Matter of Interstate Power Rates Change Request

574 N.W.2d 408
CourtSupreme Court of Minnesota
DecidedJanuary 8, 1998
DocketC1-96-1558
StatusPublished
Cited by3 cases

This text of 574 N.W.2d 408 (Matter of Interstate Power Rates Change Request) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Matter of Interstate Power Rates Change Request, 574 N.W.2d 408 (Mich. 1998).

Opinion

[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 410

Syllabus by the Court

1. The MPUC did not exceed its statutory authority when it applied the "used and useful" standard of Minn.Stat. § 216B.16 , subd. 6 (1996), to the time of pollution and thus allowed rate recovery for cleanup costs of former manufactured gas plant sites.

2. The MPUC did not exceed its statutory authority by concluding that there was a sufficient nexus between manufactured gas and natural gas to support cost recovery from the current natural gas customers.

3. The MPUC determination that the manufactured gas plant sites were actually "used and useful" at the time of pollution was supported by substantial evidence in the record.

OPINION

At issue here is whether the Minnesota Public Utilities Commission (MPUC) had the authority to order rate recovery from Interstate Power Company's (Interstate) current natural gas customers for cleanup costs of two former manufactured gas plant sites not currently used or useful for the provision of utility service. The Administrative Law Judge (ALJ) recommended that Interstate be allowed to recover one-half of the cleanup costs from its current natural gas customers. The MPUC affirmed the findings and conclusions of the ALJ, but modified the recommendation to provide full recovery of the cleanup costs for Interstate. The court of appeals affirmed the MPUC order, rejecting appellants' argument that "used and useful" applied to the time of the rate case rather than the time of pollution, and held that the MPUC acted in a legislative capacity and did not exceed its statutory authority when it determined that rate recovery was allowed if the property was used and useful at the time of pollution. The court of appeals also held that the MPUC acted in a quasi-judicial capacity when it determined that the sites at issue were, in fact, used and useful at the time of pollution, and that there was substantial evidence supporting that determination. In re Request of Interstate Power Co. forAuthority to Change its Rates for Gas Service, 559 N.W.2d 130 (Minn.App. 1997). We affirm the court of appeals.

Manufactured gas is a form of energy that was used from the late 1800s until the 1930s, when natural gas became available. It was produced by the incomplete combustion of coal and sometimes oil to produce a synthetic combustible gas that was piped from the plant site to customers for use in heating, cooking, and lighting. The manufacturing process produced residual products, including coal tar, that were frequently deposited in on-site lagoons or underground wells or pits — a method of disposal considered safe at the time. In the early 1980s the Environmental Protection Agency declared this coal tar waste a hazardous substance and began requiring current and former owners of the sites to clean up the contamination. In the early 1990s, the Minnesota Pollution Control Agency (MPCA) determined Interstate to be at least partially responsible for the cleanup of five manufactured gas plant sites in Minnesota, including plant sites in Albert Lea and Rochester, under the Comprehensive and Environmental Response Compensation *Page 411 and Liability Act (CERCLA), 42 U.S.C. § 9601-9675 (1996), the Superfund Amendments and Reauthorization Act (SARA), id., and the Minnesota Environmental Response and Liability Act (MERLA), Minn.Stat. Ch. 115B (1996). At issue here are the cleanup costs of Interstate's former manufactured gas plant sites in Albert Lea and Rochester, Minnesota.

The Albert Lea plant began manufacturing gas in 1903 under a different owner. Interstate acquired the plant in 1925 and manufactured gas at that site until 1933. When natural gas became available, Interstate ceased production of manufactured gas. The site was thereafter used as a vehicle maintenance garage and transformer repair facility until 1950, and then from 1950 to 1978 as a fuel oil storage yard for Interstate's adjacent electric plant. Part of the Albert Lea site where the manufactured gas storage containers were located was sold in 1984, but Interstate continues to own the remaining property and currently uses it as part of its underground gas and utility lines distribution system. In 1992, the MPCA concluded that the soil and groundwater at the Albert Lea site were contaminated and cleanup was required. Interstate is in the early stages of the cleanup. It has incurred investigation costs of $494,735 through March 1995; future cleanup costs are unknown. Interstate provides natural gas utility service to the Albert Lea area.

The manufactured gas plant in Rochester began operating in 1888 and Interstate purchased the company in 1925. When natural gas became available in Rochester in 1932, Interstate ceased manufacturing gas at the site and leased the gas plant and property to Minnesota Northern Natural Gas. In 1948, Interstate sold the plant and land to Peoples Natural Gas, the current owners of part of the land; the City of Rochester owns the remaining property. After soil contamination was discovered in the early 1990s and cleanup was ordered, Interstate, Peoples Natural Gas, and the City of Rochester executed a series of agreements to share the costs. Cleanup of the Rochester site is near completion, and Interstate has incurred costs of $5,422,363 through March 1995. Interstate no longer provides any utility service in Rochester.

As a public utility, Interstate's electric and gas rates are regulated by the MPUC under Minn.Stat. Ch. 216B (1996). In reviewing rate changes, the MPUC's charter is broadly defined in terms of balancing the interests of the utility companies, their shareholders, and their customers to ensure that rates are "just and reasonable." Minn.Stat. § 216B.16, subd. 6.

In July 1994, Interstate filed a petition with the MPUC seeking approval of deferred accounting for the cleanup costs associated with the Rochester and Albert Lea manufactured gas plants. A deferral allows the utility to seek rate recovery of the deferred expenses in its next gas and electric rate cases. The MPUC granted the petition deferring the accounting for the cleanup costs, but denied recovery of the cleanup costs from Interstate's electric customers, stating that the costs "are associated with the provision of gas service [and] [t]here is no nexus between costs of remediation of MGP [manufactured gas plant] sites and the provision of electric service." The MPUC allowed Interstate to defer the cleanup costs and request rate recovery from gas customers in its next general gas rate case.

On May 1, 1995, Interstate filed a general rate case with the MPUC requesting a rate increase of $2,365,280, 25 percent ($594,898) attributable to the mandated cleanup of the two former manufactured gas plants. The Department of Public Services and the Office of the Attorney General (Appellants) intervened in the case and argued against rate recovery for the former manufactured gas plant cleanup on two grounds: first, the sites must be used and useful at the time of the rate case, not the time of pollution; second, there was an insufficient nexus between manufactured gas and natural gas to support the cost recovery against the current natural gas customers.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
574 N.W.2d 408, Counsel Stack Legal Research, https://law.counselstack.com/opinion/matter-of-interstate-power-rates-change-request-minn-1998.