Shafer Redi-Mix, Inc. v. Chauffeurs, Teamsters & Helpers Local Union 7

643 F.3d 473, 190 L.R.R.M. (BNA) 2961, 2011 U.S. App. LEXIS 9207, 2011 WL 1676069
CourtCourt of Appeals for the Sixth Circuit
DecidedMay 5, 2011
Docket09-2323
StatusPublished
Cited by4 cases

This text of 643 F.3d 473 (Shafer Redi-Mix, Inc. v. Chauffeurs, Teamsters & Helpers Local Union 7) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Shafer Redi-Mix, Inc. v. Chauffeurs, Teamsters & Helpers Local Union 7, 643 F.3d 473, 190 L.R.R.M. (BNA) 2961, 2011 U.S. App. LEXIS 9207, 2011 WL 1676069 (6th Cir. 2011).

Opinions

GIBBONS, J., delivered the opinion of the court, in which SARGUS, D.J., joined. KETHLEDGE, J. (p. 481), delivered a separate dissenting opinion.

OPINION

JULIA SMITH GIBBONS, Circuit Judge.

Plaintiff-appellant Shafer Redi-Mix, Inc. (“Shafer”) appeals the district court’s grant of summary judgment to defendantappellee Chauffeurs, Teamsters & Helpers, Local Union # 7 (“Local 7” or “the union”). Shafer alleges that Local 7 caused it to lose a construction contract by having one of its sister unions threaten to boycott the project unless Shafer, a nonunion employer, was replaced by a unionized supplier. The district court held that Shafer was unable to show that the boycott threat was the proximate cause of its removal because the subcontractor that hired Shafer acted on a competing concrete-supply bid to satisfy the general contractor’s long-standing desire to use a unionized supplier. For the following reasons, we affirm the district court’s decision.

I.

Clark Construction, Inc. (“Clark”) was the general contractor for the construction of the Firekeepers Casino Project in Battle Creek, Michigan. Clark subcontracted a portion of the casino project to Grand River Construction, Inc. (“Grand River”). In February 2008, Grand River solicited and received bids for “redi-mix” concrete from two subcontractors, Shafer and Consumers Concrete (“Consumers”). According to Grand River’s project manager, Bradley Foster, Shafer was selected as the concrete supplier because its bid was lower than that of Consumers.

About a week after Grand River submitted its bid to Clark in early February [475]*4752008, there was an initial proposal meeting between Clark and Grand River in which Foster and William Kersaan, owner of Grand River, participated. During this meeting, Duane Wixson, Clark’s project manager, told Kersaan and Foster that “[tjhere would be union trade problems” with the project. Foster testified at his deposition that, at the time Grand River chose Shafer, Shafer knew “[t]hat it was questionable whether [Grand River] could use them on the job.” Wixson testified that he was concerned that the project would have to be dual-gated, meaning that Clark would have to maintain one gate for union employees and another for non-union workers.

The project was covered by a Project Labor Agreement (“PLA”) that contained a no-picketing provision, which read, in relevant part:

During the existence of this Agreement, the Unions shall not permit nor shall they participate in any strike, picketing, hand-billing, public notices, slowdown, withholding of work, refusal to work ... or other work stoppage of any type or any interference with the work of the contractor(s), owner, or others related in any manner to the Project to occur, for any reason by the Union or the Employees against any Contractor covered under this agreement on this Project and there shall be no lock-out by the Contractor.

Local 7 signed the PLA at a pre-job conference in early May 2008 as did Shafer Group, LLC, the entity used by Shafer to pay wages and benefits to employees. During the conference, an unidentified representative of Local 7 expressed reservations about Grand River’s choice of Shafer, a non-union contractor and said that he would rather have Consumers supply concrete for the project. When Foster offered Clark the option of using Consumers, Wixson did not instruct Foster to make a change. On May 20, 2008, Shafer submitted its designs for the concrete mix to be used on the project to Grand River in preparation for the concrete pour. However, Clark still had reservations about Shafer’s participation and did not approve the mix design.

On May 21, 2008, Wixson received a telephone call from three union representatives, including Tom Harty of Local 7 and A1 Sprague of a sister union, Local 164 of Jackson, Michigan. During the call, Harty asked Wixson why Consumers had not been awarded the contract, and Wixson replied that Consumers’s bid was higher than that of Shafer. The union representatives repeated Local 7’s concerns about the use of a non-union contractor and, according to Wixson, one of the representatives indicated that if Shafer remained on the project, there could be a labor disruption because Local 164 could picket the project. At his deposition, Wixson recalled that he reminded the union representatives of the no-picketing clause of the PLA and explained that although Local 164 was not bound by the PLA, he “was making no distinction between the Jackson local and any other local.” Harty said that Local 7 would abide by the PLA, but Sprague did not make that promise. Wixson testified that he spoke only with Clark’s project superintendent, Ken Stevenson, about the call and did not recall discussing it with anyone else, including Grand River.

After his call with Wixson, but on the same day, Harty called Foster to confirm that Consumers’s higher bid was the factor that prevented it from winning the contract. Harty offered to speak with Tom Thomas, the CEO of Consumers, about the price discrepancy. Thomas testified that, upon receiving Harty’s call, he understood for the first time that there was a price [476]*476discrepancy between the Consumers bid and Shafer’s. He called Foster and told him that he would investigate the discrepancy. Thomas called Foster again later that day and explained that Consumers had submitted two sets of bids — one that reflected the price of concrete mixed to the full specifications of the architects and another, lower price, that reflected Consumers’s assessment of what the project would actually require. Foster agreed that, in light of Thomas’s explanation, there was no price discrepancy between the two bids. Because Consumers had a longstanding relationship with Grand River as a “preferred supplier,” Thomas offered to match Shafer’s price. Foster instructed Thomas to resubmit a revised bid and to provide specifications for the concrete so that Foster could send them to Clark “as soon as possible.” Foster testified that by telling Thomas to resubmit his bid and create the concrete specifications, he was effectively awarding Consumers the contract and told Consumers to prepare for the concrete pour during the following week.

The next day, Consumers submitted a revised bid and concrete mix specification. The final decision to remove Shafer from the project was made by Foster, Kersaan, and another Grand River officer after they received the revised bid. Kersaan testified that he was not aware of the call between Wixson and the union representatives at the time Grand River decided to switch suppliers. However, he knew from prior conversations with Clark that the general contractor wanted Grand River to make a change to promote labor harmony. Although Foster recommended staying with Shafer, Kersaan decided that “if Clark wanted it switched we would go to Consumers.” Foster testified that Grand River wanted a letter from Clark stating that it wanted Shafer off the project, which Clark eventually provided on May 29, 2008. The letter stated that it was Clark’s “desire to promote labor harmony” on the project that led it to “prefer[] that the concrete supplier be unionized.”

Shafer then filed suit in federal district court, alleging that Local 7 violated 29 U.S.C. § 158(b)(4) by engaging in an illegal secondary boycott whereby the union threatened to picket Clark, a neutral employer, unless Grand River removed Shafer from the project. Shafer sought $650,000 in damages.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
643 F.3d 473, 190 L.R.R.M. (BNA) 2961, 2011 U.S. App. LEXIS 9207, 2011 WL 1676069, Counsel Stack Legal Research, https://law.counselstack.com/opinion/shafer-redi-mix-inc-v-chauffeurs-teamsters-helpers-local-union-7-ca6-2011.