and ask questions with AI

Related

1472 N. Milwaukee, LTD. v. Feinerman
2013 IL App (1st) 121191 (Appellate Court of Illinois, 2013)
Razor v. Hyundai Motor America
854 N.E.2d 607 (Illinois Supreme Court, 2006)
Mohanty v. St. John Heart Clinic, S.C.
866 N.E.2d 85 (Illinois Supreme Court, 2006)
William Blair & Co. v. Fi Liquidation Corp.
830 N.E.2d 760 (Appellate Court of Illinois, 2005)
Ross v. Danter Associates, Inc.
242 N.E.2d 330 (Appellate Court of Illinois, 1968)
Hart v. Lyons
436 N.E.2d 723 (Appellate Court of Illinois, 1982)
Hamilton v. American Gage & MacHine Corp.
342 N.E.2d 758 (Appellate Court of Illinois, 1976)
First National Bank v. Shape Magnetronics, Inc.
481 N.E.2d 953 (Appellate Court of Illinois, 1985)
Castricone v. Michaud
583 N.E.2d 1184 (Appellate Court of Illinois, 1991)
Franzen v. Dunbar Builders Corp.
270 N.E.2d 118 (Appellate Court of Illinois, 1971)
Richardson v. Chapman
676 N.E.2d 621 (Illinois Supreme Court, 1997)
Ollivier v. Alden
634 N.E.2d 418 (Appellate Court of Illinois, 1994)
Battaglia v. 736 N. Clark Corp.
2015 IL App (1st) 142437 (Appellate Court of Illinois, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
2020 IL App (1st) 190967-U, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shaker-v-butler-illappct-2020.