Settle-Muter Elec. Ltd. v. Intertech Sec., LLC

2018 Ohio 4839, 125 N.E.3d 279
CourtOhio Court of Appeals
DecidedDecember 6, 2018
Docket17AP-787
StatusPublished
Cited by1 cases

This text of 2018 Ohio 4839 (Settle-Muter Elec. Ltd. v. Intertech Sec., LLC) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Settle-Muter Elec. Ltd. v. Intertech Sec., LLC, 2018 Ohio 4839, 125 N.E.3d 279 (Ohio Ct. App. 2018).

Opinion

KLATT, J.

{¶ 1} Defendants-appellants, Dunlop & Johnston, Inc. ("Dunlop") and Fidelity and Deposit Company of Maryland ("Fidelity"), appeal a judgment of the Franklin County Court of Common Pleas that granted in part and denied in part Dunlop and Fidelity's motion to stay the proceedings pending arbitration. For the following reasons, we affirm the trial court's judgment.

{¶ 2} In December 2014, the Columbus City Schools hired Dunlop to serve as the general contractor for the construction of the Columbus Africentric Early College K12 School. 1 On January 20, 2015, Dunlop and Intertech Security, LLC ("Intertech") entered into a contract in which Intertech agreed to perform the electrical work for the school construction project and Dunlop agreed to pay Intertech a specified sum for that work. That contract contained an arbitration provision, which in relevant part stated:

Any and all claims, disputes, controversies, demands, and causes of action of whatever nature, kind or description arising from or relating to this Agreement, including without limitation contract, equity, tort or legal claims, and further including without limitation claims relating to rights of payment or interpretations hereof, between [Dunlop] and [Intertech] that are not resolved, as provided for in this Agreement, shall be subject to mandatory and binding arbitration, governed by RC Chapter 2711 and the Construction Industry Arbitration Rules of the American Arbitration Association.

(Ex. A, Mot. to Stay Pending Arbitration, at Article 34.)

{¶ 3} After Intertech secured its position as the electrical subcontractor on the school construction project, it hired Wood & Sons Electric, LLC ("Wood") to perform a portion of the electrical work. Wood's work, however, proved unsatisfactory, so Intertech asked plaintiff-appellee, Settle-Muter Electric Ltd. ("SME"), to replace Wood and perform the work originally allocated to Wood. SME refused. Dunlop then approached SME and promised that: (1) it would oversee administration of the submissions of SME's applications for payment to the Columbus City Schools; (2) it would ensure that SME would be paid on time every month for all work it performed; (3) SME would not have to correct any of Wood's completed work, which included the installation of wiring, boxes, fixture mounts, and subpanels; (4) SME would not be penalized for any additional work required due to Wood's unworkmanlike work; and (5) SME would report directly to Dunlop regardless of any contract. 2

{¶ 4} Based on these representations, SME agreed to undertake the work and become a second-tier subcontractor on the school construction project. On August 21, 2015, Intertech and SME entered into contract setting forth the scope of SME's work and the amount Intertech would pay SME for that work. Intertech, however, did not comply with the contractual terms governing payment for SME's work. SME sought recourse from Dunlop, which assured SME that it would pay SME for its work. 3

{¶ 5} Ultimately, according to SME, Intertech wrongfully withheld and failed to pay SME $466,933.11. SME filed and served claims against Dunlop's payment bond and Intertech's payment bond. Both Dunlop and Intertech refused to pay SME the money SME claimed was due and owed to it.

{¶ 6} On May 3, 2017, SME filed suit against Intertech and Dunlop, as well as RLI Insurance Company ("RLI"), which issued Intertech a payment bond, and Fidelity, which issued Dunlop a payment bond. Against Intertech, SME asserted claims for breach of contract, breach of the duties of good faith and fair dealing, breach of express and implied warranties, "unjust enrichment/quantum meruit," "fraud in the inducement/promissory fraud," and violation of the Prompt Payment Act, R.C. 4113.61. (Compl. at 9, 10.) Against Dunlop, SME asserted claims for breach of express and implied warranties, "unjust enrichment/quantum meruit," "fraud in the inducement/promissory fraud," and violation of the Prompt Payment Act, R.C. 4113.61. Id. Against RLI and Fidelity, SME sought recovery from the payment bonds.

{¶ 7} All defendants answered the complaint. Additionally, Intertech filed a counterclaim against SME and a cross-claim against Dunlop. In the counterclaim, Intertech contended that SME had breached its contract with Intertech by refusing to complete all the contracted-for work, which forced Intertech to hire another contractor to do the work. Intertech also alleged that SME engaged in fraud when it misrepresented that (1) it had completed 100 percent of the contracted-for work, and (2) Intertech had approved a proposed change order that increased the contract price by $227,390.63. In the cross-claim, Intertech alleged that Dunlop owed it $764,109.84 for its work on the school construction project. Based on this allegation, Intertech asserted against Dunlop claims for breach of contract and violation of the Prompt Payment Act, R.C. 4113.61.

{¶ 8} On July 31, 2017, Dunlop and Fidelity moved pursuant to R.C. 2711.02(B) to stay all proceedings pending arbitration. In a judgment issued October 11, 2017, the trial court granted a stay of the litigation of Intertech's cross-claim against Dunlop, but denied a stay of the remainder of the proceedings.

{¶ 9} Dunlop and Fidelity (hereinafter "appellants") now appeal the October 11, 2017 judgment, and they assign the following error:

The trial court erred as a matter of law in denying Appellants' Motion to Stay Proceedings in Part and failing to stay all claims and proceedings pending mandatory and binding arbitration between two of the parties, in accordance with Ohio Revised Code § 2711.02(B) and Ohio law.

{¶ 10} The standard under which a court of appeals reviews a judgment granting or denying a stay pending arbitration depends on the nature of the issues involved. Hunter v. Rhino Shield , 10th Dist. No. 15AP-172, 2015-Ohio-4603 , 2015 WL 6779395 , ¶ 17 ; accord Peters v. Columbus Steel Castings Co. , 10th Dist. No. 05AP-308, 2006-Ohio-382 , 2006 WL 225274 , ¶ 10, aff'd 115 Ohio St.3d 134 , 2007-Ohio-4787 , 873 N.E.2d 1258 (recognizing that courts of appeals have traditionally applied the abuse-of-discretion standard to judgments ruling on a motion to stay pending arbitration, but concluding that the de novo standard is appropriate when the appeal of a judgment granting or denying a stay presents a question of law). This appeal turns on the interpretation of R.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Newton v. U.S. Bancorp Invest., Inc.
2023 Ohio 1450 (Ohio Court of Appeals, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
2018 Ohio 4839, 125 N.E.3d 279, Counsel Stack Legal Research, https://law.counselstack.com/opinion/settle-muter-elec-ltd-v-intertech-sec-llc-ohioctapp-2018.