Senior Citizens Coalition of Northeastern Minnesota v. Minnesota Public Utilities Commission

355 N.W.2d 295, 1984 Minn. LEXIS 1456, 1984 WL 914466
CourtSupreme Court of Minnesota
DecidedSeptember 7, 1984
DocketC9-83-982, C9-83-1047
StatusPublished
Cited by15 cases

This text of 355 N.W.2d 295 (Senior Citizens Coalition of Northeastern Minnesota v. Minnesota Public Utilities Commission) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Senior Citizens Coalition of Northeastern Minnesota v. Minnesota Public Utilities Commission, 355 N.W.2d 295, 1984 Minn. LEXIS 1456, 1984 WL 914466 (Mich. 1984).

Opinion

SCOTT, Justice.

Two cases have been consolidated for disposition on this appeal. Both cases arose out of Minnesota Power & Light Company’s (MPL) 1981 application for a rate increase. Each case involves an appeal from a judgment entered in Ramsey County District Court, affirming a decision of the Minnesota Public Utilities Commission (PUC).

In C9-83-1047, MPL appeals from that part of the PUC’s decision which excluded from the rate base MPL’s investment in recreational facilities which are being constructed at certain hydroelectric projects pursuant to licensing requirements of the Federal Energy Regulatory Commission (FERC). 1 In C9-83-982, the Senior Citizens Coalition of Northeastern Minnesota appeals from that part of the PUC’s decision denying its request for intervenor compensation. We affirm in C9-83-982, but reverse in C9-83-1047. Because each case raises distinct issues, they will be discussed separately below.

I. 09-83-1047.

MPL operates hydroelectric facilities located on navigable waters in Blanchard, Winton, and Island Lake, Minnesota. To construct and operate those facilities, MPL had to obtain a license from the FERC, which has exclusive jurisdiction under the Federal Power Act to license hydroelectric facilities on navigable waters and to set standards for the licensing process. See 16 U.S.C. § 803 (1983); Town of Springfield v. McCarren, 549 F.Supp. 1134, 1156-57 (D.Vt.1982), affd by order, 722 F.2d 728 (2d Cir.1983), cert. denied, — U.S. —, 104 S.Ct. 360, 78 L.Ed.2d 322 (1983); see generally 2 A. Priest, Principles of Public Utility Regulation 613-39 (1969). In applying for such a license, MPL was required to file a suitable plan for project recreational facilities. That plan was identified as “Exhibit R” of the application. 2 Forrest L. Ludsen, a company witness, testified that the recreational “facilities become project facilities by incorporation” of that exhibit into the license 3 and that “[t]he license requires that the project area and work must be in substantial conformity with the approved exhibit.”

Federal regulations, as well as decisions by the FERC, establish a licensee’s duty to develop the planned recreational facilities. According to federal regulations, the FERC expects the licensee to assume responsibility for developing “suitable public recreational facilities upon project lands and waters.” 18 C.F.R. § 2.7(b) (1983). 4 Mean *299 while, the FERC has held that a licensee has ultimate responsibility for recreational development and that it retained sole authority to determine, upon a licensee’s petition, “whether a particular level of [recreational] demand attained is or is not adequate to justify proceeding with the planned development.” Public Utility District No. 1 of Chelan County, Washington, 56 Fed. Power Comm. 787, 789 (1976).

In May of 1981, MPL petitioned for a rate increase. It sought to include in the rate base, as part of its investment in the three hydroelectric plants, the cost of constructing the public recreational facilities described in the license application for each plant. The Office of Consumer Services objected to including that investment in MPL’s rate base on the ground that such facilities were not “used and useful in rendering service” within the meaning of Minn.Stat. § 216B.16, subd. 6 (1982). 5 MPL countered that its investment in the recreational facilities was properly includa-ble in the rate base because such facilities are a condition of the license under which it operates the hydroelectric plants and, therefore, they are necessarily “used and useful.”

The hearing examiner agreed with MPL and recommended that MPL be allowed to include that investment in its rate base. The PUC reversed the hearing examiner, ruling that federal law did not compel inclusion of that investment in the rate base and that the recreational facilities were not “used and useful.” On appeal, the Ramsey County District Court affirmed the PUC’s decision, ruling that substantial evidence supported its conclusion. MPL appeals to this court, challenging the PUC’s failure to include the costs of constructing the recreational facilities in its rate base. We reverse.

Since MPL is attempting to have its retail ratepayers pay for the costs of constructing recreational facilities which are required as a condition of the hydroelectric license granted by the FERC, this case involves the interaction of the federal and state spheres in utility regulation. ■ It is well established that the FERC has plenary jurisdiction over regulating wholesale interstate transactions, while state utilities commissions retain authority to regulate intrastate retail rates. See Federal Power Commission v. Southern California Edison Co., 376 U.S. 205, 214-15, 84 S.Ct. 644, 650-51, 11 L.Ed.2d 638 (1964); Public Utilities Commission of Rhode Island v. Attleboro Steam & Electric Co., 273 U.S. 83, 47 S.Ct. 294, 71 L.Ed. 54 (1927). This court recently applied those principles in Northern States Power Co. v. Minnesota Public Utilities Commission, 344 N.W.2d 374 (Minn.), cert. denied, — U.S. —, 104 S.Ct. 3546, 82 L.Ed.2d 850 (1984). There, we held that a FERC decision established a wholesale interstate rate and, therefore, the PUC had no power to reexamine the reasonableness of that FERC-approved rate. Id. at 377, 382. As a result, even though the FERC-approved rate did “not directly establish the return for retail rates,” the PUC was required to accept the FERC-approved rate as establishing expenses for purchased power in determining intrastate retail rates. Id. at 382.

The instant case, however, does not involve an interstate wholesale rate established by the FERC. Rather, the question presented here is whether the PUC must include in the intrastate rate base costs incurred as a condition of the hydroelectric license granted by the FERC. As MPL concedes, the PUC correctly ruled that this question must be resolved under state law standards.

*300 Under section 216B.16, subd. 6, a utility is entitled to a reasonable return on its investment in “property used and useful in rendering service to the public.” The PUC excluded MPL’s investment in the recreational facilities from the rate base, ruling that those facilities were not “used and useful” because:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sierra Club v. Public Utilities Commission
Court of Appeals of Minnesota, 2026
Waters-Haskins v. New Mexico Human Services Department
2009 NMSC 031 (New Mexico Supreme Court, 2009)
Matter of Interstate Power Rates Change Request
574 N.W.2d 408 (Supreme Court of Minnesota, 1998)
Axelson v. Minneapolis Teachers' Retirement Fund Ass'n
544 N.W.2d 297 (Supreme Court of Minnesota, 1996)
Petition of Minnesota Power & Light Co.
435 N.W.2d 550 (Court of Appeals of Minnesota, 1989)
Otter Tail Power Co. v. Minnesota Public Utilities Commission
417 N.W.2d 677 (Court of Appeals of Minnesota, 1988)
Application of Peoples Natural Gas Co.
413 N.W.2d 607 (Court of Appeals of Minnesota, 1987)
Application of Northwestern Bell Telephone
374 N.W.2d 758 (Court of Appeals of Minnesota, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
355 N.W.2d 295, 1984 Minn. LEXIS 1456, 1984 WL 914466, Counsel Stack Legal Research, https://law.counselstack.com/opinion/senior-citizens-coalition-of-northeastern-minnesota-v-minnesota-public-minn-1984.